Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/19/09 at 17:00:09




DRYDEN CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-03-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cassavant Elementary:
04-0268   Reconstruction               0-001-006  12/21/04     DONE    DONE       DONE      10/05/04   10/04/04   08/11/03   11/18/03   2,4,7,8,9,10,155,15,   1,514,605     1,511,962  HCM             0           0            0
                                                                                                                                                                                                                                 Highland Associates                 

          Dryden Elementary:
04-0269   Reconstruction               0-003-015  12/21/04     DONE    DONE       DONE      10/05/04   10/04/04   08/21/03   11/18/03   2,4,7,8,9,10,155,15,   9,929,981     9,929,981  HCM             0           0            0
                                                                                                                                                                                                                                 Highland Associates                 
07-1587   Reconstruction               0-003-016  03/13/08     DONE    DONE       DONE      02/11/08   02/05/08   12/05/07   05/20/07   4,7                      100,000       100,000  HCM             0           0            0
                                                                                                                                                                                                                                 joseph/rominski/architectue         
08-1768   Reconstruction               0-003-017  07/02/09     DONE    DONE       DONE      06/30/09   06/24/09   03/30/09   05/19/09   4,7                      100,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 joseph/rominski/architectue         

          Freeville Elementary:
04-0270   Reconstruction               0-004-007  12/22/04     DONE    DONE       DONE      10/05/04   10/04/04   08/11/03   11/18/03   2,4,7,8,9,10,155,15,   1,255,414     1,255,414  HCM             0           0            0
                                                                                                                                                                                                                                 Highland Associates                 

          Junior Senior High:
05-0119   Reconstruction               0-005-017  08/19/05     DONE    DONE       DONE      08/10/05   08/10/05   06/08/05   05/17/05   7                         90,000        90,000  HCM             0           0            0
                                                                                                                                                                                                                                 Highland Associates                 
05-1197   Reconstruction               0-005-018  08/28/06     DONE    DONE       DONE      04/24/06   04/24/06   12/01/05   05/16/06   8,9,155,15,16             99,379        99,379  HCM             0           0            0
                                                                                                                                                                                                                                 Highland Associates                 
07-0835   Reconstruction               0-005-019  06/10/08     DONE    DONE       DONE      11/16/07   11/15/07   01/16/07   04/03/07   2,4,7,8,9,10,14,155,   3,579,488     3,579,488  HCM             0           0      418,800
                                                                                                                                                                                                                                 joseph/rominski/architectue         
  -       Reconstruction               0-005-020                                              /  /       /  /     11/12/08     /  /     2,4,7,8,9,10,13,155,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Shed @ High School Campus:
  -    DB Discovered Building          2-016-001                                              /  /       /  /     11/16/07     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Shed @ Cassavant Elementary:
  -    DB Discovered Building          2-017-001                                              /  /       /  /     11/16/07     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          District Wide:
07-1940   Reconstruction               7-999-003  01/21/09     DONE    DONE       DONE      04/08/08   04/02/08   10/01/07   04/03/07   10,13,16                 796,512       796,512  HCM             0           0       93,192
                                                                                                                                                                                                                                 joseph/rominski/architectue         


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GEORGE JR UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-03-27-02
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Education Unit #1:
07-0328PR Additions and Alterations    0-001-005                       STARTED              09/07/07     /  /     03/26/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 George Lukaszewicz Arch.            


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GROTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-05-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior Senior High:
07-0138   Reconstruction               0-002-009  12/24/07     DONE    DONE       DONE      08/07/07   08/06/07   09/08/06   12/12/06   2,4,8,9,155,15,16      8,448,646     8,448,646  MGL             0           0      208,726
                                                                                                                                                                                                                                 Ashley McGraw Architects            
09-0103   Reconstruction               0-002-010               STARTED DONE       ADD. REQ'D***NON-COLLUSION CERTIF. MISSING FROM SPEC***                                            0  HCM             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Elementary School:
07-0139   Reconstruction               0-003-007  12/24/07     DONE    DONE       DONE      08/07/07   08/06/07   09/08/06   12/12/06   2,4,7,8,9,155,15,16    4,853,143     4,853,143  MGL             0           0      130,000
                                                                                                                                                                                                                                 Ashley McGraw Architects            
09-0104   Reconstruction               0-003-008               STARTED DONE       ADD. REQ'D***NON-COLLUSION CERTIF. MISSING FROM SPEC***                                            0  HCM             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Bus Garage Maint. Storage:
07-0140   Reconstruction               5-001-005  12/24/07     DONE    DONE       DONE      08/07/07   08/06/07   01/19/07   12/12/06   2,4,7,9,10,15,16       1,173,210     1,173,210  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ITHACA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-06-00-01
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alternative Community School (6-12):
08-0133   Additions and Alterations    0-003-008  07/17/09     DONE    DONE       DONE      08/05/08   07/31/08   11/22/06   03/06/07   02 - 16               10,294,096     5,498,993  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Enfield Elem School (K-5):
08-0388   Additions and Alterations    0-004-011  03/17/09     DONE    DONE       DONE      09/24/08   09/23/08   11/22/06   03/06/07   02 - 16                1,391,984             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Sherman Elem School(K-5):
  -    PR Additions and Alterations    0-007-009                                              /  /       /  /     11/22/06     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Cayuga Heights Elem.(K-5):
07-1818SR Reconstruction               0-011-004  03/20/08     DONE    DONE       DONE      03/17/08   03/04/08   11/22/06   03/06/07   2,155,16               2,975,669             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
08-0196   Reconstruction               0-011-004  03/16/09     DONE    DONE       DONE      08/22/08   08/13/08     /  /     03/06/07   7                      2,837,740             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Martin ES(K-5)(f'ly Central ES):
07-0950   Reconstruction               0-012-008  04/23/08     DONE    DONE       DONE      11/27/07   11/26/07   11/22/06   03/06/07   2,4,7,155,16           4,332,759             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     
08-0101   Reconstruction               0-012-009  04/22/09     DONE    DONE       DONE      07/25/08   07/25/08   08/20/07   03/06/07   2,7,155,16             1,048,242             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Fall Creek Elem School(K-5):
08-0462   Reconstruction               0-013-006  03/16/09     DONE    DONE       DONE      10/06/08   10/03/08   11/22/06   03/06/07   2,7,8,155,16           3,099,207             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          South Hill Elem School(K-5):
09-0308   Reconstruction               0-014-008               STARTED STARTED    UNREVIEWED10/14/09   10/13/09   11/22/06   03/06/07   2,8,155                        0     4,930,119  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          High School(9-12):
04-1324   Reconstruction               0-015-012  07/05/05     DONE    DONE       DONE      05/24/05   05/20/05   05/03/04   05/18/04   7                        384,128       384,128  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  
05-0023   Reconstruction               0-015-013  09/15/05     DONE    DONE       DONE      07/07/05   07/06/05   03/23/05   05/17/05   2,13,16                  348,317       348,317  DDJ             0           0            0
                                                                                                                                                                                                                                 IBC Engineering, P.C                
05-0669   Reconstruction               0-015-014  05/02/06     DONE    DONE       DONE      01/30/06   01/30/06   06/29/05   05/18/04   2,4,8,9,16               188,720       188,720  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  
05-0553   Reconstruction               0-015-015  04/13/06     DONE    DONE       DONE      01/11/06     /  /     08/23/05   05/18/04   4,15                     435,680       435,680  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0860   Reconstruction               0-015-016  03/31/06     DONE    DONE       DONE      03/01/06   03/01/06   01/19/06   05/17/05   7                        173,043       173,043  DDJ             0           0            0
                                                                                                                                                                                                                                 Kingsbury Architecture LLC          
07-1729PR Additions and Alterations    0-015-017                         UNREVIEWED         03/04/08   02/28/08   08/10/06     /  /     02 - 16                        0    33,759,160  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  
08-0193   Additions and Alterations    0-015-017  02/13/09     DONE    DONE       DONE      08/19/08   07/28/08   08/10/06   01/18/07   02 - 16               12,904,526     7,205,719  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  
  -    PR Additions and Alterations    0-015-018                                              /  /       /  /     11/22/06     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
07-0921   Reconstruction               0-015-019  06/06/08     DONE    DONE       DONE      11/23/07   11/21/07   08/01/07   03/06/07   7,155                  2,151,904             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
05-0265SC Visual Structural Inspection 0-015-SC1  10/17/05     DONE    DONE       DONE      10/17/05   10/17/05     /  /       /  /     16                        53,535        28,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Caroline Elem School(K-5):
06-1558SR Reconstruction               0-017-008  06/01/07     DONE    DONE       DONE      05/31/07   05/21/07   11/22/06     /  /     2,7,8,155,15,16        5,851,000     5,821,181  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0922   Reconstruction               0-017-008  06/06/08     DONE    DONE       DONE      11/23/07   11/21/07   11/22/06     /  /     2,7,8,155,15,16        5,851,000     5,830,820  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Northeast Elem School(K-5):
08-0544   Reconstruction               0-024-006  03/27/09     DONE    DONE       DONE      10/16/08   10/14/08   11/22/06   03/06/07   2,8,155                3,999,578             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Boynton MS (6-8):
07-0951   Reconstruction               0-026-012  04/23/08     DONE    DONE       DONE      11/27/07   11/26/07   11/22/06   03/06/07   2,7,10,155,15,16      10,754,876    10,754,876  DDJ             0           0      865,242
                                                                                                                                                                                                                                 Hunt Engineers,                     
08-0102   Reconstruction               0-026-013  04/22/09     DONE    DONE       DONE      07/25/08   07/25/08   08/20/07   03/06/07   2,155,16               3,768,940             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Dewitt MS (6-8):
07-0952   Reconstruction               0-027-012  04/23/08     DONE    DONE       DONE      11/27/07   11/26/07   11/22/06   03/06/07   2,7,10,155,15,16       9,098,352             0  DDJ             0           0      865,242
                                                                                                                                                                                                                                 Hunt Engineers,                     
08-0103   Reconstruction               0-027-013  04/22/09     DONE    DONE       DONE      07/25/08   07/25/08   08/20/07   03/06/07   155,16                 4,324,490             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Wilson Annex @ Sherman School(K-5):
09-0198   Reconstruction               0-028-006               STARTED DONE       ADD. REQ'D09/14/09   09/08/09   11/22/06   03/06/07   2,7,155,16                     0     2,577,840  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Temp Bldg. A @ High School:
  -    TQ Temporary Quarters           0-052-001                                              /  /       /  /     12/02/08     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Temp Modular @ Lehman Alt Comm Sch:
  -    PR New Construction             0-054-001                                              /  /       /  /     10/21/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Temp Modular @ Boynton Middle School:
  -    PR New Construction             0-055-001                                              /  /       /  /     10/21/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Temp Modular @ Dewitt Middle School:
  -    PR New Construction             0-056-001                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Temp office space @ HS-for project:
  -       New Construction             1-053-001                                              /  /       /  /     01/08/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Athletic Storage Building:
04-0144   New Construction             2-049-001  12/10/04     DONE    DONE       DONE      08/20/04   08/19/04   05/11/04   05/18/04   02 - 16                  125,860             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  

          Athletic Field Storage Bldg. #2:
04-0145   New Construction             2-050-001  12/10/04     DONE    DONE       DONE      08/20/04   08/19/04   06/28/04   05/18/04   02 - 16                   24,350             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Egner Architectural Associates LLC  

          Vehicle Maintenance Center:
07-0124   Reconstruction               5-002-007  08/15/07     DONE    DONE       DONE      08/03/07   08/02/07   11/22/06   03/06/07   7                        350,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Athletic Fields Restroom Facility:
07-0923   New Construction             7-051-001  06/06/08     DONE    DONE       DONE      11/23/07   11/21/07   08/01/07   03/06/07   02 - 16                  603,466             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Districtwide Technology:
08-0475   Reconstruction               7-999-003  03/31/09     DONE    DONE       DONE      10/06/08   10/03/08   01/17/08   03/06/07   16                       917,170             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LANSING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-08-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lansing Middle:
05-0022   Reconstruction               0-001-012  07/12/05     DONE    DONE       DONE      07/07/05   07/06/05   01/10/03   06/09/05   4                        250,000       250,000  DDJ             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
04-0936   Reconstruction               0-001-013  03/28/05     DONE    DONE       DONE      03/10/05   03/08/05   09/16/04   12/14/04   4,7,8,16                 649,543       649,543  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
08-1153   Reconstruction               0-001-014  07/24/09     DONE    DONE       DONE      02/02/09   01/27/09   10/07/05   08/25/08   8,16                     617,199             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Jack Eisenbach - Engineer           

          School Shop:
  -       Reconstruction               0-002-003                                              /  /       /  /     10/07/05     /  /     2                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Lansing Elementary:
04-0937   Reconstruction               0-003-008  03/28/05     DONE    DONE       DONE      03/10/05   03/08/05   09/16/04   12/14/04   8,10,16                   23,697        23,697  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
08-1154   Reconstruction               0-003-009  07/24/09     DONE    DONE       DONE      02/02/09   01/27/09   10/07/05   08/25/08   2,8,155,16               766,307             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Jack Eisenbach - Engineer           
08-1279   Reconstruction               0-003-010  03/31/09     DONE    DONE       DONE      02/25/09   02/18/09   01/26/09   12/08/08   2,7,8                    878,977       878,977  DDJ             0           0      297,973
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   

          Senior High:
04-0938   Reconstruction               0-004-011  03/28/05     DONE    DONE       DONE      03/10/05   03/08/05   09/16/04   12/14/04   7,8,16                   494,035       494,035  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
08-1155   Reconstruction               0-004-012  07/24/09     DONE    DONE       DONE      02/02/09   01/27/09   10/07/05   08/25/08   2,8,155,16             2,907,568             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Jack Eisenbach - Engineer           
06-0592   Reconstruction               0-004-013  01/02/07     DONE    DONE       DONE      12/06/06   12/05/06   09/13/06   12/14/04   10,155,15,16              51,500        51,500  DDJ             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-004-014                                              /  /       /  /     08/22/08     /  /     2,4,7                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          District Office:
  -       Reconstruction               1-005-004                                              /  /       /  /     10/07/05     /  /     2                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          TO BE DETERMINED:
  -    TQ Temporary Quarters           1-014-001                                              /  /       /  /     09/12/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Grounds Building II:
01-0828DB Discovered Building          3-013-001  09/28/09     DONE    DONE       DONE      02/14/02     /  /     12/10/01     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Maintenance Garage:
04-0939   Reconstruction               5-006-007  03/28/05     DONE    DONE       DONE      03/10/05   03/08/05   09/16/04   12/14/04   7,10,155,16               32,410        32,410  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -       Reconstruction               5-006-008                                              /  /       /  /     12/21/05     /  /     2,4,8,9,10,13,14,155           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-006-009                                              /  /       /  /     09/12/06     /  /     10                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-09-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Newfield Elementary:
07-1106   Reconstruction               0-001-010  05/07/08     DONE    DONE       DONE      12/12/07   12/11/07   01/16/07   03/20/07   2,4,7,8,9,155,15,16    4,062,713     3,885,513  DDJ             0           0      328,735
                                                                                                                                                                                                                                 Thomas Associates                   

          Junior/Senior High School:
07-1107   Additions and Alterations    0-005-006  05/07/08     DONE    DONE       DONE      12/12/07   12/11/07   01/16/07   03/20/07   02 - 16                7,202,229     7,089,273  DDJ             0           0      377,595
                                                                                                                                                                                                                                 Thomas Associates                   

          Maintenance Bldg:
07-1108   Reconstruction               3-004-001  05/07/08     DONE    DONE       DONE      12/12/07   12/11/07   01/24/07   03/20/07   4,7,8,9,155,15,16        289,500             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          New Field House:
07-1109   New Construction             7-009-001  05/07/08     DONE    DONE       DONE      12/12/07   12/11/07   01/24/07   03/20/07   02 - 16                  490,058             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Newfield Fire Station:
07-2092TQ Temporary Quarters           8-010-001  05/20/08     DONE    DONE       DONE      05/07/08   05/06/08   05/06/08     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TRUMANSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-10-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Russell I Doig Middle School:
  -       Reconstruction               0-001-008                                              /  /       /  /     01/02/07     /  /     2,4,7,8,9,155,15,16            0     7,591,218  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-001-009                                              /  /       /  /     01/02/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0019   Reconstruction               0-001-010  08/23/07     DONE    DONE       DONE      07/06/07   07/06/07   05/02/07   05/16/06   4,7,8                     73,768        73,768  HCM             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
08-0107   Reconstruction               0-001-011  01/05/09     DONE    DONE       DONE      07/31/08   07/28/08   07/25/07   10/23/07   2,4,7,8,9,155,15,16    3,589,979     3,589,979  HCM             0           0      141,109
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Trumansburg Elementary:
05-0836   Reconstruction               0-003-007  03/10/06     DONE    DONE       DONE      03/01/06   02/28/06   09/20/05   12/13/05   2,7,9,155,15,16           88,515        88,515  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-0108   Reconstruction               0-003-008  01/05/09     DONE    DONE       DONE      07/31/08   07/28/08   01/02/07   10/23/07   2,4,7,8,9,155,15,16    2,644,626     2,644,626  HCM             0           0      141,109
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -    PR Additions and Alterations    0-003-009                                              /  /       /  /     01/02/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Dickerson High School:
08-0109   Reconstruction               0-006-008  01/05/09     DONE    DONE       DONE      07/31/08   07/28/08   01/02/07   10/23/07   2,4,7,8,9,155,15,16    2,166,335     2,039,200  HCM             0           0      141,109
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -    PR Additions and Alterations    0-006-009                                              /  /       /  /     01/02/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
09-0021SC Visual Structural Inspection 0-006-SC1  07/03/09     DONE    DONE       DONE      07/03/09   05/20/08     /  /       /  /     16                         2,900             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Maintenance Storage:
  -    PR New Construction             2-009-001                                              /  /       /  /     04/03/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Buiding:
  -    DB Discovered Building          2-010-001                                              /  /       /  /     04/03/08     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Maintenance Bldg:
  -       Reconstruction               3-005-001                                              /  /       /  /     07/25/07     /  /     8,155,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
08-0110   Reconstruction               5-004-004  01/05/09     DONE    DONE       DONE      07/31/08   07/28/08   07/25/07   10/23/07   2,7,8,155,15,16          361,076       628,500  HCM             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          District Wide:
08-0111   Reconstruction               7-999-005  01/05/09     DONE    DONE       DONE      07/31/08   07/28/08   07/25/07   10/23/07   10,13,16                 882,984       878,900  HCM             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES TOMPKINS-SENECA-TIOGA STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-90-00-00
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          F Bldg Greenhouse:
05-0816   Reconstruction               0-008-003  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16             29,490        29,490  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0359   Reconstruction               0-008-004  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/21/06   06/07/06   8,16                      16,089        16,089  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          G Powell Bldg B:
05-0817   Reconstruction               0-009-005  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            492,309       492,309  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0360   Reconstruction               0-009-006  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/20/06   06/07/06   8,16                      56,430        56,430  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Occ Ed Bldg C:
05-0818   Reconstruction               0-010-004  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            352,399       352,399  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0361   Reconstruction               0-010-005  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/20/06   06/07/06   8,16                      37,192        37,192  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
08-0957   Reconstruction               0-010-006  04/27/09     DONE    DONE       DONE      12/19/08   12/16/08   10/27/08   12/03/08   10,13,155,16             207,000       167,000  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Occ Ed Bldg D:
05-0819   Reconstruction               0-011-004  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            465,528       465,528  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0362   Reconstruction               0-011-005  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06     /  /     06/07/06   8,16                      38,522        38,522  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Smith Special Ed Blg:
05-0820   Reconstruction               0-012-009  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            723,774       723,774  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0363   Reconstruction               0-012-010  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/21/06   06/07/06   8,16                      22,520        22,520  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Relocatable/Adult Ed./Adm.:
06-0364   Reconstruction               0-014-002  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/21/06   06/07/06   8,16                      16,651             0  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Admin Bldg:
05-0821   Reconstruction               1-001-004  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            319,300             0  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0365   Reconstruction               1-001-005  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/20/06   06/07/06   8,16                      32,834             0  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          G Bldg Warehouse:
  -       Reconstruction               2-007-003                                              /  /       /  /     10/19/05     /  /     2,13                           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          G BLDG Warehouse/Bus Maint.:
05-0822   Reconstruction               5-007-001  03/28/06     DONE    DONE       DONE      02/24/06   02/23/06   11/18/05   12/07/05   2,7,155,15,16            117,200       117,200  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0366   Reconstruction               5-007-002  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/21/06   06/07/06   8,16                      43,961        43,961  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Spec.Ed. Train & Resource Library:
06-0367   Reconstruction               6-003-002  11/29/06     DONE    DONE       DONE      10/27/06   10/23/06   06/21/06   06/07/06   8,16                      15,301             0  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Southside Community Center, Inc.:
05-0069TQ Temporary Quarters           8-015-001  03/01/07     DONE    DONE       DONE      07/29/05   07/28/05   08/24/92     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Adult Ed @ First Presbyterian Church:
  -    TQ Temporary Quarters           8-018-001                                              /  /       /  /     02/01/07     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED