REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
09-0320 Additions and Alterations 0-001-012 STARTED STARTED UNREVIEWED***SHPO RESPONSE*** 0 HCM 0 0 0
Ashley McGraw Architects
07-0902 Reconstruction 0-001-013 04/29/08 DONE DONE DONE 11/23/07 11/20/07 11/09/07 06/14/06 7 1,254,000 0 HCM 0 0 36,366
Ashley McGraw Architects
Altmar Elementary:
07-0903 Additions and Alterations 0-002-009 04/29/08 DONE DONE DONE 11/23/07 11/20/07 / / 06/14/06 02 - 16 978,180 0 HCM 0 0 28,367
Ashley McGraw Architects
Parish Elementary:
- Reconstruction 0-003-008 / / / / 03/08/06 / / 2,4,7,8,9,14,155,15, 0 6,718,473 HCM 0 0 0
New Middle School:
09-0321 Additions and Alterations 0-005-006 STARTED STARTED UNREVIEWED***SHPO RESPONSE*** 0 HCM 0 0 0
Ashley McGraw Architects
Williamstown Elementary:
07-0904 Reconstruction 0-006-013 04/29/08 DONE DONE DONE 11/23/07 11/20/07 03/08/06 06/14/06 2,4,7,8,9,14,155,15, 1,350,650 0 HCM 0 0 339,596
Ashley McGraw Architects
Storage Bldg @ Williamstown ES:
07-0905 New Construction 2-022-001 04/09/08 DONE DONE DONE 11/23/07 11/20/07 03/08/06 06/14/06 02 - 16 124,950 0 HCM 0 0 0
Ashley McGraw Architects
Transporation Storage Building:
- PR New Construction 2-023-001 / / / / / / / / 02 - 16 0 0 HCM 0 0 0
Altmar Storage Building:
07-0906 New Construction 2-024-001 04/29/08 DONE DONE DONE 11/23/07 11/20/07 10/16/07 06/14/06 02 - 16 124,950 0 HCM 0 0 0
Ashley McGraw Architects
New Transportation Facility:
- PR Additions and Alterations 5-019-003 / / / / 03/08/06 / / 02 - 16 0 0 HCM 0 0 0
Sewage Treatment Plt.:
09-0322 Reconstruction 7-017-002 STARTED STARTED UNREVIEWED***SHPO RESPONSE*** 0 HCM 0 0 0
Ashley McGraw Architects
Concession @ MS:
- PR New Construction 7-020-001 / / / / 03/08/06 / / 02 - 16 0 0 HCM 0 0 0
Concession @ HS:
- PR New Construction 7-021-001 / / / / 03/08/06 / / 02 - 16 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Fulton Jr High School:
08-0275 Reconstruction 0-005-007 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,10,14,155, 1,248,220 2,539,000 HCM 0 0 24,965
Ashley McGraw Architects
07-0020SC Visual Structural Inspection 0-005-SC1 07/09/07 DONE DONE DONE 05/29/07 05/29/07 / / / / 16 1,977 0 JOD 0 0 0
James E. Lannigan:
08-0276 Reconstruction 0-006-006 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,10,14,155, 2,680,602 2,738,000 HCM 0 0 53,612
Ashley McGraw Architects
06-1646SC Visual Structural Inspection 0-006-SC1 07/09/07 DONE DONE DONE 05/29/07 05/29/07 / / / / 16 1,800 0 JOD 0 0 0
Granby Elementary School:
08-0277 Reconstruction 0-009-005 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,14,155,15, 778,623 689,375 HCM 0 0 15,572
Ashley McGraw Architects
Erie Street School:
08-0278 Reconstruction 0-011-003 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,14,15,16 0 2,234,000 HCM 0 0 0
Ashley McGraw Architects
Fairgrieve Elementary:
08-0279 Reconstruction 0-012-007 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,14,155,15, 1,573,262 1,167,846 HCM 0 0 31,465
Ashley McGraw Architects
G. Ray Bodley High School:
07-0947PR Additions and Alterations 0-015-008 11/23/07 / / 04/17/07 / / 02 - 16 0 0 HCM 0 0 0
Ashley McGraw Architects
08-0280 Additions and Alterations 0-015-008 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 02 - 16 14,409,372 12,382,985 HCM 0 0 0
Ashley McGraw Architects
05-0812SC Visual Structural Inspection 0-015-SC1 02/24/06 DONE DONE DONE 01/09/06 01/09/06 / / / / 16 4,700 4,700 JOD 0 0 0
05-1209SC Visual Structural Inspection 0-015-SC2 04/28/06 DONE DONE DONE 04/26/06 04/26/06 / / / / 16 1,653 1,653 JOD 0 0 0
06-1645SC Visual Structural Inspection 0-015-SC3 07/09/07 DONE DONE DONE 05/29/07 05/29/07 / / / / 16 10,295 0 JOD 0 0 0
Volney Elementary:
08-0281 Reconstruction 0-017-007 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,10,14,155, 858,921 596,000 HCM 0 0 17,178
Ashley McGraw Architects
06-1647SC Visual Structural Inspection 0-017-SC1 07/09/07 DONE DONE DONE 05/29/07 05/29/07 / / / / 16 1,800 0 JOD 0 0 0
Education Center:
08-0282 Additions and Alterations 0-018-006 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 02 - 16 1,965,444 2,458,000 HCM 0 0 39,309
Ashley McGraw Architects
Athletic Complex:
08-0283 Reconstruction 7-002-001 04/09/09 DONE DONE DONE 09/09/08 09/03/08 04/17/07 12/12/07 2,4,7,8,9,14,155,15, 152,734 0 HCM 0 0 0
Ashley McGraw Architects
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
09-0336 Reconstruction 0-002-013 STARTED STARTED UNREVIEWED10/23/09 10/20/09 12/26/07 01/21/09 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0
SWBR Architects P.C.
Fairley Elementary:
04-1183 Reconstruction 0-003-012 04/21/05 DONE DONE DONE 04/21/05 / / 12/01/04 04/07/05 2,7 100,000 100,000 JOD 0 0 0
James Jordan Associates
04-1272 Reconstruction 0-003-013 05/16/05 DONE DONE DONE 05/18/05 05/18/05 04/15/05 04/07/05 2,4,7,8,9,155,15,16 3,413,291 3,413,291 JOD 0 0 0
James Jordan Associates
09-0337 Reconstruction 0-003-014 STARTED STARTED UNREVIEWED10/23/09 10/21/09 12/26/07 01/21/09 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
SWBR Architects P.C.
Kenney Middle School (Cayuga Street):
08-1630 Reconstruction 0-004-011 06/05/09 DONE DONE DONE 05/18/09 04/12/09 12/26/07 01/21/09 2,4,7,8,9,155,15,16 330,200 0 JOD 0 0 0
SWBR Architects P.C.
09-0338 Reconstruction 0-004-012 STARTED STARTED UNREVIEWED10/23/09 10/21/09 09/18/09 01/21/09 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0
SWBR Architects P.C.
Bus Garage:
- Reconstruction 5-006-008 / / / / 12/26/07 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brewerton Elementary:
07-0398 Reconstruction 0-001-012 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,8,9,155,15,16 589,869 684,300 MGL 0 0 44,830
Ashley McGraw Architects
Cole Elementary at Constantia:
07-0399 Reconstruction 0-002-011 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,9,155,15,16 1,477,630 803,850 MGL 0 0 112,299
Ashley McGraw Architects
Cleveland Elementary:
07-0400 Reconstruction 0-003-010 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,155,16 243,445 407,250 MGL 0 0 18,501
Ashley McGraw Architects
Paul V Moore High School:
07-0401 Reconstruction 0-005-010 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,8,9,155,15,16 310,815 181,500 MGL 0 0 23,621
Ashley McGraw Architects
Hawk Primary School:
07-0402 Reconstruction 0-006-008 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,8,9,155,15,16 2,309,668 1,680,300 MGL 0 0 175,534
Ashley McGraw Architects
Central Square Elementary:
07-0403 Reconstruction 0-007-009 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,8,9,155,15,16 1,864,729 1,545,200 MGL 0 0 141,719
Ashley McGraw Architects
Hastings Mallory Elementary:
07-0404 Reconstruction 0-008-009 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,8,9,155,16 958,655 1,557,000 MGL 0 0 72,857
Ashley McGraw Architects
Middle School:
07-0405 Reconstruction 0-019-005 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,7,8,9,155 3,493,007 3,796,000 MGL 0 0 265,468
Ashley McGraw Architects
District Office:
07-0406 Reconstruction 1-004-006 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 2,4,9,16 125,398 0 MGL 0 0 0
Ashley McGraw Architects
Maintenance Garage at Dist. Office:
07-0407 New Construction 3-024-001 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 02 - 16 56,365 0 MGL 0 0 0
Ashley McGraw Architects
Bus Garage:
07-0408 Reconstruction 5-009-004 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 4,8 56,365 36,750 MGL 0 0 0
Ashley McGraw Architects
Transportation Center:
07-0409 Reconstruction 5-020-003 03/06/08 DONE DONE DONE 09/24/07 09/21/07 12/15/06 01/30/07 7,10,16 317,704 552,000 MGL 0 0 0
Ashley McGraw Architects
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New Haven Elementary:
06-0198 Reconstruction 0-001-007 11/09/06 DONE DONE DONE 09/05/06 08/31/06 12/19/03 05/16/06 2,8,9,10,14,155,15,1 40,365 40,365 MAC 0 0 0
Bernier Carr Associates
06-0949 Reconstruction 0-001-008 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 8,155,16 350,096 350,096 HCM 0 0 0
Bernier Carr Associates
09-0200 Reconstruction 0-001-009 DONE ADD. REQ'D STARTED 09/14/09 09/08/09 05/01/08 03/24/08 2,4,7,8,10,155,15,16 0 0 HCM 0 0 0
Bernier Carr Associates
08-0046 Reconstruction 0-001-010 07/28/08 DONE DONE DONE 07/21/08 07/03/08 06/02/08 03/04/08 2,15 48,500 0 HCM 0 0 0
Bernier Carr Associates
Palermo Elementary School:
06-0199 Reconstruction 0-002-008 11/09/06 DONE DONE DONE 09/05/06 08/31/06 12/19/03 05/16/06 2,8,10,155,15,16 142,403 142,403 MAC 0 0 0
Bernier Carr Associates
05-0080 Reconstruction 0-002-009 08/03/05 DONE DONE DONE 08/03/05 08/02/05 07/22/05 06/14/05 2,15,16 137,917 137,917 HCM 0 0 0
Bernier Carr Associates
06-0950 Reconstruction 0-002-010 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 8,155,16 341,730 341,730 HCM 0 0 0
Bernier Carr Associates
09-0201 Reconstruction 0-002-011 DONE ADD. REQ'D STARTED 09/14/09 09/08/09 05/01/08 03/24/08 2,4,7,8,10,155,15,16 0 0 HCM 0 0 0
Bernier Carr Associates
Mexico Elementary School:
06-0200 Reconstruction 0-003-008 11/09/06 DONE DONE DONE 09/05/06 08/31/06 12/19/03 05/16/06 2,4,7,8,9,10,155,15, 96,344 96,344 MAC 0 0 0
Bernier Carr Associates
06-0951 Reconstruction 0-003-009 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 2,8,9,155,16 1,330,826 1,330,826 HCM 0 0 0
Bernier Carr Associates
09-0202 Reconstruction 0-003-010 DONE ADD. REQ'D STARTED 09/14/09 09/08/09 05/01/08 03/24/08 2,7,8,9,10,155,15,16 0 0 HCM 0 0 0
Bernier Carr Associates
Mexico High School:
06-0952 Reconstruction 0-004-010 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 8,9,10,155,16 1,440,086 1,440,086 HCM 0 0 0
Bernier Carr Associates
06-1672 Reconstruction 0-004-011 08/06/07 DONE DONE DONE 06/27/07 06/27/07 05/24/07 05/05/07 15,16 193,750 193,750 HCM 0 0 0
Bernier Carr Associates
- PR Additions and Alterations 0-004-012 / / / / 05/01/08 / / 02 - 16 0 0 HCM 0 0 0
Mexico Middle School:
06-0201 Reconstruction 0-005-005 11/09/06 DONE DONE DONE 09/05/06 08/31/06 12/19/03 05/16/06 2,8,9,10,155,15,16 100,913 100,913 MAC 0 0 0
Bernier Carr Associates
06-0953 Reconstruction 0-005-006 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 8,155,16 1,392,660 1,392,660 HCM 0 0 0
Bernier Carr Associates
- PR Additions and Alterations 0-005-007 / / / / 05/01/08 / / 02 - 16 0 0 HCM 0 0 0
District Office:
- Reconstruction 1-006-002 / / / / 05/01/08 / / 2,155,15,16 0 0 HCM 0 0 0
Bus Garage:
06-0954 Reconstruction 4-008-004 07/11/07 DONE DONE DONE 02/21/07 02/16/07 10/05/06 08/24/06 4,8,155,16 203,137 203,137 HCM 0 0 0
Bernier Carr Associates
09-0203 Additions and Alterations 4-008-005 DONE ADD. REQ'D STARTED 09/14/09 09/08/09 05/01/08 03/24/08 02 - 16 0 0 HCM 0 0 0
Bernier Carr Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
05-0169 Reconstruction 0-001-013 11/18/05 DONE DONE DONE 08/30/05 08/30/05 07/18/05 07/12/05 2,13 75,000 75,000 JOD 0 0 0
M/E Engineering,P.C.
08-0484 Additions and Alterations 0-001-014 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 02 - 16 5,391,400 0 JOD 0 0 160,900
Ashley McGraw Architects
Fitzhugh Park Elementary:
04-0403 Reconstruction 0-002-011 12/01/04 DONE DONE DONE 11/16/04 11/12/04 03/29/04 05/18/04 8 1,108,750 1,108,750 JOD 0 0 0
Stantec Architect/Engineer
08-0485 Reconstruction 0-002-012 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 2,10,14,155,15,16 5,008,300 0 JOD 0 0 147,600
Ashley McGraw Architects
Kingsford Park Elementary:
04-0404 Reconstruction 0-003-012 12/01/04 DONE DONE DONE 11/16/04 11/12/04 03/29/04 05/18/04 8 1,091,250 1,091,250 JOD 0 0 0
Stantec Architect/Engineer
08-0486 Reconstruction 0-003-014 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 2,10,14,155,15,16 4,078,700 0 JOD 0 0 118,100
Ashley McGraw Architects
Riley Elementary:
08-0487 Reconstruction 0-004-016 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 2,4,7,8,9,10,14,155, 3,197,400 0 JOD 0 0 94,400
Ashley McGraw Architects
Fred Leighton Elementary:
08-0488 Reconstruction 0-005-015 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 2,4,7,8,9,10,14,155, 2,363,700 0 JOD 0 0 73,800
Ashley McGraw Architects
Minetto Elementary:
08-0489 Reconstruction 0-008-014 05/27/09 DONE DONE DONE 10/07/08 10/03/08 03/23/07 05/15/07 2,4,7,8,9,10,14,155, 4,293,500 0 JOD 0 0 132,800
Ashley McGraw Architects
High School:
07-1692 Additions and Alterations 0-018-022 11/14/08 DONE DONE DONE 02/23/08 02/19/08 03/23/07 05/15/07 02 - 16 19,575,000 19,575,000 JOD 0 0 0
Ashley McGraw Architects
07-1262 Reconstruction 0-018-023 02/21/08 DONE DONE DONE 12/31/07 12/27/07 11/09/07 05/15/07 2,155,16 2,034,000 0 JOD 0 0 0
Ashley McGraw Architects
08-0089 Reconstruction 0-018-024 07/25/08 DONE DONE DONE 07/22/08 07/21/08 06/20/08 05/15/07 155,15,16 100,000 0 JOD 0 0 0
Ashley McGraw Architects
District Office:
07-1755 Reconstruction 1-006-003 11/14/08 DONE DONE DONE 03/06/08 02/19/08 03/23/07 05/15/07 2,10,14,155,15,16 484,000 0 JOD 0 0 0
Ashley McGraw Architects
New Administration Offices:
- Reconstruction 1-028-006 / / / / 03/26/07 / / 2,10,14,155,15,16 0 0 JOD 0 0 0
District Warehouse:
07-1693 Reconstruction 2-009-004 11/14/08 DONE DONE DONE 02/23/08 02/19/08 03/23/07 05/15/07 2,4,7,8,155,15,16 307,000 0 JOD 0 0 0
Ashley McGraw Architects
Red Barn:
07-1694 Reconstruction 2-010-001 11/14/08 DONE DONE DONE 02/23/08 02/19/08 03/23/07 05/15/07 7 20,000 0 JOD 0 0 0
Ashley McGraw Architects
Bus Storage Bldg:
07-1695 Reconstruction 4-014-003 11/14/08 DONE DONE DONE 02/23/08 02/19/08 03/23/07 05/15/07 2,7,8,15,16 553,000 0 JOD 0 0 0
Ashley McGraw Architects
Transportation Center:
07-1696 Reconstruction 5-007-004 11/14/08 DONE DONE DONE 02/23/08 02/19/08 03/23/07 05/15/07 2,7,8,9,155,15,16 794,000 0 JOD 0 0 0
Ashley McGraw Architects
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Lura Sharp Elementary:
05-0517 Reconstruction 0-002-009 05/26/06 DONE DONE DONE 12/28/05 12/23/05 02/24/04 12/07/04 2,4,8,9,10,155,15,16 2,595,559 2,595,559 HCM 0 0 0
Stantec Architecture
07-1625 Reconstruction 0-002-010 02/03/09 DONE DONE DONE 02/14/08 02/12/08 03/26/07 05/15/07 2,4,8,9,155,15,16 5,185,000 0 HCM 0 0 274,910
SCHOPFER ARCH.
05-0238SC Visual Structural Inspection 0-002-SC2 10/06/05 DONE DONE DONE 10/03/05 10/03/05 / / / / 16 12,000 12,000 JOD 0 0 0
06-0416SC Visual Structural Inspection 0-002-SC3 11/03/06 DONE DONE DONE 09/11/06 09/11/06 / / / / 16 19,980 19,980 JOD 0 0 0
07-0893SC Visual Structural Inspection 0-002-SC4 12/06/07 DONE DONE DONE 10/29/07 10/29/07 / / / / 16 19,900 0 JOD 0 0 0
08-1347SC Visual Structural Inspection 0-002-SC5 03/16/09 DONE DONE DONE 12/08/08 12/08/08 / / / / 16 19,860 0 JOD 0 0 0
Jr/ Sr High School:
05-0518 Additions and Alterations 0-007-008 05/26/06 DONE DONE DONE 12/28/05 12/23/05 02/24/04 12/07/04 02 - 16 13,025,990 10,627,810 HCM 0 0 450,000
Stantec Architecture
07-1626 Reconstruction 0-007-009 02/03/09 DONE DONE DONE 02/14/08 02/12/08 03/26/07 05/15/07 2,4,7,8,9,13,155,15, 3,391,000 0 HCM 0 0 183,272
SCHOPFER ARCH.
05-0239SC Visual Structural Inspection 0-007-SC2 10/06/05 DONE DONE DONE 10/03/05 10/03/05 / / / / 16 18,000 12,000 JOD 0 0 0
06-0417SC Visual Structural Inspection 0-007-SC3 11/06/06 DONE DONE DONE 09/11/06 09/11/06 / / / / 16 19,998 19,998 JOD 0 0 0
07-0894SC Visual Structural Inspection 0-007-SC4 12/06/07 DONE DONE DONE 10/29/07 10/29/07 / / / / 16 19,982 0 JOD 0 0 0
08-1348SC Visual Structural Inspection 0-007-SC5 03/16/09 DONE DONE DONE 12/08/08 12/08/08 / / / / 16 19,490 0 JOD 0 0 0
Bus Garage/Transportation Facility:
05-0519 Additions and Alterations 5-008-003 05/26/06 DONE DONE DONE 12/28/05 12/23/05 02/24/04 12/07/04 02 - 16 275,682 275,682 HCM 0 0 0
Stantec Architecture
07-1627 Additions and Alterations 5-008-004 02/03/09 DONE DONE DONE 02/14/08 02/12/08 03/26/07 05/15/07 02 - 16 797,000 797,000 HCM 0 0 0
SCHOPFER ARCH.
New Concession Stand:
04-0837 New Construction 7-010-001 04/01/05 DONE DONE DONE 02/02/05 02/01/05 02/24/04 / / 02 - 16 22,000 0 HCM 0 0 0
Stantec Consulting Group Inc.
Press Box:
08-1105 New Construction 7-011-001 02/03/09 DONE DONE DONE 01/21/09 01/15/09 11/04/08 05/15/07 02 - 16 45,000 0 HCM 0 0 0
SCHOPFER ARCH.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
08-0405 Reconstruction 0-002-007 03/30/09 DONE DONE DONE 09/26/08 09/24/08 04/24/08 03/18/08 2,8,9,10,155,15,16 3,150,000 0 JOD 0 0 636,300
Ashley McGraw Architects
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elm Street School:
06-1048 Reconstruction 0-002-009 09/24/07 DONE DONE DONE 03/06/07 03/01/07 12/28/05 04/18/06 8,155,15,16 2,212,105 3,834,060 MGL 0 0 0
Ashley McGraw Architects
08-0579 Reconstruction 0-002-010 05/08/09 DONE DONE DONE 10/23/08 10/22/08 01/17/08 03/25/08 2,8,9,155,15,16 2,876,940 3,682,105 MGL 0 0 218,648
Ashley McGraw Architects
John Birdlebough High School:
06-1049 Reconstruction 0-003-011 09/24/07 DONE DONE DONE 03/06/07 03/01/07 12/28/05 04/18/06 2,7,8 5,335,620 5,335,620 MGL 0 0 0
Ashley McGraw Architects
08-0580 Reconstruction 0-003-012 05/08/09 DONE DONE DONE 10/23/08 10/22/08 01/17/08 03/25/08 2,8,9,10,155,15,16 3,856,928 3,856,928 MGL 0 0 293,126
Ashley McGraw Architects
08-0583 Reconstruction 0-003-013 11/07/08 DONE DONE DONE 10/23/08 10/22/08 05/29/08 03/25/08 2 460,204 532,507 HCM 0 0 34,976
Ashley McGraw Architects
Pennellville School:
08-0581 Reconstruction 0-004-006 05/08/09 DONE DONE DONE 10/23/08 10/22/08 01/17/08 03/25/08 2,4,8,9,15,16 789,178 607,334 MGL 0 0 0
Ashley McGraw Architects
Junior High School:
- PR Additions and Alterations 0-005-008 / / / / 12/28/05 / / 02 - 16 0 16,432,578 MGL 0 0 0
06-1050 Additions and Alterations 0-005-008 09/24/07 DONE DONE DONE 03/06/07 03/01/07 12/28/05 04/18/06 02 - 16 21,326,170 19,938,091 MGL 0 0 0
Ashley McGraw Architects
06-1518 Reconstruction 0-005-009 09/07/07 DONE DONE DONE 05/21/07 05/18/07 03/22/07 04/18/06 99,200 99,200 MGL 0 0 0
Ashley McGraw Architects
08-0582 Reconstruction 0-005-010 05/08/09 DONE DONE DONE 10/23/08 10/22/08 01/17/08 03/25/08 2,8 1,056,770 714,601 MGL 0 0 80,315
Ashley McGraw Architects
Athletic Storage Building:
06-1051 New Construction 2-014-001 09/24/07 DONE DONE DONE 03/06/07 03/01/07 01/06/06 04/18/06 02 - 16 581,505 0 MGL 0 0 0
Ashley McGraw Architects
Maint & Operations (Old Bus Garage):
06-1052 Reconstruction 5-001-004 09/24/07 DONE DONE DONE 03/06/07 03/01/07 12/28/05 04/18/06 2,4,7,8,155,15,16 1,053,285 1,053,285 MGL 0 0 0
Ashley McGraw Architects
New Bus Garage:
06-1053 New Construction 5-013-001 09/24/07 DONE DONE DONE 03/06/07 03/01/07 03/31/88 04/18/06 02 - 16 10,869,100 10,869,100 MGL 0 0 0
Ashley McGraw Architects
New Press Box:
06-1054 New Construction 7-015-001 09/24/07 DONE DONE DONE 03/06/07 03/01/07 01/06/06 04/18/06 02 - 16 89,215 0 MGL 0 0 0
Ashley McGraw Architects
District Wide:
- Reconstruction 7-999-002 / / / / 03/11/09 / / 10,13,16 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
East 230 (Special Educ 1 Instr):
- PR Additions and Alterations 0-001-001 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
East 240 (Special Educ 2 Instr):
- Reconstruction 0-002-001 / / / / 07/14/06 / / 4,9 0 0 JOD 0 0 0
West 450 (West Annex 1 Instr):
- Reconstruction 0-003-002 / / / / 07/14/06 / / 2,4,7,8,9,155,16 0 1,678,200 JOD 0 0 0
Central 120 (Annex C):
- Reconstruction 0-006-001 / / / / 07/14/06 / / 4,7,9 0 0 JOD 0 0 0
Burton Ramer Technical Career Center:
- PR Additions and Alterations 0-007-006 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
- Reconstruction 0-007-007 / / / / 09/28/09 / / 2,13,15 0 0 JOD 0 0 0
North 510(Hero Bld):
- PR Additions and Alterations 0-008-004 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
- Reconstruction 0-008-005 / / / / 09/28/09 / / 2,10,15 0 0 JOD 0 0 0
Central 130(Annex C):
- Reconstruction 0-010-002 / / / / 04/06/06 / / 2,7,8,9,155,15,16 0 0 JOD 0 0 0
South 330 (Bldg B-Trades):
- PR Additions and Alterations 0-011-004 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
East 210 (Pre Vocational House):
- Reconstruction 0-012-001 / / / / 04/06/06 / / 2,7,8,9,155,15,16 0 0 JOD 0 0 0
Central 140 (Annex B-youth Corps):
- Reconstruction 0-014-001 / / / / 04/06/06 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
East 220 (Special Education):
- PR Additions and Alterations 0-015-005 / / / / 07/14/06 / / 02 - 16 0 0 JOD 0 0 0
West 440 (West 2):
- Reconstruction 0-025-001 / / / / 07/14/06 / / 4,7,9 0 0 JOD 0 0 0
West 430 (West 3):
- Reconstruction 0-026-001 / / / / 07/14/06 / / 4,7,9 0 0 JOD 0 0 0
West 420 (West 4):
- Reconstruction 0-027-001 / / / / 07/14/06 / / 4,7,9 0 0 JOD 0 0 0
West 460 (Pole Barn Alt. Schl):
- Reconstruction 0-028-001 / / / / 04/06/06 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
West 410 (Teacher Center):
- PR Additions and Alterations 1-037-002 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
South 320 (Warehouse South Stor):
- Reconstruction 2-017-001 / / / / 04/06/06 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
South 340 (Storage Horticult):
- Reconstruction 2-024-001 / / / / 07/14/06 / / 4,7,9 0 0 JOD 0 0 0
North 520 (Bus Garage Maint):
- Reconstruction 5-004-002 / / / / 08/29/05 / / 2,9,155,15,16 0 0 JOD 0 0 0
- PR Additions and Alterations 5-004-003 / / / / 04/06/06 / / 02 - 16 0 0 JOD 0 0 0
North 530 (Bus Drivers Lounge off.):
- Reconstruction 7-020-001 / / / / 04/06/06 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
South 350 (Alternative Ed):
- Reconstruction 8-031-002 / / / / 04/06/06 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
St. Mary's School:
07-1072TQ Temporary Quarters 8-048-002 ADDENDUM REQ'D 12/07/07 11/29/07 / / / / 02 - 16 0 0 JOD 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
EAA Chapter bldg Oswego Airport:
05-0336TQ Temporary Quarters 8-049-001 01/18/06 DONE DONE DONE 11/09/05 11/01/05 09/02/05 / / 0 0 JOD 0 0 0
Adminstrative Offices:
08-1679XX Alterations 8-050-001 07/27/09 CANCELLED 06/15/09 06/15/09 06/15/09 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED