DUANESBURG 530101
MOHONASEN 530515
NISKAYUNA 530301
SCHALMONT 530501
SCHENECTADY 530600
SCOTIA GLENVIL 530202
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
HIGH MIDDLE SCHOOL:
05-0450 Reconstruction 0-001-011 04/26/06 DONE DONE DONE 12/19/05 12/14/05 05/02/05 05/17/05 10,15,16 100,000 100,000 JOD 0 0 0
CWG Architects.P.C.
05-0646 Reconstruction 0-001-012 05/26/06 DONE DONE DONE 01/24/06 01/24/06 05/02/05 05/17/05 10,16 88,022 88,022 JOD 0 0 0
CWG Architects.P.C.
- PR Additions and Alterations 0-001-013 / / / / 03/24/06 / / 02 - 16 0 0 JOD 0 0 0
06-0773 Reconstruction 0-001-014 04/24/07 DONE DONE DONE 01/17/07 01/17/07 09/19/06 12/12/06 2,4,7,8,9,10,13,155, 1,329,000 1,329,000 JOD 0 0 279,090
CWG Architects.P.C.
08-1221 Reconstruction 0-001-015 07/07/09 DONE DONE DONE 02/18/09 02/10/09 01/02/09 05/19/08 4,8,9,155,16 100,000 0 JOD 0 0 0
Griffith Dardanelli,Architects,PC
Elementary:
04-0284 Additions and Alterations 0-002-009 12/16/04 DONE DONE DONE 10/13/04 10/08/04 01/28/03 12/09/03 02 - 16 4,172,025 3,952,344 MAC 0 0 0
Cataldo, Waters and Griffith Arch.
Annex former Bus. Off. 1-003:
- New Construction 0-003-001 / / / / 04/05/05 / / 02 - 16 0 0 JOD 0 0 0
- Reconstruction 0-003-002 / / / / 07/11/05 / / 2,4,8,9 0 0 JOD 0 0 0
High School Relocata:
06-0774 Reconstruction 0-004-001 04/24/07 DONE DONE DONE 01/17/07 01/17/07 09/20/06 12/12/06 2,9,15,16 69,000 69,000 JOD 0 0 14,490
CWG Architects.P.C.
- Reconstruction 0-004-002 / / / / 09/22/06 / / 2,9,15,16 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Glendaal School:
- XX Reconstruction 0-001-011 CANCELLED / / / / / / / / 2,7 0 6,440,580 JOD 0 0 0
07-1328 Reconstruction 0-001-012 01/17/08 DONE DONE DONE 01/04/08 01/03/08 10/31/07 05/15/07 2,7 800,000 800,000 JOD 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
- Reconstruction 0-001-013 / / / / 07/22/09 / / 2,7,155,16 0 0 JOD 0 0 0
High School:
- Reconstruction 0-002-016 / / / / 07/22/09 / / 2,8,10,155,16 0 0 JOD 0 0 0
Lincoln School:
05-1365 Reconstruction 0-005-009 06/15/06 DONE DONE DONE 06/13/06 06/09/06 06/01/06 05/16/06 2,9 46,742 46,742 HCM 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
- Reconstruction 0-005-010 / / / / 07/22/09 / / 4,7,16 0 0 JOD 0 0 0
Sacandaga School:
- Reconstruction 0-007-011 / / / / 07/22/09 / / 7,16 0 0 JOD 0 0 0
Junior High School:
- PR Additions and Alterations 0-009-011 / / / / 07/22/09 / / 02 - 16 0 0 JOD 0 0 0
Glen-Worden School:
- Reconstruction 0-017-007 / / / / 07/22/09 / / 2,7,16 0 0 JOD 0 0 0
District Office:
07-2089 Reconstruction 1-006-003 05/07/08 DONE DONE DONE 05/06/08 04/29/08 03/31/08 / / 155 70,000 0 JOD 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
- Reconstruction 1-006-004 / / / / 07/22/09 / / 155,16 0 0 JOD 0 0 0
Drama Storage Building:
- XX Reconstruction 2-022-001 CANCELLED / / / / 11/23/07 / / 0 0 JOD 0 0 0
Dugout Storage:
- DB Discovered Building 2-025-001 / / / / 11/23/07 / / 0 0 JOD 0 0 0
Storage Shed @ Beukendaal:
- DB Discovered Building 2-028-001 / / / / 11/23/07 / / 0 0 JOD 0 0 0
Storage Shed #1 @ District Office:
- DB Discovered Building 2-029-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed #2 @ District Office:
- DB Discovered Building 2-030-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed @ Middle School:
- DB Discovered Building 2-031-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed #1 @ High School:
- DB Discovered Building 2-032-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed #2 @ High School:
- DB Discovered Building 2-033-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed #3 @ High School:
- DB Discovered Building 2-034-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed @ Sacandaga School:
- DB Discovered Building 2-035-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed @ Lincoln School:
- DB Discovered Building 2-036-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed @ Glendal School:
- DB Discovered Building 2-037-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Storage Shed @ Glen Worden School:
- DB Discovered Building 2-038-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Salt Storage Building:
- New Construction 2-041-001 / / / / 07/22/09 / / 02 - 16 0 0 JOD 0 0 0
Bus Garage:
- Reconstruction 5-008-006 / / / / / / / / 155,16 0 0 JOD 0 0 0
- Reconstruction 5-008-007 / / / / 07/22/09 / / 7,16 0 0 JOD 0 0 0
Ticket Boot #1:
- DB Discovered Building 7-023-001 / / / / 11/23/07 / / 0 0 JOD 0 0 0
Ticket Booth #2:
- DB Discovered Building 7-024-001 / / / / 11/23/07 / / 0 0 JOD 0 0 0
Concession Building @ Beukendaal:
- XX Reconstruction 7-026-001 CANCELLED / / / / 11/23/07 / / 0 0 JOD 0 0 0
Storage & Bathroom Bldg. @Beukendaal:
- XX Reconstruction 7-027-001 CANCELLED / / / / 11/23/07 / / 0 0 JOD 0 0 0
Beverage & Storage Building:
- DB Discovered Building 7-039-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
Announcer & Restrooms Building:
- DB Discovered Building 7-040-001 / / / / 10/23/08 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Van Antwerp Middle School:
- PR Alterations 0-001-011 / / / / 07/22/05 / / 02 - 16 0 0 JOD 0 0 0
06-0598 Alterations 0-001-011 04/04/07 DONE DONE DONE 12/06/06 12/05/06 07/22/05 01/24/06 02 - 16 8,041,501 8,041,501 JOD 0 0 0
Thomas Associates
07-1310 Reconstruction 0-001-012 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/27/07 2,4,7,8,9,10,13,155, 670,527 670,527 JOD 0 0 196,464
Thomas Associates
Craig Elementary School:
- PR Additions and Alterations 0-002-013 / / / / 07/22/05 / / 02 - 16 0 0 JOD 0 0 0
06-0599 Additions and Alterations 0-002-013 04/04/07 DONE DONE DONE 12/06/06 12/05/06 07/22/05 01/24/06 02 - 16 6,414,749 5,024,841 JOD 0 0 0
Thomas Associates
07-1311 Reconstruction 0-002-014 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/27/07 2,4,7,8,9,10,13,155, 474,371 474,371 JOD 0 0 138,991
Thomas Associates
Glencliff Elementary:
- PR Additions and Alterations 0-003-010 / / / / 07/22/05 / / 02 - 16 0 0 JOD 0 0 0
06-0600 Additions and Alterations 0-003-010 04/04/07 DONE DONE DONE 12/06/06 12/05/06 07/22/05 01/24/06 02 - 16 5,617,802 4,371,670 JOD 0 0 0
Thomas Associates
07-1312 Additions and Alterations 0-003-011 12/05/08 DONE DONE DONE 01/02/08 12/28/07 02/12/07 02/27/07 02 - 16 474,371 451,299 JOD 0 0 138,991
Thomas Associates
- Reconstruction 0-003-012 / / / / 05/14/09 / / 2,15 0 0 JOD 0 0 0
Rosendale Elementary:
07-0780 Additions and Alterations 0-004-011 05/14/08 DONE DONE DONE 11/13/07 11/08/07 07/22/05 01/24/06 02 - 16 5,382,710 4,507,200 JOD 0 0 0
Thomas Associates
07-1313 Reconstruction 0-004-012 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/28/07 2,4,7,8,9,10,13,155, 485,546 462,474 JOD 0 0 142,265
Thomas Associates
High School:
07-0527 Alterations 0-006-021 03/25/08 DONE DONE DONE 10/11/07 10/05/07 07/22/05 01/24/06 02 - 16 24,272,497 0 JOD 0 0 0
Thomas Associates
05-0521 Reconstruction 0-006-022 12/20/05 DONE DONE DONE 12/28/05 12/27/05 12/09/05 12/05/05 7 294,919 294,919 JOD 0 0 0
Thomas Associates
06-0695 Additions and Alterations 0-006-023 05/24/07 DONE DONE DONE 12/29/06 12/28/06 / / 01/24/06 02 - 16 29,000,000 28,661,274 JOD 0 0 0
Thomas Associates
07-1314 Reconstruction 0-006-024 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/27/07 2,4,7,8,9,10,13,155, 1,161,626 1,161,626 JOD 0 0 340,356
Thomas Associates
07-2343 Reconstruction 0-006-025 08/01/07 DONE DONE DONE 07/08/08 06/30/08 06/30/08 01/28/08 2,15 454,850 454,850 JOD 0 0 0
Thomas Associates
Hillside Elementary:
07-0782 Additions and Alterations 0-007-011 05/09/08 DONE DONE DONE 11/13/07 11/07/07 07/22/05 01/24/06 02 - 16 5,706,010 0 JOD 0 0 0
Thomas Associates
07-1315 Reconstruction 0-007-012 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/27/07 2,4,7,8,9,10,13,155, 464,133 464,133 JOD 0 0 135,991
Thomas Associates
Iroquois Middle School:
07-0781 Alterations 0-008-013 05/14/08 DONE DONE DONE 11/13/07 11/08/07 07/22/05 01/24/06 02 - 16 4,335,639 0 JOD 0 0 0
Thomas Associates
07-1316 Reconstruction 0-008-014 12/05/08 DONE DONE DONE 01/02/08 12/28/07 01/30/07 02/28/07 2,4,7,8,9,10,13,155, 490,235 490,235 JOD 0 0 143,639
Thomas Associates
Birchwood Elementary:
07-0783 Additions and Alterations 0-021-007 05/09/08 DONE DONE DONE 11/13/07 11/08/07 07/22/05 01/24/06 02 - 16 5,379,093 4,503,583 JOD 0 0 0
Thomas Associates
07-1317 Additions and Alterations 0-021-008 12/05/08 DONE DONE DONE 01/02/08 12/28/07 02/12/07 02/27/07 02 - 16 485,468 462,396 JOD 0 0 142,242
Thomas Associates
Leased Bus Facility:
- Reconstruction 5-023-004 / / / / / / / / 0 0 JOD 0 0 0
05-0066TQ Temporary Quarters 5-023-L02 07/22/05 DONE DONE DONE 03/04/05 03/04/05 / / / / 02 - 16 4,106,535 419,328 JOD 0 0 0
District-wide Technology:
07-1161 Reconstruction 7-999-002 03/26/08 DONE DONE DONE 12/19/07 12/18/07 07/25/07 01/24/07 10,13,14,16 3,126,114 3,126,114 JOD 0 0 0
Thomas Associates
08-0476 Reconstruction 7-999-003 11/20/08 DONE DONE DONE 10/06/08 10/03/08 09/24/08 01/24/06 13,16 1,868,640 0 JOD 0 0 0
Thomas Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School/Middle School:
04-1477 Reconstruction 0-001-011 06/30/05 DONE DONE DONE 06/27/05 06/27/05 08/27/04 06/21/05 2,9,155,15,16 935,000 935,000 HCM 0 0 0
Jack Eisenbach - Engineer
04-0961 Reconstruction 0-001-012 04/28/05 DONE DONE DONE 03/11/05 03/11/05 08/30/04 03/09/05 2,9,155,15,16 690,125 690,125 HCM 0 0 0
07-1620 Reconstruction 0-001-013 07/08/08 DONE DONE DONE 02/14/08 02/12/08 07/05/07 10/15/07 2,4,7,8,9,10,155,15, 682,000 2,067,000 HCM 0 0 0
Griffith Dardanelli,Architects,PC
- Reconstruction 0-001-014 / / / / 02/04/08 / / 2,4,15 0 0 HCM 0 0 0
08-0112 Reconstruction 0-001-015 02/12/09 DONE DONE DONE 08/04/08 07/28/08 02/04/08 10/16/07 2,7,8,155,15,16 8,351,000 6,772,000 HCM 0 0 676,811
Griffith Dardanelli,Architects,PC
- Reconstruction 0-001-016 / / / / 02/04/08 / / 2,4,7,8,155,15,16 0 0 HCM 0 0 0
- Reconstruction 0-001-017 / / / / 11/06/09 / / 7 0 0 HCM 0 0 0
- Reconstruction 0-001-018 / / / / 11/10/09 / / 2,4,8,9,155,15,16 0 0 HCM 0 0 0
Schonowe School:
06-0965 Reconstruction 0-003-004 02/23/07 DONE DONE DONE 02/21/07 02/20/07 02/05/07 02/12/07 2,9 40,000 40,000 HCM 0 0 0
Jack Eisenbach - Engineer
- Reconstruction 0-003-005 / / / / 02/06/07 / / 2,9 0 0 HCM 0 0 0
- Reconstruction 0-003-006 / / / / 03/01/07 / / 2 0 67,130 HCM 0 0 0
07-1622 Reconstruction 0-003-007 06/04/08 DONE DONE DONE 02/14/08 02/12/08 07/05/07 10/16/07 2,9,155,15,16 680,000 72,684 HCM 0 0 0
Griffith Dardanelli,Architects,PC
Jefferson Elementary:
- Reconstruction 0-005-012 / / / / 07/05/07 / / 2,7,8,9,155,16 0 0 HCM 0 0 0
Pine Grove School:
- Reconstruction 0-006-007 / / / / 11/09/07 / / 2,4,15 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
05-0443 Additions and Alterations 0-001-011 03/21/06 DONE DONE DONE 12/14/05 12/12/05 02/02/04 05/18/04 02 - 16 2,634,425 2,189,627 RDR 0 0 0
CWG Architects.P.C.
08-0323 Additions and Alterations 0-001-012 03/10/09 DONE DONE DONE 09/16/08 09/15/08 03/08/07 10/16/07 02 - 16 8,046,710 6,151,085 MGL 0 0 406,335
Collins & Scoville Architects
- PR Additions and Alterations 0-001-013 / / / / 10/01/09 / / 02 - 16 0 0 JOD 0 0 0
Herman L Bradt Elementary:
04-0476 Reconstruction 0-004-012 02/15/05 DONE DONE DONE 12/03/04 12/02/04 02/02/04 03/22/04 2,7,155,15,16 1,285,195 1,285,195 RDR 0 0 0
Cataldo, Waters and Griffith Arch.
05-0674 Reconstruction 0-004-013 05/05/06 DONE DONE DONE 02/09/06 01/30/06 11/10/05 05/18/04 7 860,961 860,961 RDR 0 0 0
CWG Architects.P.C.
08-0324 Reconstruction 0-004-014 03/10/09 DONE DONE DONE 09/16/08 09/15/08 03/08/07 10/16/07 2,4,7,8,9,10,155,15, 2,321,178 2,321,178 MGL 0 0 134,000
Collins & Scoville Architects
07-1937 Reconstruction 0-004-015 04/16/08 DONE DONE DONE 04/08/08 03/28/08 01/30/08 10/16/07 155 318,849 318,849 MGL 0 0 15,942
Collins & Scoville Architects
- PR Additions and Alterations 0-004-016 / / / / 10/01/09 / / 02 - 16 0 0 JOD 0 0 0
Pinewood Elementary School:
04-0477 Reconstruction 0-005-009 02/15/05 DONE DONE DONE 12/03/04 12/02/04 02/02/04 03/22/04 2,7,9,155,15,16 761,945 761,945 RDR 0 0 0
Cataldo, Waters and Griffith Arch.
08-0325 Additions and Alterations 0-005-010 03/10/09 DONE DONE DONE 09/16/08 09/15/08 03/08/07 10/16/07 02 - 16 5,041,638 4,660,568 MGL 0 0 252,100
Collins & Scoville Architects
- PR Additions and Alterations 0-005-011 / / / / 10/01/09 / / 02 - 16 0 0 JOD 0 0 0
Draper Junior High:
05-0444 Additions and Alterations 0-007-010 03/21/06 DONE DONE DONE 12/14/05 12/12/05 02/02/04 05/18/04 02 - 16 797,918 476,973 RDR 0 0 0
CWG Architects.P.C.
08-0326 Additions and Alterations 0-007-011 03/10/09 DONE DONE DONE 09/16/08 09/15/08 03/08/07 10/16/07 02 - 16 4,274,874 4,274,874 MGL 0 0 301,605
Collins & Scoville Architects
07-1791 Reconstruction 0-007-012 03/25/08 DONE DONE DONE 03/15/08 03/11/08 01/30/08 10/16/07 7 1,020,063 1,020,063 MGL 0 0 51,003
Collins & Scoville Architects
- PR Additions and Alterations 0-007-013 / / / / 10/01/09 / / 02 - 16 0 0 JOD 0 0 0
Bus Garage:
04-0475 Additions and Alterations 5-002-006 02/15/05 DONE DONE DONE 12/03/04 12/02/04 02/02/04 03/22/04 02 - 16 262,294 262,294 RDR 0 0 0
Cataldo, Waters and Griffith Arch.
New Bus Garage:
- New Construction 5-011-001 / / / / 10/05/09 / / 02 - 16 0 0 JOD 0 0 0
District Wide:
04-0478 Reconstruction 7-999-002 02/15/05 DONE DONE DONE 12/03/04 12/02/04 02/02/04 03/22/04 16 1,550,000 1,550,000 RDR 0 0 0
Cataldo, Waters and Griffith Arch.
- Reconstruction 7-999-003 / / / / 03/08/07 / / 16 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central Park School:
05-1044 Reconstruction 0-002-009 03/02/07 DONE DONE DONE 03/29/06 03/29/06 09/10/03 01/27/04 7,8,9,155,15,16 1,338,971 1,338,971 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-1320 Additions and Alterations 0-002-010 07/20/09 DONE DONE DONE 03/03/09 02/27/09 / / 01/30/07 02 - 16 5,222,050 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0042SC Visual Structural Inspection 0-002-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Elmer Ave. School:
05-0965 Reconstruction 0-003-008 03/22/07 DONE DONE DONE 03/15/06 03/14/06 09/10/03 01/27/04 7,8,9,155,15,16 1,382,386 1,382,386 DDJ 0 0 0
Synthesis Architects,L.L.P.
04-0410 Reconstruction 0-003-009 04/04/05 DONE DONE DONE 11/16/04 11/12/04 06/18/04 01/27/04 15 184,823 184,823 DDJ 0 0 0
Synthesis Architects,L.L.P.
- PR Additions and Alterations 0-003-010 / / / / 04/20/07 / / 02 - 16 0 0 DDJ 0 0 0
Fulton School:
06-0964 Reconstruction 0-006-004 05/04/07 DONE DONE DONE 02/21/07 02/14/07 09/10/03 01/27/04 7,8,9,155,15,16 1,999,908 1,694,408 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-006-005 / / / / 04/20/07 / / 2,4,8,9,155,15,16 0 0 DDJ 0 0 0
Hamilton School:
04-0956 Reconstruction 0-009-007 06/09/05 DONE DONE DONE 03/10/05 03/09/05 07/30/04 01/27/04 2,155 258,395 258,395 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-1280 Reconstruction 0-009-008 06/16/09 DONE DONE DONE 02/25/09 02/18/09 04/20/07 01/30/07 2,8,9,155,15,16 1,011,750 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
Howe School:
04-0411 Reconstruction 0-011-008 04/04/05 DONE DONE DONE 11/16/04 11/12/04 06/18/04 01/27/04 2,155,15,16 311,296 311,296 DDJ 0 0 0
Synthesis Architects,L.L.P.
04-1030 Reconstruction 0-011-009 06/03/05 DONE DONE DONE 03/23/05 03/22/05 07/30/04 01/27/04 2,4,8,9,155 805,929 805,929 DDJ 0 0 0
Synthesis Architects,L.L.P.
- PR Additions and Alterations 0-011-010 / / / / 04/20/07 / / 02 - 16 0 0 DDJ 0 0 0
Lincoln School:
05-0966 Reconstruction 0-012-007 03/22/07 DONE DONE DONE 03/15/06 03/14/06 09/10/03 01/27/04 7,8,9,155,15,16 660,000 660,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-012-008 / / / / 04/20/07 / / 2,4,9,155,16 0 0 DDJ 0 0 0
Schenectady High:
04-0407 Reconstruction 0-013-012 12/10/04 DONE DONE DONE 11/16/04 11/12/04 06/18/04 01/27/04 155 63,702 63,702 MAC 0 0 0
Synthesis Architects.LLp
04-1065 Reconstruction 0-013-013 06/02/05 DONE DONE DONE 04/01/05 03/31/05 07/30/04 01/27/04 2,7,8,9,155 5,171,290 5,171,290 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0806 Reconstruction 0-013-014 DONE DONE ADD. REQ'D01/24/07 01/23/07 03/07/06 01/27/04 2,8,9,155,16 0 34,101,024 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-0070PR Additions and Alterations 0-013-015 UNREVIEWED 07/21/08 07/15/08 04/20/07 / / 02 - 16 10,335,100 10,335,100 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-0237 Additions and Alterations 0-013-015 04/20/09 DONE DONE DONE 09/03/08 08/25/08 04/20/07 01/30/07 02 - 16 11,635,200 11,635,200 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-013-016 / / / / 10/07/08 / / 2,8 0 0 DDJ 0 0 0
08-1607 Reconstruction 0-013-017 05/19/09 DONE DONE DONE 05/11/09 05/06/09 03/27/09 01/27/04 9 514,085 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0035SC Visual Structural Inspection 0-013-SC2 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 157,880 80,000 JOD 0 0 0
Steinmetz School:
05-0938 Reconstruction 0-014-007 10/04/06 DONE DONE DONE 03/13/06 03/10/06 09/10/03 01/27/04 7,8,9,155,15,16 1,630,000 1,630,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-1606 Reconstruction 0-014-008 05/12/09 DONE DONE DONE 05/11/09 05/06/09 04/20/07 01/27/04 7 383,045 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0045SC Visual Structural Inspection 0-014-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 8,195 8,195 JOD 0 0 0
Mont Pleasant Middle School:
04-1136 Reconstruction 0-015-011 07/01/05 DONE DONE DONE 04/11/05 04/11/05 09/10/03 01/27/04 7,8,9,155,15,16 1,940,000 1,940,000 DDJ 0 0 0
Synthesis Architects.LLp
- Reconstruction 0-015-012 / / / / 04/20/07 / / 2,4,7,9,155,15,16 0 0 DDJ 0 0 0
Oneida School:
05-0790 Reconstruction 0-017-010 08/07/06 DONE DONE DONE 02/21/06 02/17/06 09/10/03 01/27/04 7,8,9,155,15,16 1,189,151 1,189,151 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-017-011 / / / / 04/20/07 / / 2,7,9,155,15,16 0 0 DDJ 0 0 0
- Reconstruction 0-017-012 / / / / 03/10/08 / / 15,16 0 0 DDJ 0 0 0
06-0041SC Visual Structural Inspection 0-017-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Paige School:
05-0896 Reconstruction 0-018-012 10/19/06 DONE DONE DONE 03/08/06 03/07/06 09/10/03 01/27/04 7,8,9,155,15,16 1,290,000 857,908 DDJ 0 0 0
Synthesis Architects,L.L.P.
07-0374PR Additions and Alterations 0-018-013 DONE 09/18/07 / / 04/20/07 / / 02 - 16 0 6,677,751 DDJ 0 0 0
Synthesis Architects,L.L.P.
07-0397 Additions and Alterations 0-018-013 02/27/08 DONE DONE DONE 09/21/07 09/20/07 04/20/07 01/30/07 02 - 16 2,662,000 2,651,523 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0040SC Visual Structural Inspection 0-018-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Pleasant Valley School:
04-1134 Reconstruction 0-019-009 07/15/05 DONE DONE DONE 04/11/05 04/11/05 09/10/03 01/27/04 7,8,9,155,15,16 510,000 510,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-019-010 / / / / 04/20/07 / / 2,4,7,9,10,155,15,16 0 0 DDJ 0 0 0
06-0039SC Visual Structural Inspection 0-019-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Van Corlaer School:
05-1045 Reconstruction 0-021-008 03/02/07 DONE DONE DONE 03/29/06 03/29/06 09/10/03 01/27/04 7,8,9,155,15,16 600,000 600,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-1281 Reconstruction 0-021-009 05/11/09 DONE DONE DONE 02/25/09 02/18/09 04/20/07 01/30/07 2,4,7,8,9,155,15,16 1,031,000 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0043SC Visual Structural Inspection 0-021-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Washington Irving S:
04-1037 Reconstruction 0-022-004 06/03/05 DONE DONE DONE 03/28/05 03/25/05 09/10/03 01/27/04 7,8,9,155,15,16 683,833 523,265 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-022-005 / / / / 07/14/06 / / 15 0 580,014 DDJ 0 0 0
- Reconstruction 0-022-006 / / / / 04/20/07 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0
Yates School:
05-0791 Reconstruction 0-024-008 08/07/06 DONE DONE DONE 02/21/06 02/17/06 09/10/03 01/27/04 7,8,9,155,15,16 1,390,000 1,390,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
- Reconstruction 0-024-009 / / / / 04/20/07 / / 2,9,155,15,16 0 0 DDJ 0 0 0
06-0036SC Visual Structural Inspection 0-024-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Zoller School:
04-0989 Reconstruction 0-025-005 06/14/05 DONE DONE DONE 03/16/05 03/15/05 09/10/03 01/27/04 7,8,9,155,15,16 3,515,641 3,424,400 DDJ 0 0 0
Synthesis Architects.LLp
- Reconstruction 0-025-006 / / / / 04/20/07 / / 2,4,7,8,9,10,155,15, 0 0 DDJ 0 0 0
06-0038SC Visual Structural Inspection 0-025-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Dr. Martin L. King School:
04-1036 Reconstruction 0-027-007 06/30/05 DONE DONE DONE 03/28/05 03/25/05 09/10/03 01/27/04 7,8,9,155,15,16 2,092,844 2,092,844 MAC 0 0 0
Synthesis Architects,L.L.P.
07-0544PR Reconstruction 0-027-008 DONE 10/12/07 / / 04/20/07 / / 2,4,7,8,9,10,155,15, 6,005,300 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
07-2117 Reconstruction 0-027-008 11/24/08 DONE DONE DONE 05/16/08 05/09/08 04/20/07 01/30/07 2,4,7,8,9,10,155,15, 6,005,300 6,005,300 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0044SC Visual Structural Inspection 0-027-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Woodlawn E.S (fmly M.S.):
04-0712 Reconstruction 0-032-007 02/22/05 DONE DONE DONE 01/24/05 01/20/05 09/10/03 01/27/04 7,8,9,155,15,16 341,069 341,069 DDJ 0 0 0
Synthesis Architects.LLp
07-2006 Reconstruction 0-032-008 05/22/08 DONE DONE DONE 04/22/08 04/14/08 04/20/07 01/30/07 2,4,7,9,14,155,15,16 1,213,700 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
08-1401 Reconstruction 0-032-009 05/29/09 DONE DONE DONE 03/19/09 03/12/09 10/07/08 01/30/07 2,16 1,005,580 0 DDJ 0 0 0
Synthesis Architects,L.L.P.
06-0037SC Visual Structural Inspection 0-032-SC1 08/09/06 DONE DONE DONE 06/08/06 06/08/06 / / / / 16 2,556 2,000 JOD 0 0 0
Districtwide:
- Reconstruction 7-999-002 / / / / 03/27/09 / / 15 0 0 DDJ 0 0 0
LEASE @ STEINMERTZ INVESTMENT CNTR.:
- Reconstruction 8-035-L01 / / / / 08/22/06 / / 0 0 DDJ 0 0 0
William Keane ES (St Lukes):
07-1031 Reconstruction 8-036-001 02/27/08 DONE DONE DONE 12/04/07 11/29/07 05/03/07 10/09/07 1,600,000 1,600,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
07-1030 New Construction 8-036-L01 01/24/08 DONE DONE DONE 12/04/07 11/29/07 05/09/07 10/09/07 02 - 16 720,000 720,000 DDJ 0 0 0
Synthesis Architects,L.L.P.
Katharine Burr-Blodgett (Immaculate:
08-0246 Reconstruction 8-037-L01 09/03/08 DONE DONE DONE 09/04/08 07/03/08 07/15/08 06/25/08 800,305 800,305 DDJ 0 0 0
Synthesis Architects,L.L.P.
Franklin D Roosevelt (St Adalberts):
08-0247 Reconstruction 8-038-L01 09/03/08 DONE DONE DONE 09/04/08 07/03/08 07/16/08 06/25/08 1,184,750 1,184,750 DDJ 0 0 0
Synthesis Architects,L.L.P.
k - 8 DOWNTOWN FINE ARTS SCHOOL:
08-0875PR Reconstruction 8-039-L01 UNREVIEWED 12/05/08 12/05/08 10/20/08 / / 0 15,895,497 DDJ 0 0 0
Synthesis Architects,L.L.P.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED