Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/04/08 at 11:27:01




MAHOPAC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lakeview Elementary:
05-1418   Reconstruction               0-001-009  05/07/07     DONE    DONE       DONE      06/27/06   06/26/06   06/08/06   05/23/06   2,7                      600,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
07-2308   Reconstruction               0-001-010                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,8,155,15,16                  0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 
07-1912   Reconstruction               0-001-011  04/21/08     DONE    DONE       DONE      04/03/08   03/25/08   03/11/08   02/12/08   7                        237,600             0  HCM             0           0      237,600
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          Austin Road Elementary:
03-1281   Reconstruction               0-002-010  03/23/04     DONE    DONE       DONE      03/15/04   03/11/04   02/20/04   02/10/04   4,7,13                   110,684       110,684  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
07-2309   Reconstruction               0-002-011                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,155,16                       0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Mahopac Falls Elem:
  -    XX Reconstruction               0-003-003                         CANCELLED            /  /       /  /     04/06/04     /  /     4,7,8,9                        0     8,990,217  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-2310   Reconstruction               0-003-004                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,8,155,15,16                  0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Senior High:
07-2311   Additions and Alterations    0-004-011                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Fulmar Road Elementary:
05-1375XX Additions and Alterations    0-005-008                         CANCELLED          06/14/06   05/21/06   03/06/03     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Blasland, Bouck & Lee, INc          
04-1123   Reconstruction               0-005-009  06/24/05     DONE    DONE       DONE      04/08/05   04/07/05   12/22/04   02/08/05   155,16                   233,450       233,450  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
  -       Reconstruction               0-005-010                                              /  /       /  /     03/03/05     /  /     8,9,10,155,15,16               0     8,990,217  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-2312   Reconstruction               0-005-011                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,8,155,15,16                  0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 
  -       Reconstruction               0-005-012                                              /  /       /  /     04/23/08     /  /     2,4,7,8,9,10,13,155,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Mahopac Middle School:
03-1280   Reconstruction               0-006-007  03/23/04     DONE    DONE       DONE      03/15/04   03/11/04   02/20/04   03/15/04   4,7,13                   187,331       187,331  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
04-0203   Additions and Alterations    0-006-008  01/27/05     DONE    DONE       DONE      09/13/04   09/09/04   08/11/04   05/24/04   02 - 16                  573,636       573,636  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
  -    XX Additions and Alterations    0-006-009                         CANCELLED            /  /       /  /     12/22/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-1203   Reconstruction               0-006-010  07/08/05     DONE    DONE       DONE      04/25/05   04/12/05   04/11/05   05/17/04   4,8,9,10,155,15,16       183,000       183,000  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    
07-2313   Reconstruction               0-006-011                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,15,16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Bus Garage:
07-2314   Reconstruction               5-010-007                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,155,16                       0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Old District Office:
07-2315   Reconstruction               7-012-006                         UNREVIEWED         07/07/08   06/16/08   02/26/08   12/11/07   2,15,16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 ECG ENGINEERING,LLC                 

          Concession Stand/Restrooms:
03-0739   New Construction             7-021-001  06/07/04     DONE    DONE       DONE      11/25/03   11/24/03   04/25/03   05/13/03   02 - 16                  192,000             0  RDR             0           0            0
                                                                                                                                                                                                                                 Anderson-Larocca-Anderson-Haynes    

          FRES Pump Station:
06-1343   New Construction             7-022-001  06/07/07     DONE    DONE       DONE      04/23/07   04/18/07   04/23/07   05/13/03   02 - 16                1,003,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 Arcadis Infrastructure, Environment,

          MSHS Pump Station:
  -    XX Alterations                  7-023-001                         CANCELLED            /  /       /  /       /  /       /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          MHSS Treatment Plant:
  -       New Construction             7-024-001                                              /  /       /  /     07/17/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CARMEL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-02-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Kent Elementary School:
  -    XX Reconstruction               0-001-010                         CANCELLED            /  /       /  /     04/01/04     /  /     8,9,155,15,16                  0     6,960,168  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-001-011                                              /  /       /  /     11/21/07     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Carmel High School:
  -    PR Additions and Alterations    0-003-011                                              /  /       /  /     12/19/03     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-0711SR Additions and Alterations    0-003-012  03/17/05     DONE    DONE       DONE      01/24/05   01/20/05   04/01/04   10/05/04   02 - 16               16,972,720     7,435,186  RDR             0           0            0
                                                                                                                                                                                                                                                                     
04-1352   Additions and Alterations    0-003-012  10/11/05     DONE    DONE       DONE      06/01/05   01/20/05   04/01/04   10/05/04   02 - 16               16,373,570    11,865,960  RDR             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
  -       Reconstruction               0-003-013                                              /  /       /  /     11/21/07     /  /     2,8,9,14,155,16                0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Kent Primary School:
  -    XX Reconstruction               0-004-007                         CANCELLED            /  /       /  /     04/01/04     /  /     8,9,155,15,16                  0    26,901,546  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-004-008                                              /  /       /  /     11/21/07     /  /     2,8,9,155,16                   0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Fine Arts Bldg:
04-1284   Reconstruction               0-007-003  10/11/05     DONE    DONE       DONE      05/18/05   05/02/05   04/01/04   10/05/04   9,155,16                 476,430       476,430  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          George Fisher Middle School:
05-1356   Reconstruction               0-008-007  11/06/06     DONE    DONE       DONE      06/08/06   05/09/06   04/07/00   05/15/01   2,15,16                2,856,300             0  MGL             0           0            0
                                                                                                                                                                                                                                 Chazen Engineering & Land Surveying 
  -       Reconstruction               0-008-010                                              /  /       /  /     01/21/04     /  /     2,9,10,13,155,15,16            0    28,145,262  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-1233   Additions and Alterations    0-008-011  09/09/05     DONE    DONE       DONE      05/09/05   05/02/05   03/31/04   10/05/04   02 - 16                6,000,000     5,384,528  RDR             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
  -       Reconstruction               0-008-012                                              /  /       /  /     11/21/07     /  /     2,8,9,155,16                   0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Mathew Patterson Elementary:
03-1594   Reconstruction               0-010-005  06/01/04     DONE    DONE       DONE        /  /       /  /     03/31/04     /  /     4,7,8,9,155,15,16              0    13,575,759  RDR             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX Reconstruction               0-010-006                         CANCELLED            /  /       /  /     04/01/04     /  /     8,9,155,15,16                  0     9,280,224  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-010-007                                              /  /       /  /     11/21/07     /  /     2,8,155,16                     0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Administration Building:
05-1091   Reconstruction               1-002-005  05/10/06     DONE    DONE       DONE      04/05/06   04/05/06   01/09/06     /  /     7                         87,500             0  RDR             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          :
  -    TQ Temporary Quarters           8-016-L01                                              /  /       /  /     09/20/05     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HALDANE CSD OF PHILIPSTOWN STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-04-01-04
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
02-2443   Additions and Alterations    0-001-009  03/25/04     DONE    DONE       DONE      06/19/03   06/18/03   10/25/02   12/12/02   02 - 16                3,767,086     3,767,086  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
03-1482   Reconstruction               0-001-010  05/21/04     DONE    DONE       DONE      04/26/04   04/26/04   11/13/03   04/20/04   7                         70,841        70,841  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
08-0212   Reconstruction               0-001-011                         UNREVIEWED         08/26/08   08/08/08   06/20/08   05/20/08   2,9,155                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Fuller and D'Angelo                 
06-0058SC Visual Structural Inspection 0-001-SC1  08/08/06     DONE    DONE       DONE      07/07/06   07/07/06     /  /       /  /     16                         5,800         5,800  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Merritt Building:
07-0101   Reconstruction               0-003-007  07/26/07     DONE    DONE       DONE        /  /       /  /     04/17/07   06/05/07   2,155                     30,000             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New High School Annex:
02-2444   New Construction             0-016-001  03/25/04     DONE    DONE       DONE      06/19/03   06/18/03   04/17/02   12/12/02   02 - 16                9,891,514     8,119,373  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-0057SC Visual Structural Inspection 0-016-SC1  08/08/06     DONE    DONE       DONE      07/07/06   07/07/06     /  /       /  /     16                         3,500         3,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage/Admin. Bldg.:
07-0102   Reconstruction               5-006-007  07/26/07     DONE    DONE       DONE        /  /       /  /     04/17/07   06/05/07   2,155                     20,000        20,000  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GARRISON UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-04-04-02
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-2165   Reconstruction               0-001-013  07/29/08     DONE    DONE       DONE      05/27/08   05/22/08   03/05/07   03/21/07   7,8                      175,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 Cosentino Architecture,PLLC         
07-0879SC Visual Structural Inspection 0-001-SC1  11/21/07     DONE    DONE       DONE      09/26/07   09/26/07     /  /       /  /     16                         4,900             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Storage Building:
  -       New Construction             2-008-001                                              /  /       /  /     07/16/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Pavillion:
06-1249PR New Construction             7-007-001  04/30/07     DONE    DONE       DONE      04/02/07   03/28/07   03/17/06   01/24/07   02 - 16                   45,000             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PUTNAM VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-05-03-04
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
03-0591   Reconstruction               0-001-005  11/07/03     DONE    DONE       DONE      11/03/03   10/31/03   04/21/03   11/06/03   155                      100,000       100,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
04-0691   Reconstruction               0-001-006  03/09/05     DONE    DONE       DONE      01/19/05   01/18/05   05/21/04   06/15/04   2,4,7,8,9,155,15,16    6,751,691     6,751,691  DDJ             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
07-0155PR Additions and Alterations    0-001-007               DONE                         08/14/07     /  /     03/15/07     /  /     02 - 16                        0     9,498,170  DDJ             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
07-0392   Additions and Alterations    0-001-007  02/04/08     DONE    DONE       DONE      09/21/07   09/20/07   03/15/07   02/13/07   02 - 16                3,490,000     2,084,122  DDJ             0           0      613,039
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          Middle School:
04-0827   Reconstruction               0-004-008  04/29/05     DONE    DONE       DONE      02/11/05   02/11/05   05/21/04   06/15/04   9,15,16                  704,909       704,909  DDJ             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
  -       Reconstruction               0-004-009                                              /  /       /  /     05/14/08     /  /     9,10,15,16                     0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Putnam Valley High School (new):
04-0439SC Visual Structural Inspection 0-006-SC1  11/23/04     DONE    DONE       DONE      11/23/04   11/23/04     /  /       /  /     16                        57,743        57,743  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Field House:
07-2045   New Construction             7-011-001                         UNREVIEWED         05/01/08   04/24/08   12/27/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BREWSTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-06-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Henry G Wells Middle:
03-1037   Reconstruction               0-001-012  03/24/04     DONE    DONE       DONE      01/26/04   01/26/04   10/29/03   12/10/03   155,15,16                567,343       567,343  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
  -    PR Additions and Alterations    0-001-013                                              /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1748   Reconstruction               0-001-014                       ADDENDUM REQ'D       03/04/08   02/29/08   10/18/04   05/17/07   2,4,7,8,9,14,155,15,           0    14,413,556  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
04-0971   Reconstruction               0-001-015  03/30/05     DONE    DONE       DONE      03/15/05   03/14/05   01/18/05   01/11/05   4,9,13                   189,752       189,752  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0014   Reconstruction               0-001-016  12/22/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                       821,016       821,016  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0394   Reconstruction               0-001-017  12/11/07     DONE    DONE       DONE      09/21/07   09/20/07   03/06/07   05/15/07   2,8,155,15,16            322,000             0  MGL             0           0      185,500
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
05-0356SC Visual Structural Inspection 0-001-SC1  11/21/05     DONE    DONE       DONE      11/14/05   11/14/05     /  /       /  /     16                         4,796         4,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0178SC Visual Structural Inspection 0-001-SC2  09/12/06     DONE    DONE       DONE      08/14/06   08/14/06     /  /       /  /     16                         3,650         3,650  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0184SC Visual Structural Inspection 0-001-SC3  08/17/07     DONE    DONE       DONE      08/07/07   08/07/07     /  /       /  /     16                         3,285             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Garden Street School:
03-1038   Reconstruction               0-002-005  03/24/04     DONE    DONE       DONE      01/26/04   01/26/04   10/29/03   12/10/03   155,15,16                379,259       379,259  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
  -    PR Additions and Alterations    0-002-006                                              /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1749   Reconstruction               0-002-007                       ADDENDUM REQ'D       03/04/08   02/29/08   10/18/04   05/17/07   2,4,7,8,9,14,155,15,           0     6,670,161  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0015   Reconstruction               0-002-008  12/22/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                       222,875       222,875  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0395   Reconstruction               0-002-009  12/11/07     DONE    DONE       DONE      09/21/07   09/20/07   03/06/07   05/15/07   16                       235,000             0  MGL             0           0      135,500
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0176SC Visual Structural Inspection 0-002-SC1  09/12/06     DONE    DONE       DONE      07/14/06   07/14/06     /  /       /  /     16                         5,037         5,037  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          John F Kennedy Elementary:
  -    XX Additions and Alterations    0-003-006                         CANCELLED            /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX Reconstruction               0-003-007                         CANCELLED            /  /       /  /     10/18/04     /  /     2,4,7,8,9,14,155,15,           0     8,120,196  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0016   Reconstruction               0-003-008  12/22/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                     1,617,810     1,617,810  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1750   Reconstruction               0-003-009                       ADDENDUM REQ'D       03/04/08   02/29/08   03/06/07   05/17/07   16                             0     8,120,196  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
05-0358   Visual Structural Inspection 0-003-SC1  11/21/05     DONE    DONE       DONE      11/14/05   11/14/05     /  /       /  /     16                         3,736         3,736  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Brewster High School:
  -    XX Additions and Alterations    0-004-008                         CANCELLED            /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX Reconstruction               0-004-009                         CANCELLED            /  /       /  /     10/18/04     /  /     2,4,8,9,14,155,15,16           0    22,538,376  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0017   Reconstruction               0-004-010  12/22/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                       468,363       468,363  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1751   Reconstruction               0-004-011                       ADDENDUM REQ'D       03/04/08   02/29/08   03/06/07   05/17/07   16                             0    22,538,376  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
05-0359SC Visual Structural Inspection 0-004-SC1  11/21/05     DONE    DONE       DONE      11/14/05   11/14/05     /  /       /  /     16                         3,736         3,736  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0177SC Visual Structural Inspection 0-004-SC2  09/12/06     DONE    DONE       DONE      08/14/06   08/14/06     /  /       /  /     16                         8,145         8,145  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          C.V. Starr Intermediate:
05-0357SC Visual Structural Inspection 0-009-SC1  11/21/05     DONE    DONE       DONE      11/14/05   11/14/05     /  /       /  /     16                         4,656         4,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Greenhouse @ Garden Street School:
05-0875DB Discovered Building          0-011-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   06/30/03     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Administration Bldg:
  -    XX Additions and Alterations    1-005-003                         CANCELLED            /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX Reconstruction               1-005-004                         CANCELLED            /  /       /  /     10/18/04     /  /     2,4,7,8,9,14,155,15,           0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0018   Reconstruction               1-005-005  12/23/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                        87,317             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1752   Reconstruction               1-005-006                       ADDENDUM REQ'D       03/04/08   02/29/08   03/06/07   05/17/07   16                             0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Grnds Maintenance Storage Trailer#1:
05-0876DB Discovered Building          2-012-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Grnds Maintenance Storage Trailer#2:
05-0010DB Discovered Building          2-013-001  03/06/06     DONE    DONE       DONE      07/06/05   07/05/05   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Grnds Maintenance Storage Trailer#3:
05-0877DB Discovered Building          2-014-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Grnds Maintenance Storage Trailer#4:
05-0878DB Discovered Building          2-015-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          CV Star Storage Trailer #5:
05-0879DB Discovered Building          2-016-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Soccer Storage Trailer #6:
05-0880DB Discovered Building          2-017-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Youth Football Storage Trailer #7:
05-0881DB Discovered Building          2-018-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Brewster HS Track Stor.Trailer #8:
05-0882DB Discovered Building          2-019-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          HS Varsity Football Stor.Trailer #9:
05-0883DB Discovered Building          2-020-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          HS Graduation Storage Trailer #10:
05-0884DB Discovered Building          2-021-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          HS Maintenance Storage Trailer #11:
05-0885DB Discovered Building          2-022-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          HS Maintenance Storage Trailer #12:
05-0886DB Discovered Building          2-023-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          HS NJROTC Storage Trailer #13:
05-0887DB Discovered Building          2-024-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          JFK Elementary Gym Storage Trailer14:
05-0888DB Discovered Building          2-025-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage Storage Trailer #15:
05-0889DB Discovered Building          2-026-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage Parts Trailer #16:
05-0890DB Discovered Building          2-027-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage Parts Shed #17:
05-0891DB Discovered Building          2-028-001  03/07/06     DONE    DONE       DONE      03/07/06   03/07/06   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Tennis Courts Storage Shed # 23:
06-0023DB Discovered Building          2-033-001  07/17/06     DONE    DONE       DONE      07/07/06   07/05/06   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Box Trailer-JFK Elementary School:
07-0314DB Discovered Building          2-035-001  12/19/07     DONE    DONE       DONE      09/06/07   09/06/07   05/22/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Box Trailer-Grounds / Maintance Shop:
07-0315DB Discovered Building          2-036-001  12/19/07     DONE    DONE       DONE      09/06/07   09/06/07   05/22/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Box Trailer - Trnsporationg Facility:
07-0316DB Discovered Building          2-037-001  12/19/07     DONE    DONE       DONE      09/06/07   09/06/07   05/22/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Box Trailer- Swing Space:
07-0317DB Discovered Building          2-038-001  09/06/07     DONE    DONE       DONE      09/06/07   09/06/07   05/22/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage:
  -    XX Additions and Alterations    5-006-003                         CANCELLED            /  /       /  /     10/18/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX Reconstruction               5-006-004                         CANCELLED            /  /       /  /     10/18/04     /  /     2,4,7,8,9,14,155,15,           0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0019   Reconstruction               5-006-005  12/22/06     DONE    DONE       DONE      07/07/06   07/05/06   01/18/05   04/07/06   10                        58,319        58,319  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0305   Reconstruction               5-006-006  11/29/06     DONE    DONE       DONE      10/12/06   10/05/06   07/18/06   05/16/06   7                        156,000       156,000  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1753   Reconstruction               5-006-007                       ADDENDUM REQ'D       03/04/08   02/29/08   03/03/08   05/17/07   16                             0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
08-0153   Reconstruction               5-006-008  09/04/08     DONE    DONE       DONE      08/13/08   08/06/08   04/22/08   05/20/08   2,15                           0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Sports Field Power Room #18:
05-0011DB Discovered Building          7-029-001  03/06/06     DONE    DONE       DONE      07/06/05   07/05/05   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Stand # 19:
05-0012DB Discovered Building          7-030-001  03/06/06     DONE    DONE       DONE      07/06/05   07/05/05   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Football Field Box/Tower #20:
05-0013DB Discovered Building          7-031-001  03/06/06     DONE    DONE       DONE      07/06/05   07/05/05   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Pump House/Foggintown Road # 21:
05-0014DB Discovered Building          7-032-001  03/06/06     DONE    DONE       DONE      07/06/05   07/05/05   10/08/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Waste Water Treatment Building:
06-0027DB Discovered Building          7-034-001  07/17/06     DONE    DONE       DONE      07/10/06   07/05/06   01/09/06     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES PUTNAM-WESTCHESTER STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-90-00-00
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Special Ed Bldg B:
04-0481   Reconstruction               0-003-003  01/12/05     DONE    DONE       DONE      12/06/04   12/03/04   11/09/04   04/21/04   15,16                    140,000       140,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0593   Reconstruction               0-003-004  01/25/07     DONE    DONE       DONE      12/06/06   12/05/06   10/16/06   05/16/06   155,16                   995,000       995,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Tech Bldg C:
  -    XX Reconstruction               0-004-003                         CANCELLED            /  /       /  /     12/21/04     /  /     15,16                          0     6,712,800  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Building D:
06-0526   Reconstruction               0-005-002  12/22/06     DONE    DONE       DONE      11/20/06   11/17/06   10/16/06   05/16/06   16                       150,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          School Services A:
  -       Reconstruction               0-006-002                                              /  /       /  /     10/16/06     /  /     16                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED