ASBESTOS HAZARD EMERGENCY RESPONSE ACT (AHERA) SURVEILLANCE REQUIREMENT
At least once every six months following the implementation of the AHERA management plan, an LEA must conduct a periodic visual
surveillance of asbestos containing building material (ACBM) and assumed ACBM in each building which they lease, own, or otherwise use
as a school building (Section 763.92(b)). The name of the person performing the surveillance, the date, and any changes noted in the condition of
the asbestos must be recorded for each surveillance conducted (Section 763.94(d)).
Although a periodic surveillance may coincide with the upcoming triennial AHERA reinspection, keep in mind that a surveillance
cannot serve as the triennial reinpsection (Section 763.85(b)). The following chart
illustrates the major causes for this distinction.
Periodic Six Month Surveillance Triennial Reinspection
May be performed by anyone. Must be performed by a New York State Certified
Inspector/Management Planner.
Visual inspection only of ACBM. The Inspector must "look at and touch asbestos containing
material to assess its condition."
Should you have questions regarding the AHERA surveillance or triennial reinspection, you may contact your local BOCES Health and
Safety Office.