Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/19/09 at 17:00:09




WEST PARK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-02-02-02
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Maintenance Storage Building:
00-0188DB Discovered Building          2-010-001  09/21/09     DONE    DONE       DONE      08/22/00     /  /     07/24/00     /  /                                    0             0  BJB             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




KINGSTON CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-06-00-01
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Frank T. Meagher Elementary:
05-1095   Reconstruction               0-001-008  06/12/06     DONE    DONE       DONE      04/10/06   04/07/06   02/16/06   05/05/05   155                      108,973       108,973  JOD             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
08-0845   Reconstruction               0-001-009  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,8,16                   125,000             0  JOD             0           0       35,500
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Sophie Finn Elementary School:
07-0931   Reconstruction               0-002-010  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/17/06   03/20/07   8                        694,000             0  JOD             0           0      197,096
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1801   Reconstruction               0-002-011  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07                            741,976       437,500  JOD             0           0      210,721
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          John F. Kennedy Elem School:
07-0932   Reconstruction               0-003-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   8                        125,000             0  JOD             0           0       35,500
                                                                                                                                                                                                                                 Collins & Scoville Architects       
08-0846   Reconstruction               0-003-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/09/08   03/20/07   2,7,8,155,15,16        1,932,500             0  JOD             0           0      548,830
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          George Washington School:
07-0933   Reconstruction               0-004-008  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,8,9,13,14,15,16        860,000       860,000  JOD             0           0      244,240
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1802   Reconstruction               0-004-009  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07   7                        677,421       600,000  JOD             0           0      192,387
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Myron J. Michael Building:
05-1096   Reconstruction               0-005-010  06/12/06     DONE    DONE       DONE      04/10/06   04/07/06   02/16/06   05/05/05   155                      112,785       112,785  JOD             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-0934   Reconstruction               0-005-011  07/24/08     DONE    DONE       DONE      11/23/07   11/21/07     /  /     03/20/07                            575,800             0  JOD             0           0      163,527
                                                                                                                                                                                                                                 Collins & Scoville Architects       
  -       Reconstruction               0-005-012                                              /  /       /  /     07/30/07     /  /     2,4,7,8,9,10,14,15,1           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Kingston High School:
07-0935   Reconstruction               0-006-014  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,8,9,15,16        1,058,000             0  JOD             0           0      300,472
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1803   Reconstruction               0-006-015  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07   7                        819,000             0  JOD             0           0      232,596
                                                                                                                                                                                                                                 Collins & Scoville Architects       
  -       Reconstruction               0-006-016                                              /  /       /  /     02/06/09     /  /     10                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Vocational Bldg(Whiston Bldg.):
07-0936   Reconstruction               0-007-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   155,16                    75,600             0  JOD             0           0       21,470
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Kate Walton Field House:
07-0937   Reconstruction               0-008-010  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   7                        446,000             0  JOD             0           0      126,664
                                                                                                                                                                                                                                 Collins & Scoville Architects       
06-1244   Reconstruction               0-008-011  06/20/07     DONE    DONE       DONE      03/29/07   03/28/07   03/05/07   05/15/07   2,7                      358,344       358,344  JOD             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Chambers Elementary:
08-0847   Reconstruction               0-009-010  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/08   7,8,155,16             1,437,500             0  JOD             0           0      408,250
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          eeea Devine School:
07-0938   Reconstruction               0-010-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   2,8                      387,500             0  JOD             0           0      110,050
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1804   Reconstruction               0-010-006  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07   7                        874,276       662,500  JOD             0           0      248,294
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Louis A Salzmann Bldg.:
07-0939   Reconstruction               0-011-006  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   9,16                     589,000             0  JOD             0           0      167,276
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Robert Graves Ptbldg:
  -       Reconstruction               0-012-002                                              /  /       /  /     02/17/06     /  /     8,155                          0       279,266  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Ernest C. Myer Elementary:
08-0848   Reconstruction               0-013-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/08   8                        957,500             0  JOD             0           0      271,930
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Edward R.Crosby Elementary:
05-1097   Reconstruction               0-014-006  06/12/06     DONE    DONE       DONE      04/10/06   04/07/06   02/17/06   05/05/05   2,8,155                  107,780       107,780  JOD             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
08-0849   Reconstruction               0-014-007  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,7,8,16               1,314,000             0  JOD             0           0      373,176
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Robert Graves Elem. School:
07-0940   Reconstruction               0-016-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,9,15,16            220,000             0  JOD             0           0       62,480
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1805   Reconstruction               0-016-006  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07   7                      1,005,070       819,000  JOD             0           0      285,440
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Tobin Learning Center:
07-0941   Reconstruction               0-017-004  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   155,16                    74,000             0  JOD             0           0       21,016
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          J. Watson Bailey Jr High proj.advent:
06-0235   Alterations                  0-026-007  09/21/06     DONE    DONE       DONE      07/05/06   07/05/06     /  /       /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0942   Reconstruction               0-026-008  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   07/30/07   03/20/07   2,4,7,8,9,10,155,15,   1,130,994             0  JOD             0           0      321,202
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1806   Reconstruction               0-026-009  05/01/08     DONE    DONE       DONE      03/15/08   03/14/08   01/30/08   03/20/07   7                      2,839,382     1,227,600  JOD             0           0      806,385
                                                                                                                                                                                                                                 Collins & Scoville Architects       
08-0850   Reconstruction               0-026-010  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/09/08   03/20/07   2,8,155,16             2,000,000             0  JOD             0           0      568,000
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Harry L. Edson Elem. School:
07-0943   Reconstruction               0-027-005  07/03/08     DONE    DONE       DONE      11/23/07   11/21/07   02/16/06   03/20/07   8                        665,000             0  JOD             0           0      188,860
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          M. Clifford Miller Middle:
08-0851   Reconstruction               0-028-008  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   02/16/06   03/20/07   8                      1,487,500             0  JOD             0           0      422,450
                                                                                                                                                                                                                                 Collins & Scoville Architects       
06-0236   Alterations                  0-028-009  09/21/06     DONE    DONE       DONE      07/05/06   07/05/06     /  /       /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Zena Elementary:
08-0852   Reconstruction               0-031-005  05/19/09     DONE    DONE       DONE      12/03/08   12/01/08   07/30/07   03/20/07   2,7,8,15,16              412,500             0  JOD             0           0      117,150
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Carnegie Learning Center:
09-0380   Reconstruction               0-041-001               STARTED STARTED    UNREVIEWED11/02/09   11/02/09     /  /     11/19/08   2,4,7,8,9,10,14,155,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                 KSQ Architects,P.C                  

          Central Administration:
  -       Reconstruction               1-029-005                                              /  /       /  /     02/16/06     /  /     9,155                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Buildings and Grounds Dept. Leased:
07-1066TQ Temporary Quarters           1-048-001  01/25/08     DONE    DONE       DONE      12/06/07   11/27/07   10/17/07     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Carnegie Library Annex:
  -       Additions and Alterations    6-041-002                         UNREVIEWED         11/03/09   11/02/09   05/14/09   11/19/08   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 KSQ Architects,P.C                  
09-0119PR Additions and Alterations    6-041-002  09/22/09     DONE    DONE       DONE      08/12/09   08/11/09   05/14/09   11/19/08   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 KSQ Architects,P.C                  

          Gray Building:
  -    TQ Temporary Quarters           8-049-001                                              /  /       /  /     11/10/09     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HIGHLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-08-03-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
07-1102   Reconstruction               0-001-003  01/11/08     DONE    DONE       DONE      12/12/07   12/11/07   06/19/07   10/30/07   4,7,8,16                 198,116       156,000  JOD             0           0       49,920
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-2019   Reconstruction               0-001-004  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,4,8,10,16              299,635       650,000  JOD             0           0       66,010
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Junior/Senior High School:
05-0158   Reconstruction               0-009-006  09/30/05     DONE    DONE       DONE      08/29/05   08/25/05   07/22/05   05/17/05   155                       51,177        51,177  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1103   Reconstruction               0-009-007  01/11/08     DONE    DONE       DONE      12/12/07   12/11/07   06/19/07   10/30/07   7,8,9,155,15,16          502,449       504,000  JOD             0           0      160,281
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-2020   Reconstruction               0-009-008  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,8,10,155,16            797,317       530,000  JOD             0           0      178,227
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Elementary School:
07-1104   Reconstruction               0-010-007  01/11/08     DONE    DONE       DONE      12/12/07   12/11/07   06/19/07   10/30/07   4,7,8,155,15,16          258,315       322,400  JOD             0           0       82,402
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-2021   Reconstruction               0-010-008  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   02/04/08   10/30/07   2,4,8,10,155,16          444,168       444,168  JOD             0           0       85,813
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage:
07-2022   Reconstruction               5-002-004  11/24/08     DONE    DONE       DONE      04/24/08   04/16/08   06/19/07   10/30/07   2,7,15                         0       100,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-2106   Reconstruction               5-002-005  05/12/08     DONE    DONE       DONE      05/08/08   05/07/08   08/20/07     /  /     2,15                     124,406       124,406  JOD             0           0            0
                                                                                                                                                                                                                                 Chazen Engineering & Land Surveying 


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RONDOUT VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-09-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Rondout Valley High:
08-0285PR Additions and Alterations    0-002-007                         UNREVIEWED         09/09/08   09/04/08   01/10/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
08-0593   Additions and Alterations    0-002-007  05/14/09     DONE    DONE       DONE      10/24/08   10/22/08   01/10/06   10/21/07   02 - 16               25,736,500    23,368,940  MGL             0           0      871,330
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
  -    PR Additions and Alterations    0-002-008                                              /  /       /  /     08/27/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Kerhonkson Elementary:
  -    PR Additions and Alterations    0-006-006                                              /  /       /  /     04/06/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Middle School:
08-0594   Reconstruction               0-007-010  05/14/09     DONE    DONE       DONE      10/24/08   10/22/08   11/06/06   10/21/07   2,8,9,10,15,16         1,688,500             0  MGL             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
  -       Reconstruction               0-007-011                                              /  /       /  /     03/24/09     /  /     10,15                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Rosendale Elementary:
  -       Reconstruction               0-012-007                                              /  /       /  /     03/24/09     /  /     2,7                            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Metak Storage Building:
  -    PR New Construction             2-018-001                                              /  /       /  /     12/06/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               5-008-003                                              /  /       /  /     03/24/09     /  /     2,7                            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MARLBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-10-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
08-1730   Reconstruction               0-001-007  07/15/09     DONE    DONE       DONE      06/22/09   06/12/09   03/24/09   05/11/09   15                       325,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Fellenzer Engineering               

          Middle Hope ES:
04-0704   Additions and Alterations    0-003-003  02/11/05     DONE    DONE       DONE      01/21/05   01/20/05   05/01/01   12/17/02   02 - 16                5,011,491     2,424,004  BJB             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        

          Milton Elementary:
04-0705   Additions and Alterations    0-006-004  02/11/05     DONE    DONE       DONE      01/21/05   01/20/05   05/01/01   12/17/02   02 - 16                4,844,745     2,384,484  BJB             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        

          Marlboro High School:
07-0541   Reconstruction               0-007-004  01/21/08     DONE    DONE       DONE      10/12/07   10/11/07   09/03/04   03/20/07   2                      3,187,500     3,187,500  HCM             0           0      684,823
                                                                                                                                                                                                                                 ThomasAssociates, PC                
07-1263   Additions and Alterations    0-007-005  09/26/08     DONE    DONE       DONE      12/31/07   12/26/07   09/07/04   03/20/07   02 - 16               20,878,500             0  HCM             0           0      870,000
                                                                                                                                                                                                                                 ThomasAssociates, PC                
09-0311   Reconstruction               0-007-006               STARTED STARTED    UNREVIEWED***SHPO RESPONSE***                                                                      0  HCM             0           0            0
                                                                                                                                                                                                                                 Tetra  Tech Architects & Engineers  

          Marlboro CSD - Central Offices:
08-0675TQ Temporary Quarters           1-020-001  11/03/08     DONE    DONE       DONE      11/04/08   10/31/08   04/03/08     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Lattintown School:
07-2292   Reconstruction               2-005-001  07/07/08     DONE    DONE       DONE      07/01/08   06/16/08   04/03/08   04/17/08   2                         90,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                

          Central Storage:
  -    PR Additions and Alterations    3-004-001                                              /  /       /  /     06/08/06     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Residential Building (1 Fam Rental):
04-1074DB Discovered Building          7-018-001  05/23/05     DONE    DONE       DONE      04/01/05   03/31/05   02/20/03     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Residential Building #4 (1 Fam Rent):
08-1303DB Discovered Building          7-019-001  04/30/09     DONE    DONE       DONE      03/02/09   02/26/09   04/23/07     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Stand at Middle High:
09-0400   New Construction             7-021-001               STARTED STARTED    UNREVIEWED***SHPO RESPONSE***                                                                      0  HCM             0           0            0
                                                                                                                                                                                                                                 Tetra  Tech Architects & Engineers  

          Press Box at Middle High School:
  -    PR New Construction             7-022-001                                              /  /       /  /     03/26/09     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEW PALTZ CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-11-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
06-0004   Reconstruction               0-001-010  05/11/07     DONE    DONE       DONE      07/06/06   07/06/06   05/19/06   03/01/06   2,4,8,9,155,15,16        126,200             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hewitt Monahan Associates,PLLC      
  -    PR Additions and Alterations    0-001-011                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Duzine Elementary School:
06-0005   Reconstruction               0-004-008  05/11/07     DONE    DONE       DONE      07/06/06   07/06/06   05/19/06   03/01/06   2,4,7,8,9,155,15,16       12,400             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hewitt Monahan Associates,PLLC      
07-0579   Reconstruction               0-004-009  10/17/07     DONE    DONE       DONE      10/17/07   09/18/07   06/26/07   05/15/07   2,4,7                    200,000       200,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
07-1282   Reconstruction               0-004-010  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,155,15,16          803,555             0  DDJ             0           0      315,418
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
  -       Reconstruction               0-004-011                                              /  /       /  /     08/12/08     /  /     2,4,10,13,14,15,16             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          High School:
07-1283   Reconstruction               0-005-014  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,8,9,10,155,15,     927,257             0  DDJ             0           0      364,566
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
  -       Reconstruction               0-005-015                                              /  /       /  /     01/20/09     /  /     2,4,8,9,10,155,15,16           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-005-016                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Lenape Elementary School:
  -       Reconstruction               0-008-007                                              /  /       /  /     05/19/06     /  /     2,4,7,8,9,155,15,16            0    13,018,017  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
07-1284   Reconstruction               0-008-008  04/15/09     DONE    DONE       DONE      01/02/08   12/28/07   09/27/07   05/15/07   2,4,7,8,9,10,13,14,1     135,688             0  DDJ             0           0       53,548
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
08-1610   Reconstruction               0-008-009  05/12/09     DONE    DONE       DONE      05/11/09   05/05/09   01/20/09   01/20/09   2,4,8,9,10,155,15,16      20,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 AlFandre Architecture               

          District Office (Leased):
  -    TQ Temporary Quarters           1-016-001                                              /  /       /  /     12/07/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Transportation Facility:
  -    XX New Construction             5-015-001                         CANCELLED            /  /       /  /     01/05/05     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    5-015-002                                              /  /       /  /     11/06/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONTEORA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-12-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
07-1199   Reconstruction               0-001-016  08/04/08     DONE    DONE       DONE      12/24/07   12/21/07   04/18/07   03/29/07   4,8,9,10,13,14,155,1   1,587,060     1,587,060  DDJ             0           0      321,010
                                                                                                                                                                                                                                 KSQ Architects,P.C                  
08-1391   Reconstruction               0-001-017  03/18/09     DONE    DONE       DONE      03/18/09   03/18/09   01/09/09   12/02/08   2,15,16                  181,329       181,329  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
08-1546   Reconstruction               0-001-018  07/06/09     DONE    DONE       DONE      04/27/09   04/21/09   01/12/09   05/20/08   2,7                    1,079,100             0  DDJ             0           0            0
                                                                                                                                                                                                                                 KSQ Architects,P.C                  
  -    PR Additions and Alterations    0-001-019                                              /  /       /  /     06/04/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-1707   Reconstruction               0-001-019  09/03/09     DONE    DONE       DONE      06/18/09   06/18/09   01/14/09   05/20/08   2,15,16                  171,000             0                  0           0            0
                                                                                                                                                                                                                                 KSQ Architects,P.C                  

          Woodstock Elementary:
05-1230   Reconstruction               0-009-009  06/13/06     DONE    DONE       DONE      05/08/06   05/01/06   03/21/06   01/31/06   13                       116,000       116,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Warren & Panzer Engineers, P.C.     
06-1391   Reconstruction               0-009-010  05/10/07     DONE    DONE       DONE      05/02/07   05/01/07   04/18/07   03/29/07   9,155,15,16              495,219             0  DDJ             0           0      341,701
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAUGERTIES CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-16-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Riccardi School (F'mlyGlasco):
05-0651   Alterations                  0-004-005  04/13/06     DONE    DONE       DONE      01/24/06   01/24/06     /  /     03/15/05   02 - 16                2,181,995     2,181,995  DDJ             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P

          Cahill Elementary School:
05-0652   Reconstruction               0-005-015  04/13/06     DONE    DONE       DONE      01/24/06   01/24/06   09/01/04   03/15/05   7,9,155,16               286,168       286,168  DDJ             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P

          Mt Marion Elementary:
05-0653   Alterations                  0-008-011  04/13/06     DONE    DONE       DONE      01/24/06   01/24/06   09/01/04   03/15/05   02 - 16                2,867,631     2,867,631  DDJ             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P

          Jr/Sr High School:
05-0772   Additions and Alterations    0-009-016  06/08/06     DONE    DONE       DONE      02/15/06   02/07/06   09/01/04   03/15/05   02 - 16               19,961,954    19,961,954  DDJ             0           0    1,081,872
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P

          Grant D Morse Elem. School:
05-0654   Alterations                  0-010-008  04/13/06     DONE    DONE       DONE      01/24/06   01/24/06   09/01/04   03/15/05   02 - 16                2,371,513     2,371,513  DDJ             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P

          Multi-purpose Bldg:
  -       Reconstruction               2-002-002                                              /  /       /  /     12/21/04     /  /     4,7,8,9,10,155,15,16           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WALLKILL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-18-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Leptondale Elementary:
04-1187   Reconstruction               0-001-012  06/21/05     DONE    DONE       DONE      04/25/05   04/22/05   03/23/04   03/21/00   2,15                     357,420       357,420  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
05-1213   Reconstruction               0-001-013  06/22/06     DONE    DONE       DONE      04/28/06   04/26/06   02/16/06   05/16/06                             62,800        62,800  DDJ             0           0       11,932
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0775   Reconstruction               0-001-014  04/16/08     DONE    DONE       DONE      11/13/07   11/08/07   03/20/07   02/27/07   2,4,7,8,9,10,13,155,   2,036,067     2,036,067  DDJ             0           0      199,754
                                                                                                                                                                                                                                 Thomas Associates                   
09-0414   Reconstruction               0-001-015               DONE    STARTED    UNREVIEWED11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TEtra Tech Engineers,Architects,& La

          John G. Borden Middle(fmly Wallkill):
07-0776   Reconstruction               0-002-008  04/16/08     DONE    DONE       DONE      11/13/07   11/08/07   03/20/07   02/27/07   2,4,7,8,9,10,13,14,1   2,807,885     2,807,885  DDJ             0           0      275,475
                                                                                                                                                                                                                                 Thomas Associates                   
09-0415   Reconstruction               0-002-009               DONE    STARTED    UNREVIEWED11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TEtra Tech Engineers,Architects,& La
06-0679SC Visual Structural Inspection 0-002-SC1  12/28/06     DONE    DONE       DONE      12/14/06   12/14/06     /  /       /  /     16                         3,006         2,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Ostrander Elementary:
07-0777   Reconstruction               0-003-009  04/16/08     DONE    DONE       DONE      11/13/07   11/08/07   03/20/07   02/27/07   2,4,7,8,9,10,13,155,   1,790,585     1,790,585  DDJ             0           0      175,670
                                                                                                                                                                                                                                 Thomas Associates                   
09-0416   Reconstruction               0-003-010               DONE    STARTED    UNREVIEWED11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TEtra Tech Engineers,Architects,& La
06-0680SC Visual Structural Inspection 0-003-SC1  12/28/06     DONE    DONE       DONE      12/14/06   12/14/06     /  /       /  /     16                         2,406         2,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Plattekill Elementary:
07-0778   Reconstruction               0-005-010  04/16/08     DONE    DONE       DONE      11/13/07   11/08/07   03/20/07   02/27/07   2,4,7,8,9,10,13,155,   1,967,961     1,967,961  DDJ             0           0      193,072
                                                                                                                                                                                                                                 Thomas Associates                   
09-0417   Reconstruction               0-005-011               DONE    STARTED    UNREVIEWED11/10/09   11/09/09   05/07/09   02/27/07   2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TEtra Tech Engineers,Architects,& La
06-0681SC Visual Structural Inspection 0-005-SC1  12/28/06     DONE    DONE       DONE      12/14/06   12/14/06     /  /       /  /     16                         2,406         2,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Wallkill High School:
05-1214   Reconstruction               0-007-013  06/22/06     DONE    DONE       DONE      04/28/06   04/26/06   02/16/06   05/16/06   7                         67,483        67,483  DDJ             0           0       16,663
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0779   Reconstruction               0-007-014  04/16/08     DONE    DONE       DONE      11/13/07   11/08/07   03/20/07   02/27/07   2,4,7,8,9,10,13,14,1   3,012,082     3,012,082  DDJ             0           0      295,509
                                                                                                                                                                                                                                 Thomas Associates                   
06-0249SC Visual Structural Inspection 0-007-SC1  10/03/06     DONE    DONE       DONE      09/25/06   09/25/06     /  /       /  /     16                         8,593         8,593  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Lacrosse Storage:
06-0375DB Discovered Building          2-022-001  11/15/07     DONE    DONE       DONE      10/30/06   10/30/06   10/24/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Soccer Storage:
06-0376DB Discovered Building          2-023-001  11/15/07     DONE    DONE       DONE      10/30/06   10/30/06   10/24/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Athletic Storage @ Ostrander ES:
06-0377DB Discovered Building          2-024-001  11/15/07     DONE    DONE       DONE      10/30/06   10/30/06   10/24/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Pump House @ HS Soccer Field:
06-0378DB Discovered Building          7-025-001  11/15/07     DONE    DONE       DONE      10/30/06   10/30/06   10/24/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Bldg. @ Soccer Field:
06-0379DB Discovered Building          7-026-001  11/15/07     DONE    DONE       DONE      10/30/06   10/30/06   10/24/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ELLENVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-20-02-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 5-12:
05-0172   Reconstruction               0-001-019  06/02/06     DONE    DONE       DONE      09/01/05   09/01/05   09/23/04   05/17/05   4                        632,000       651,478  DDJ             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
08-0002   Reconstruction               0-001-020  07/14/08     DONE    DONE       DONE      07/11/08   07/07/08   05/14/08   05/22/08   155,16                   341,376       341,376  DDJ             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          ES K-4:
  -       Reconstruction               0-008-004                                              /  /       /  /     02/27/06     /  /     4,9,16                         0    11,456,591  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-1654   Reconstruction               0-008-005  06/26/09     DONE    DONE       DONE      06/01/09   05/20/09   03/26/09   05/13/08   2,9                       56,599        56,599  DDJ             0           0            0
                                                                                                                                                                                                                                 Mosaic Associates                   

          Ellenville Public Library:
06-0563   Reconstruction               6-007-003  12/04/06     DONE    DONE       DONE      11/29/06   11/28/06   11/28/06   11/15/06   7,13                     141,250             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Bryan Zelnik Architect              


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ULSTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 62-90-00-00
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Port Ewen Ed Center (Votec):
05-0638   Reconstruction               0-014-012  05/19/06     DONE    DONE       DONE      01/19/06   01/19/06   07/21/05   05/17/05   2,4,8,9,10,155,15,16     699,585       699,585  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
05-0909   Reconstruction               0-014-013  07/21/06     DONE    DONE       DONE      03/09/06   03/07/06   02/08/06   05/17/05   4,8,9,10,155,15,16       755,528       755,528  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
08-1422   Reconstruction               0-014-014  04/13/09     DONE    DONE       DONE      03/24/09   03/20/09   01/21/09   05/11/08   7                        241,188       324,000  JOD             0           0            0
                                                                                                                                                                                                                                 Mosaic Associates                   
08-1421   Reconstruction               0-014-015  04/21/09     DONE    DONE       DONE      03/24/09   03/20/09   01/26/09   05/11/08   4,8,9                    170,972       211,500  JOD             0           0            0
                                                                                                                                                                                                                                 Mosaic Associates                   
  -       Reconstruction               0-014-016                                              /  /       /  /     06/04/09     /  /     4,8,9,10,155,15,16             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
09-0390   Reconstruction               0-014-017                         UNREVIEWED         11/05/09   11/04/09   09/04/09   05/19/08   4,9,155                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Mosaic Associates                   

          Instructional Center:
05-0139   Reconstruction               1-002-002  09/06/05     DONE    DONE       DONE      08/18/05   08/17/05   07/20/05   05/17/05   7,10,155,15,16            50,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Administration Building:
05-0186   Reconstruction               1-003-010  11/10/05     DONE    DONE       DONE      09/13/05   09/10/05   07/21/05   05/17/05   2,4,8,9,10                94,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0550   Reconstruction               1-003-011  11/30/06     DONE    DONE       DONE      11/22/06   11/22/06     /  /     05/16/06   2,10                     160,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Route 9W Bus Garage:
04-1469TQ Temporary Quarters           4-030-001  07/14/05     DONE    DONE       DONE        /  /       /  /     09/30/02     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          District-Wide Project:
08-1131   Reconstruction               7-999-002  03/16/09     DONE    DONE       DONE      01/27/09   01/23/09   12/04/08   05/20/08   16                       356,904       420,250  JOD             0           0            0
                                                                                                                                                                                                                                 Mosaic Associates                   

          :
  -    TQ Temporary Quarters           8-034-001                                              /  /       /  /     07/11/05     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          ULSTER CCC-ALQONQUIN BUILDING:
06-0203TQ Temporary Quarters           8-035-001  02/13/07     DONE    DONE       DONE      09/06/06   08/21/06   07/25/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          KINGSTON SD-GEORGE WASHINGTON ELEMNT:
06-0204TQ Temporary Quarters           8-036-001                       ADDENDUM REQ'D       09/06/06   08/21/06   07/25/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Business Resource:
07-1385TQ Temporary Quarters           8-037-001  01/24/08     DONE    DONE       DONE      01/16/08   01/16/08   06/05/07     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                 MRB GROUP                           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED