Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/24/09 at 17:08:48




GILBERTSVILLE-MT. UPTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-02-02-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building:
07-0357PR Additions and Alterations    0-012-003               DONE                         09/13/07     /  /     07/12/02     /  /     02 - 16                        0    15,778,060  MGL             0           0            0
                                                                                                                                                                                                                                 Teitsch-Kent                        
08-0409   Additions and Alterations    0-012-003  03/27/09     DONE    DONE       DONE      09/26/08   09/25/08   07/12/02   12/12/07   02 - 16                8,490,000     8,288,470  DDJ             0           0      381,342
                                                                                                                                                                                                                                 Teitsch-Kent                        

          Storage Building:
  -    DB Discovered Building          2-016-001                                              /  /       /  /     01/29/09     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
08-0410   Additions and Alterations    5-013-002  03/27/09     DONE    DONE       DONE      09/26/08   09/25/08   12/08/95   12/12/07   02 - 16                  661,987       661,987  DDJ             0           0            0
                                                                                                                                                                                                                                 Teitsch-Kent                        

          Press Box:
08-1375   New Construction             7-017-001  03/27/09     DONE    DONE       DONE      03/16/09   03/16/09   01/29/09   12/12/07   02 - 16                   18,800             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Teitsch-Kent                        

          Concession Stant/Athletic Storage:
  -       New Construction             7-018-001                                              /  /       /  /     01/29/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EDMESTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-05-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School:
08-0406   Reconstruction               0-001-009  04/03/09     DONE    DONE       DONE      09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,10,155,15,   4,907,000     4,907,000  JOD             0           0      348,397
                                                                                                                                                                                                                                 King & King, Architects             

          Shop Bus Garage:
08-0407XX Reconstruction               0-003-003  04/03/09               CANCELLED          09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,155,15,16      221,000       221,000  JOD             0           0       11,934
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
08-0408   Reconstruction               5-004-002  04/03/09     DONE    DONE       DONE      09/26/08   09/25/08   02/05/07   10/02/07   2,4,7,8,9,155,15,16      393,000       597,000  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Prin. Residence:
  -       Reconstruction               7-007-001                                              /  /       /  /     02/05/07     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAURENS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-08-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
06-0462   Additions and Alterations    0-001-010  05/09/07     DONE    DONE       DONE      11/10/06   11/09/06   05/23/01   12/20/05   02 - 16               17,100,000    17,045,728  MGL             0           0      338,525
                                                                                                                                                                                                                                 King & King Architects              


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCHENEVUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-09-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Andrew Draper School:
07-2268   Reconstruction               0-001-008  08/08/08     DONE    DONE       DONE      06/16/08   06/06/08   04/18/07   02/05/08   2,4,7,8,9,155,15,16      100,000       100,000  DDJ             0           0            0
                                                                                                                                                                                                                                 James Jordan Associates             
06-0779SC Visual Structural Inspection 0-001-SC1  01/18/07     DONE    DONE       DONE      01/12/07   01/12/07     /  /       /  /     16                        10,416        10,416  JOD             0           0            0
                                                                                                                                                                                                                                                                     
08-1686SC Visual Structural Inspection 0-001-SC2  06/18/09     DONE    DONE       DONE      06/15/09   06/15/09     /  /       /  /     16                        12,594             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-11-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Milford Central School:
05-0707   Additions and Alterations    0-010-005  05/30/06     DONE    DONE       DONE      02/10/06   02/10/06   08/06/04   05/02/05   02 - 16                1,887,944     1,887,944  RDR             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     
07-2079   Reconstruction               0-010-006  05/05/08     DONE    DONE       DONE      05/05/08   04/30/08   04/10/08   04/24/08   15                        16,700        16,700  DDJ             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     
  -    PR Additions and Alterations    0-010-007                                              /  /       /  /     05/01/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-1676   Reconstruction               0-010-008  09/18/09     DONE    DONE       DONE      06/09/09   06/04/09   09/03/08   05/15/09   9,16                     100,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     
  -       Reconstruction               0-010-009                                              /  /       /  /     09/21/09     /  /     16                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0862SC Visual Structural Inspection 0-010-SC1  02/06/07     DONE    DONE       DONE      01/22/07   01/22/07     /  /       /  /     16                        18,795        18,795  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
05-0708   Additions and Alterations    5-009-001  05/30/06     DONE    DONE       DONE      02/10/06   02/01/06   08/06/04   05/02/05   02 - 16                  230,445       230,445  RDR             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     
07-0205   Reconstruction               5-009-002  01/09/07     DONE    DONE       DONE      08/17/07   08/17/07   09/25/06   12/18/06   2,15                      16,977        16,977  MGL             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MORRIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-12-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Morris Central School:
05-1260   Reconstruction               0-001-008  07/19/06     DONE    DONE       DONE      05/19/06   05/17/06   12/01/05   10/20/05   7,9,155,15,16            425,627       425,627  DDJ             0           0       40,625
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
  -       Reconstruction               0-001-009                                              /  /       /  /     09/05/07     /  /     2,8,9,10,13,155,15,1           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Custodial/Maintenance(former I.A.):
05-1261   Reconstruction               0-002-004  07/19/06     DONE    DONE       DONE      05/19/06   05/17/06   02/27/06   10/20/05   2,7                       23,576             0  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
  -       Reconstruction               0-002-005                                              /  /       /  /     08/30/07     /  /     4                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               5-005-005                                              /  /       /  /       /  /       /  /     2,16                           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-005-006                                              /  /       /  /     09/05/07     /  /     2,16                           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
  -    PR New Construction             5-007-001                                              /  /       /  /     08/30/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ONEONTA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-14-00-01
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Valley View Elementary:
05-0922   Reconstruction               0-004-006  08/24/06     DONE    DONE       DONE      03/13/06   03/08/06   03/10/06   12/10/02   2,4,8,9,10,13,155,15      81,968        81,968  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1205   Reconstruction               0-004-007  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,155,15,16    1,805,112     1,805,112  DDJ             0           0      250,244
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          Center Street Elementary:
05-0923   Reconstruction               0-006-010  08/24/06     DONE    DONE       DONE      03/13/06   03/08/06   03/10/06   12/10/02   2,8,9,10,13,155,15,1     432,313       432,313  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1206   Reconstruction               0-006-011  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,   1,978,364             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          Oneonta Jr/Sr High:
05-0924   Reconstruction               0-014-016  08/24/06     DONE    DONE       DONE      03/13/06   03/08/06   03/10/06   12/10/02   2,4,8,9,10,13,155,15   1,743,730     1,743,730  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1207   Reconstruction               0-014-017  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,   6,667,890     6,667,890  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
  -       Reconstruction               0-014-018                                              /  /       /  /     10/17/07     /  /     7                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-0549XX Reconstruction               0-014-019                         CANCELLED          10/17/08   10/15/08   11/26/07   11/14/07   155                            0    20,504,925  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1858   Reconstruction               0-014-020  05/28/08     DONE    DONE       DONE      03/24/08   03/17/08   02/27/08   05/15/07   15                       304,200             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          Great Plains Elementary:
05-0925   Reconstruction               0-017-009  08/24/06     DONE    DONE       DONE      03/13/06   03/08/06   03/10/06   12/10/02   2,4,8,9,10,13,155,15     192,360       192,360  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1208   Reconstruction               0-017-010  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,155,15,16      339,518             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1162   Reconstruction               0-017-011  03/18/08     DONE    DONE       DONE      12/20/07   12/19/07   03/29/07   05/15/07   7                      1,199,137     1,199,137  DDJ             0           0      227,837
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          Riverside Elementary:
05-0926   Reconstruction               0-018-009  08/24/06     DONE    DONE       DONE      03/13/06   03/08/06     /  /     12/10/02   2,4,8,9,10,13,155,15     134,057       134,057  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1209   Reconstruction               0-018-010  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   01/31/07   05/15/07   2,4,7,8,9,10,155,15,     695,925             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
07-1163   Reconstruction               0-018-011  03/18/08     DONE    DONE       DONE      12/20/07   12/19/07   03/29/07   05/15/07   7                      1,024,127     1,024,127  DDJ             0           0      192,000
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          District Offices:
05-1424TQ Temporary Quarters           1-027-002  03/14/07     DONE    DONE       DONE      06/29/06   06/05/06   06/28/06     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          District Maintenace Storage Bldg:
04-1297DB Discovered Building          3-023-001  02/08/06     DONE    DONE       DONE      05/19/05   05/19/05   10/18/96     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage Reconstruction:
  -    XX Reconstruction               5-001-001                         CANCELLED            /  /       /  /     02/20/07     /  /     15                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          New Bus Garage:
07-1210   Reconstruction               5-019-002  06/27/08     DONE    DONE       DONE      12/24/07   12/21/07   12/28/07   05/15/07   15                        26,469             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          New Press Box/Concession Stand:
03-0816DB Discovered Building          7-025-001  12/24/04     DONE    DONE       DONE      12/11/03   12/11/00   08/10/99     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UNATEGO (OTEGO-UNADILLA) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-16-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Otego Elementary School:
08-0520   Reconstruction               0-001-007  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   03/06/07   05/15/07   2,4,7,8,9,10,13,155,     109,680       109,680  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-1213   Reconstruction               0-001-008  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   10/10/08   05/15/07   2,4,7,8,9,10,13,155,   3,676,695     3,676,695  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Unadilla Elementary School:
08-0521   Reconstruction               0-009-008  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   07/05/06   05/15/07   8,9,155,15,16            122,220       122,220  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-1214   Additions and Alterations    0-009-009  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   03/06/07   05/15/07   02 - 16                4,701,600             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Unatego Jr/Sr High:
08-0522   Reconstruction               0-015-010  03/31/09     DONE    DONE       DONE      10/14/08   10/09/08   03/06/07   05/15/07   2,16                   3,255,000     3,255,000  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -    XX Reconstruction               0-015-011  02/28/08               CANCELLED            /  /       /  /     03/06/07     /  /     2,4,7,8,9,10,155,15,   2,603,086     2,603,086  HCM             0           0      140,567
                                                                                                                                                                                                                                                                     
07-0525   Reconstruction               0-015-012  10/11/07     DONE    DONE       DONE      10/11/07   10/10/07   08/14/07   05/15/07   2,4,16                   663,519       663,519  HCM             0           0       37,821
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
07-1464   Reconstruction               0-015-013  02/28/08     DONE    DONE       DONE      01/23/08   01/23/08   12/26/07   05/15/07   2,4,7                  2,603,086     2,603,086  HCM             0           0      140,567
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Storage Building@Unadilla Elementary:
08-0117   New Construction             2-019-001  12/10/08     DONE    DONE       DONE      08/04/08   07/30/08   03/08/07   05/15/07   02 - 16                   89,500             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Storage Building @ Otego Elementary:
08-0118   New Construction             2-020-001  12/10/08     DONE    DONE       DONE      08/04/08   07/30/08   03/08/07   05/15/07   02 - 16                   89,500             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Bus Garage:
05-1299   Reconstruction               5-006-004  07/11/06     DONE    DONE       DONE      05/31/06   05/17/06   08/05/04   07/09/06   2,8,16                   390,000       390,000  MAC             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-1215   Reconstruction               5-006-005  04/29/09     DONE    DONE       DONE      02/18/09   02/09/09   03/06/07   05/15/07   2,4,7,8,16               489,200             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




COOPERSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-17-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
05-0478   Reconstruction               0-002-008  04/03/06     DONE    DONE       DONE      12/21/05   12/20/05   12/30/04   05/17/05   2,4,7,16               1,027,400     1,027,400  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -    PR Additions and Alterations    0-002-009                                              /  /       /  /     07/05/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1077   Reconstruction               0-002-010  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,4,7,8,9,10,14,155,   1,137,216       658,416  MGL             0           0      175,113
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-0459   Reconstruction               0-002-011  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,10,155,15,16   2,212,326     2,212,326  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Junior/Senior High School:
05-0479   Reconstruction               0-006-006  04/03/06     DONE    DONE       DONE      12/21/05   12/20/05   01/03/05   05/17/05   2,4,7,9,16             1,469,943     1,469,943  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -    PR Additions and Alterations    0-006-007                                              /  /       /  /     07/05/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1078   Reconstruction               0-006-008  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,8,9,155,15,16          694,488       694,488  MGL             0           0      172,586
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-0460   Reconstruction               0-006-009  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,10,155,15,16   2,784,791     2,784,791  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Playground Equipment Storage Shed:
04-0755DB Discovered Building          2-010-001  11/01/05     DONE    DONE       DONE      02/01/05   02/01/05   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Playground Storage Shed #2:
  -    DB Discovered Building          2-013-001                                              /  /       /  /     10/26/09     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          :
  -       New Construction             4-012-001                                              /  /       /  /     07/05/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               5-003-008                                              /  /       /  /     07/05/05     /  /     2                              0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1079   Reconstruction               5-003-009  05/28/08     DONE    DONE       DONE      12/10/07   12/07/07   12/29/06   05/15/07   2,4,7,8,9,10,13,155,     388,000       388,000  MGL             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
08-0461   Reconstruction               5-003-010  04/10/09     DONE    DONE       DONE      10/06/08   10/02/08   04/22/08   05/15/07   2,4,8,9,13,155,15,16     463,312       463,312  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          :
  -       New Construction             5-011-001                                              /  /       /  /     07/05/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Soccer Concession Shed:
04-0754DB Discovered Building          7-009-001  11/01/05     DONE    DONE       DONE      02/01/05   02/01/05   10/07/04     /  /                                    0             0  RDR             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RICHFIELD SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-20-01-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-0746   Reconstruction               0-001-017  02/14/08     DONE    DONE       DONE      11/06/07   11/05/07   05/19/06   08/07/07   8                        932,434     1,100,000  MGL             0           0      151,987
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-1374   Reconstruction               0-001-018  10/06/08     DONE    DONE       DONE      01/15/08   01/11/08   07/17/07   08/07/07   2,4,8,9,10,13,15,16    2,167,566     2,000,000  MGL             0           0      361,984
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-001-019                                              /  /       /  /     08/01/07     /  /     2,4,8,9,10,13,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Trasnportation Building:
  -    PR New Construction             5-007-001                                              /  /       /  /     12/28/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Press Box:
  -       New Construction             7-006-001                                              /  /       /  /     08/01/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHERRY VALLEY-SPRINGFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-22-02-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Build. del./FSU/Sold:
04-1188   Reconstruction               0-001-004  07/11/05     DONE    DONE       DONE      04/25/05   04/22/05   08/26/04   11/19/04   2,9,15,16                252,600       252,600  RDR             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          New Main Building:
08-1341   Reconstruction               0-004-003  10/07/09     DONE    DONE       DONE      03/13/09   03/03/09   02/27/07   12/12/07   2,7,8,9,155,15,16      8,050,180             0  MGL             0           0      161,004
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    

          New Transportation Bldg.:
04-1189   Reconstruction               5-012-002  07/11/05     DONE    DONE       DONE      04/25/05   04/22/05   08/26/04   11/19/04   2,4                      136,400       136,400  RDR             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -       Reconstruction               5-012-003                                              /  /       /  /     02/27/07     /  /     2                              0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WORCESTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 47-25-06-04
last updated on 11/24/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-0388PR Additions and Alterations    0-001-005               DONE                         09/20/07     /  /     09/30/03     /  /     02 - 16               16,780,532    16,021,766  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
09-0204   Additions and Alterations    0-001-005               DONE    ADD. REQ'D STARTED   09/14/09   09/10/09   09/30/03   03/12/08   02 - 16               16,780,532    16,021,766  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng
05-0197   Reconstruction               0-001-006  10/26/05     DONE    DONE       DONE      09/16/05   09/15/05   04/04/05   01/27/05   4,7,9,155,16             258,554       258,554  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
  -       Reconstruction               0-001-007                                              /  /       /  /     03/11/09     /  /     2,4,7,8,9,10,14,155,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Annex/Bus Garage:
08-0176   Reconstruction               0-002-003  02/05/09     DONE    DONE       DONE      08/18/08   08/07/08   05/05/94   03/12/08   2,7,8                    278,600       278,600  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng

          New Bus Garage:
08-0175   New Construction             5-003-001  02/05/09     DONE    DONE       DONE      08/18/08   08/07/08   08/30/02   03/12/08   02 - 16                2,736,970     2,736,970  DDJ             0           0            0
                                                                                                                                                                                                                                 Keystone Trozze,LLC Architects & Eng


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED