Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/05/08 at 08:53:26




SOUTH SENECA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-05-01-04
last updated on 09/05/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ovid Jr/Sr High School:
07-0981PR Additions and Alterations    0-001-009                         UNREVIEWED         11/29/07   11/28/07   06/29/05   03/15/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     
07-1255   Additions and Alterations    0-001-009  08/07/08     DONE    DONE       DONE      12/31/07   12/24/07   06/29/05   03/15/07   02 - 16               16,453,506             0  HCM             0           0      640,865
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Interlaken Elementary:
07-1256   Reconstruction               0-004-009  08/07/08     DONE    DONE       DONE      12/31/07   12/24/07   06/29/05   03/15/07   2,4,7,8,9,10,155,15,   5,840,577             0  HCM             0           0      100,000
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Bus Storage-Interlaken:
07-1257   Additions and Alterations    4-007-004  08/07/08     DONE    DONE       DONE      12/31/07   12/24/07   07/13/05   03/15/07   02 - 16                   15,948             0  HCM             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Bus Storage Garage:
  -    XX New Construction             4-011-001                         CANCELLED            /  /       /  /     12/07/06     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage at Ovid:
  -    XX Additions and Alterations    5-002-004                         CANCELLED            /  /       /  /     06/29/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-002-005                                              /  /       /  /     05/30/08     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Maintenance Garage:
07-1258   New Construction             5-010-001               STARTED DONE       DONE      ***MULTIPLE PROBLEMS***                                                                  0  HCM             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROMULUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-06-03-04
last updated on 09/05/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Romulus Central School:
04-0412   Additions and Alterations    0-002-015  12/24/04     DONE    DONE       DONE      11/16/04   11/12/04   02/06/02   11/10/03   02 - 16                8,958,669     8,958,669  MAC             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
06-1564   Reconstruction               0-002-016  09/14/07     DONE    DONE       DONE      06/04/07   06/01/07   11/22/06   01/30/07   2,4,7,8,9              1,750,000     1,750,000  HCM             0           0      174,009
                                                                                                                                                                                                                                 King & King, Architects             
03-0366FP Reconstruction               0-002-FP1  10/21/03     DONE    DONE       DONE      10/02/03     /  /       /  /       /  /     16                         5,885         5,885  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SENECA FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-07-01-06
last updated on 09/05/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cady Stanton Elementary:
03-0318   Reconstruction               0-001-012  02/13/04     DONE    DONE       DONE      09/18/03   09/08/03   01/15/03   03/25/03   2,4,7,8,9,155,15,16      120,034       120,034  RDR             0           0            0
                                                                                                                                                                                                                                 King & King Architects              
07-0021   Reconstruction               0-001-013  11/19/07     DONE    DONE       DONE      07/09/07   07/06/07   12/18/06   01/30/07   2,7,9,155,16             661,260             0  MGL             0           0      101,900
                                                                                                                                                                                                                                 King & King, Architects             
07-1796   Reconstruction               0-001-014  03/25/08     DONE    DONE       DONE      03/15/08   03/12/08   11/26/07   02/12/08   155                      574,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Frank M. Knight Elementary:
03-0319   Reconstruction               0-002-010  02/13/04     DONE    DONE       DONE      09/18/03   09/08/03   01/15/03   03/25/03   2,4,7,8,9,155,15,16    1,335,322     1,335,322  RDR             0           0            0
                                                                                                                                                                                                                                 King & King Architects              
03-1648   Reconstruction               0-002-011  08/27/04     DONE    DONE       DONE      06/25/04   06/23/04   03/24/04   03/25/03   2,9,16                   476,700       476,700  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-0022   Reconstruction               0-002-012  11/19/07     DONE    DONE       DONE      07/09/07   07/06/07   12/18/06   01/30/07   2,155,16                 257,330             0  MGL             0           0       18,660
                                                                                                                                                                                                                                 King & King, Architects             
07-1797   Reconstruction               0-002-013  03/25/08     DONE    DONE       DONE      03/15/08   03/12/08   11/26/07   02/12/08   155                      472,500             0  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Mynderse Jr/Sr High School:
03-0320   Reconstruction               0-005-014  02/13/04     DONE    DONE       DONE      09/18/03   09/08/03   01/15/03   03/25/03   2,4,7,8,9,10,13,155,   3,938,542     3,580,000  RDR             0           0            0
                                                                                                                                                                                                                                 King & King Architects              
03-1649   Reconstruction               0-005-015  08/27/04     DONE    DONE       DONE      06/25/04   06/23/04   03/24/04   03/25/03   2,8,9,10,155,15,16     1,293,700     1,293,700  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
06-0355   Reconstruction               0-005-016  01/08/07     DONE    DONE       DONE      10/23/06   10/23/06   06/30/06   09/19/06   2,8,9,155,15,16        1,009,431     1,009,431  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-0023   Reconstruction               0-005-017  11/19/07     DONE    DONE       DONE      07/09/07   07/06/07   12/18/06   01/30/07   2,9,155,15,16          1,481,410             0  MGL             0           0      225,640
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
03-0321   Reconstruction               5-007-003  02/13/04     DONE    DONE       DONE      09/18/03   09/08/03   01/15/03   03/25/03   2,4,7,8,9,155,15,16      122,704       122,704  RDR             0           0            0
                                                                                                                                                                                                                                 King & King Architects              

          Press Box/Bleachers:
03-1650   New Construction             7-014-001  08/27/04     DONE    DONE       DONE      06/25/04   06/23/04   05/12/04   03/25/03   02 - 16                   15,000             0  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          District-Wide:
06-0356   Reconstruction               7-999-001  01/08/07     DONE    DONE       DONE      10/23/06   10/23/06   10/10/06   09/19/06   13,16                    562,209       562,209  MGL             0           0       50,087
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERLOO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-10-06-06
last updated on 09/05/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          LaFayette Elementary:
02-1702   Reconstruction               0-003-010  12/19/03     DONE    DONE       DONE      03/14/03   11/27/02   07/24/01   06/11/02   2,4,7,8,9,155,15,16    3,725,646     3,421,890  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
07-0678   Reconstruction               0-003-011  04/09/08     DONE    DONE       DONE      10/30/07   10/29/07   05/22/07   06/25/07   2,7,8,155,15,16        3,242,281             0  HCM             0           0       64,846
                                                                                                                                                                                                                                 Clark Patterson Associates          
03-0051FP Reconstruction               0-003-FP1  09/30/03     DONE    DONE       DONE      07/16/03     /  /       /  /       /  /     16                         5,674         5,674  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Skoi Yase Elementary:
02-1703   Reconstruction               0-008-010  12/19/03     DONE    DONE       DONE      03/14/03   11/27/02   07/27/01   06/11/02   2,4,7,8,9,155,15,16    3,421,151     3,289,253  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
07-0679   Reconstruction               0-008-011  04/09/08     DONE    DONE       DONE      10/30/07   10/29/07   05/22/07   06/25/07   2,7,8,10,13,155,15,1   2,551,279             0  HCM             0           0       51,026
                                                                                                                                                                                                                                 Clark Patterson Associates          
03-0056FP Reconstruction               0-008-FP1  09/30/03     DONE    DONE       DONE      07/16/03     /  /       /  /       /  /     16                         5,674         5,674  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Main St. School-Middle School:
02-2137   Reconstruction               0-010-009  12/31/03     DONE    DONE       DONE      05/02/03   04/28/03   07/27/01   06/11/02   2,4,7,8,9,10,14,155,   5,211,100     3,645,368  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
05-0951   Reconstruction               0-010-010  10/24/06     DONE    DONE       DONE      03/14/06   03/13/06   03/17/04   06/11/02   155,16                   451,250       451,250  MAC             0           0            0
                                                                                                                                                                                                                                 Stantec Consulting Services Inc,.   
07-0680   Reconstruction               0-010-011  04/09/08     DONE    DONE       DONE      10/30/07   10/29/07   05/22/07   06/25/07   2,7,14,155,16          3,484,438             0  HCM             0           0       69,689
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Claude C Doxtator High School:
02-2153   Reconstruction               0-011-007  09/19/03     DONE    DONE       DONE      05/08/03   04/24/03   10/07/96   06/21/00   2                        510,103       510,103  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
02-2452SR Alterations                  0-011-009  12/31/03     DONE    DONE       DONE      06/24/03   04/29/03   07/27/01   06/11/02   02 - 16                        0             0  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
03-0057   Additions and Alterations    0-011-009  12/31/03     DONE    DONE       DONE      07/11/03     /  /     07/27/01   06/11/02   02 - 16               42,807,026    33,179,633  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    
05-0952   Reconstruction               0-011-010  10/24/06     DONE    DONE       DONE      03/14/06   03/13/06   03/17/04   06/11/02   155,16                   379,250       379,250  MAC             0           0            0
                                                                                                                                                                                                                                 Stantec Consulting Services Inc,.   
07-0681   Reconstruction               0-011-011  04/09/08     DONE    DONE       DONE      10/30/07   10/29/07   05/22/07   06/25/07   2,7,8,9,16             3,230,000     3,230,000  HCM             0           0       64,600
                                                                                                                                                                                                                                 Clark Patterson Associates          
03-0055FP Reconstruction               0-011-FP1  09/30/03     DONE    DONE       DONE      07/16/03     /  /       /  /       /  /     16                         5,885         5,885  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Athletic Storage Building:
03-0895   New Construction             2-021-001  12/31/03     DONE    DONE       DONE      12/29/03   12/17/03   12/29/03   06/11/02   02 - 16                  170,270             0  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    

          High School Press Box:
03-0893   New Construction             7-019-001  12/31/03     DONE    DONE       DONE      12/29/03   12/17/03   12/29/03   06/11/02   02 - 16                   33,185             0  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    

          High School Concession Stand:
03-0894   New Construction             7-020-001  12/31/03     DONE    DONE       DONE      12/29/03   12/17/03   12/29/03   06/11/02   02 - 16                  370,723             0  MAC             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED