Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 08/21/08 at 08:44:40




CANANDAIGUA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-03-00-05
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Primary School:
04-1197SR Reconstruction               0-004-011  05/10/05     DONE    DONE       DONE      04/25/05   04/25/05   03/19/04   12/04/04   2,4,8,9,155,15,16              0    14,252,942  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0288   Reconstruction               0-004-011  03/16/06     DONE    DONE       DONE      10/24/05   04/25/05   03/19/04   12/14/04   2,4,8,9,155,15,16      1,913,393     1,913,393  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
  -    PR Additions and Alterations    0-004-012                                              /  /       /  /     12/26/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-004-013                                              /  /       /  /     06/10/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-004-014                                              /  /       /  /     08/18/08     /  /     2,8                            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
  -    XX Reconstruction               0-005-009                         CANCELLED            /  /       /  /     03/19/04     /  /     2,4,7,8,9,155,15,16            0    10,659,000  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Field House Lockers:
  -    XX Reconstruction               0-006-001                         CANCELLED            /  /       /  /     03/29/04     /  /     2,7,9,10,155,15,16             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Canandaigua Middle School:
04-1198SR Additions and Alterations    0-007-015  05/10/05     DONE    DONE       DONE      04/25/05   04/25/05   03/19/04   12/04/04   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0289   Additions and Alterations    0-007-015  03/16/06     DONE    DONE       DONE      10/24/05   04/25/05   03/19/04   12/14/04   02 - 16                5,165,626     5,165,626  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
04-0082   Reconstruction               0-007-016  08/12/04     DONE    DONE       DONE      07/23/04   07/22/04   05/27/04   06/19/01   16                       100,000       100,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-007-017                                              /  /       /  /     12/26/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-007-018                                              /  /       /  /     06/10/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-007-019                                              /  /       /  /     08/18/08     /  /     2,8                            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Canandaigua Academy - SHS:
05-0290   Additions and Alterations    0-013-014  03/16/06     DONE    DONE       DONE      10/24/05   10/21/05   03/18/04   12/14/04   02 - 16                8,049,134     7,528,078  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
04-0083   Reconstruction               0-013-015  08/12/04     DONE    DONE       DONE      07/23/04   07/22/04   05/27/04   06/19/01   16                       200,200       200,200  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -       Reconstruction               0-013-016                                              /  /       /  /     12/26/07     /  /     2,7,8,9,155,15,16              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-013-017                                              /  /       /  /     06/10/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-013-018                                              /  /       /  /     08/18/08     /  /     2,7                            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -    XX Reconstruction               5-001-006                         CANCELLED            /  /       /  /     03/19/04     /  /     2,4,7,8,9,13,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Transportation Facility:
04-1466   New Construction             5-021-001  09/13/05     DONE    DONE       DONE      06/24/05   06/23/05   04/14/04   12/14/04   02 - 16                9,003,700     9,003,700  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                

          Field House @ Academy:
  -    XX New Construction             7-022-001                         CANCELLED            /  /       /  /     04/14/04     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Press Box @ Evans Field:
05-0291   New Construction             7-023-001  03/16/06     DONE    DONE       DONE      10/24/05   10/21/05   04/14/04   12/14/04   02 - 16                   45,824             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST BLOOMFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-05-01-04
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr. Sr. High School:
04-0833   Reconstruction               0-001-009  04/11/05     DONE    DONE       DONE      02/16/05   02/16/05   03/12/02   06/15/04   2,4,7,8,9,10,155,15,     888,493       888,493  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR ARCHITECTS                     
04-1039   Reconstruction               0-001-010  08/24/05     DONE    DONE       DONE      03/28/05   03/25/05   03/11/05   06/30/98   2,8,9,155,15,16          495,256       495,256  DDJ             0           0            0
                                                                                                                                                                                                                                 M/E Engineering                     
05-0757   Reconstruction               0-001-011  08/07/06     DONE    DONE       DONE      02/15/06   02/07/06   09/20/05   11/15/05   10,16                    200,000       200,000  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
07-0958   Reconstruction               0-001-012  05/09/08     DONE    DONE       DONE      11/20/07   11/19/07   11/09/07   10/30/07   2,7,8,9,10,155,15,16   2,047,923             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
07-0858   Reconstruction               0-001-013  01/04/08     DONE    DONE       DONE      11/20/07   11/19/07   11/23/07   10/30/07   2,7,15,16              1,385,790             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
08-0022   Reconstruction               0-001-014                         UNREVIEWED         07/21/08   07/01/08   02/05/08   10/30/07   2,4,7,8,9,155,15,16            0    19,925,913  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Elementary School:
04-0834   Reconstruction               0-006-009  04/11/05     DONE    DONE       DONE      02/16/05   02/16/05   03/12/02   06/15/04   2,4,7,8,9,10,155,15,     166,225       166,225  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
04-1040   Reconstruction               0-006-010  08/24/05     DONE    DONE       DONE      03/28/05   03/25/05   03/11/05   06/30/98   2,4,7,8,9,10,155,15,   1,039,565     1,039,565  DDJ             0           0            0
                                                                                                                                                                                                                                 M/E Engineering                     
05-0758   Reconstruction               0-006-011  08/07/06     DONE    DONE       DONE      02/15/06   02/07/06   03/11/05   11/15/05   2,8,9,155,15,16        2,122,800     2,122,800  DDJ             0           0      353,787
                                                                                                                                                                                                                                 SWBR Architects P.C.                
07-0863   Reconstruction               0-006-012  05/09/08     DONE    DONE       DONE      11/21/07   11/19/07   11/09/07   10/30/07   2,8,16                   235,533       235,533  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -    XX Reconstruction               0-006-013                         CANCELLED            /  /       /  /     11/20/07     /  /     2,7,15,16                      0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-0023   Reconstruction               0-006-014                         UNREVIEWED         07/21/08   07/01/08   02/05/08   10/30/07   2,4,7,8,9,155,15,16            0    11,157,276  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          NEW STORAGE BUILDING @ ELEMENTARY SC:
07-0864   New Construction             2-012-001  05/09/08     DONE    DONE       DONE      11/21/07   11/19/07   11/09/07   10/30/07   02 - 16                  156,003             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          NEW STORAGE BUILDING @ HIGH SCHOOL S:
07-0865   New Construction             2-013-001  05/09/08     DONE    DONE       DONE      11/21/07   11/19/07   11/09/07   10/30/07   02 - 16                  155,239             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Bus Garage/Admin.:
03-1497   Reconstruction               5-002-006  05/04/04     DONE    DONE       DONE      04/30/04   04/30/04   12/31/99   02/11/04   2,4,7,8,9,155,15,16       86,185        86,185  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
04-0835   Reconstruction               5-002-007  04/11/05     DONE    DONE       DONE      02/16/05   02/16/05   01/03/05   06/15/04   2,4,7                    136,481       136,481  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
04-1041   Reconstruction               5-002-008  08/24/05     DONE    DONE       DONE      03/28/05   03/25/05   03/11/05   06/30/98   2,8,9,155,15,16           72,027        72,027  DDJ             0           0            0
                                                                                                                                                                                                                                 M/E Engineering                     
07-0859   Reconstruction               5-002-009  01/04/08     DONE    DONE       DONE      11/20/07   11/19/07   11/09/07   10/30/07   2,7                       95,896             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
08-0024   Reconstruction               5-002-010                         UNREVIEWED         07/21/08   07/01/08   02/05/08   10/30/07   2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          District Wide:
06-1500   Reconstruction               7-999-001  06/13/07     DONE    DONE       DONE      05/16/07   05/16/07   05/01/07   11/05/05   10,16                     79,900        79,900  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               7-999-002                                              /  /       /  /     11/09/07     /  /     10,13,16                       0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENEVA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-07-00-01
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          West Street School:
05-1332SC Visual Structural Inspection 0-001-SC1  06/30/06     DONE    DONE       DONE      06/27/06   06/27/06     /  /       /  /     16                         4,125         4,125  JOD             0           0            0
                                                                                                                                                                                                                                                                     
05-1354SC Visual Structural Inspection 0-001-SC2  06/30/06     DONE    DONE       DONE      06/27/06   06/27/06     /  /       /  /     16                         3,818         3,818  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New District Office Building:
06-1321   Reconstruction               1-013-002  05/30/07     DONE    DONE       DONE      04/13/07   04/13/07   11/30/06   01/08/07   7                         30,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects, Pllc            


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GORHAM - MIDDLESEX CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-09-01-06
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Gorham Elementary:
05-0423   Reconstruction               0-001-011  04/27/06     DONE    DONE       DONE      12/07/05   12/05/05   05/11/00   08/16/04   7                        694,000       694,000  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
07-2119   Reconstruction               0-001-013  07/01/08     DONE    DONE       DONE      05/16/08   05/09/08   05/24/07   12/04/07   7,10,16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    

          Middlesex Valley Bldg.:
05-0424   Reconstruction               0-006-007  04/27/06     DONE    DONE       DONE      12/07/05   12/05/05   10/16/95   08/16/04   4,8,9,155,15,16          696,000       696,000  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
07-2120   Reconstruction               0-006-011  07/01/08     DONE    DONE       DONE      05/16/08   05/09/08   05/24/07   12/04/07   7,16                           0             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    

          Marcus Whitman Jr/Sr High:
04-1288   Reconstruction               0-012-011  06/27/05     DONE    DONE       DONE      05/19/05   05/17/05   03/10/00   02/15/05   155                      191,400       191,400  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0425   Reconstruction               0-012-013  04/27/06     DONE    DONE       DONE      12/07/05   12/05/05   10/07/05   08/16/04   2,8,10,155,15,16       3,218,600     3,218,600  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-1235   Reconstruction               0-012-014  06/19/07     DONE    DONE       DONE      03/27/07   03/20/07     /  /     08/16/04   2,4,10,13,15,16        1,499,970     1,499,970  HCM             0           0            0
                                                                                                                                                                                                                                 Sniedze Associates                  
07-2121   Reconstruction               0-012-015  07/01/08     DONE    DONE       DONE      05/16/08   05/09/08   05/24/07   12/04/07   7,10,16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    
07-1422   Reconstruction               0-012-016  01/22/08     DONE    DONE       DONE      01/18/08   12/24/07   01/17/08     /  /     10,13,14,155,16          196,945       196,945  HCM             0           0            0
                                                                                                                                                                                                                                 Sear-Brown Group Inc.               
03-1528FP Reconstruction               0-012-FP1  06/04/04     DONE    DONE       DONE      05/07/04     /  /       /  /       /  /     16                        28,940        28,940  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Environmental Classroom Opportunity:
  -    XX New Construction             0-015-001                         CANCELLED            /  /       /  /     05/07/04     /  /     02 - 16                        0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          :
05-0426XX New Construction             2-017-001  04/27/06               CANCELLED          12/07/05   12/05/05   08/09/05   08/16/04   02 - 16                   83,160             0  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          New Transportation Building:
07-2122   Reconstruction               5-013-002  07/01/08     DONE    DONE       DONE      05/16/08   05/09/08   02/08/08   12/04/07   16                             0             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    

          Water & Piping Building:
06-1236   New Construction             7-018-001  06/19/07     DONE    DONE       DONE      03/27/07   03/20/07     /  /     08/16/04   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Sniedze Associates                  

          Cumming Nature Center:
  -       Reconstruction               8-016-L01                                              /  /       /  /     06/08/05     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MANCHESTER-SHORTSVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-11-01-04
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Manchester-Shortsville Inst. Complex:
03-0864   Reconstruction               0-007-010  03/18/04     DONE    DONE       DONE      12/22/03   12/12/03   09/22/03   12/10/03   155                      287,000       287,000  HCM             0           0            0
                                                                                                                                                                                                                                 Patterson - Mossien Architects P.C. 
03-0865   Reconstruction               0-007-011  03/18/04     DONE    DONE       DONE      12/22/03   12/12/03   09/22/03   12/10/03   2,4,7                  1,514,377     1,514,377  HCM             0           0            0
                                                                                                                                                                                                                                 Patterson - Mossien Architects P.C. 
03-1188   Reconstruction               0-007-012  05/04/04     DONE    DONE       DONE      02/26/04   02/26/04   09/25/03   12/10/03   2,4,7,8,9,10,155,15,   2,038,623     2,038,623  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1662   Reconstruction               0-007-013  04/10/08     DONE    DONE       DONE      06/27/07   06/22/07   11/02/06     /  /     2,4,8,9,155,15,16      2,903,000     2,903,000  HCM             0           0      298,348
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
06-0418SC Visual Structural Inspection 0-007-SC1  11/06/06     DONE    DONE       DONE      10/23/06   10/23/06     /  /       /  /     16                        10,283        10,283  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Storage #1:
  -    DB Discovered Building          2-011-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
06-1663   Reconstruction               5-001-005  04/10/08     DONE    DONE       DONE      06/27/07   06/22/07   11/02/06     /  /     2,4,7,8,9,155,15,16      527,000       527,000  HCM             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NAPELS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-12-01-04
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Naples High School:
07-0193   Additions and Alterations    0-001-010  12/31/07     DONE    DONE       DONE      08/17/07   08/16/07   10/04/06   02/15/07   02 - 16                2,368,600             0  MGL             0           0      111,482
                                                                                                                                                                                                                                 Hunt Engineers,                     
  -       Reconstruction               0-001-011                                              /  /       /  /     12/07/06     /  /     7,10,16                        0    10,220,238  MGL             0           0            0
                                                                                                                                                                                                                                                                     
02-2361FP Reconstruction               0-001-FP1  08/25/03     DONE    DONE       DONE      06/09/03     /  /       /  /       /  /     16                         5,950         5,950  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-1440SC Visual Structural Inspection 0-001-SC1  06/20/05     DONE    DONE       DONE      06/14/05   06/14/05     /  /       /  /     16                        14,646        14,646  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Naples Elementary:
07-0194   Reconstruction               0-002-008  12/31/07     DONE    DONE       DONE      08/17/07   08/16/07   10/04/06   02/15/07   2,4,7,8,9,155,15,16    3,521,400             0  MGL             0           0      174,368
                                                                                                                                                                                                                                 Hunt Engineers,                     
  -       Reconstruction               0-002-009                                              /  /       /  /     12/07/06     /  /     7,10,16                        0     7,862,412  MGL             0           0            0
                                                                                                                                                                                                                                                                     
02-2360FP Reconstruction               0-002-FP1  08/25/03     DONE    DONE       DONE      06/09/03     /  /       /  /       /  /     16                         5,885         5,885  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-1439SC Visual Structural Inspection 0-002-SC1  06/20/05     DONE    DONE       DONE      06/14/05   06/14/05     /  /       /  /     16                        11,675        11,675  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Districtwide:
  -       Reconstruction               7-999-000                                              /  /       /  /       /  /       /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PHELPS CLIFTON SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-13-01-06
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Midlakes MS/bldg.sold now 0-011:
  -    XX Reconstruction               0-001-007                         CANCELLED            /  /       /  /     11/14/07     /  /     2,16                           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Midlakes Middle/High School:
06-1338   Reconstruction               0-011-012  09/27/07     DONE    DONE       DONE      04/18/07   04/16/07   08/14/06   12/13/06   2,4,9,10,155,15,16     1,882,154     1,882,154  DDJ             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1339   Alterations                  0-011-013  09/27/07     DONE    DONE       DONE      04/18/07   04/16/07   04/17/07   12/13/06   02 - 16                  617,846       617,846  DDJ             0           0      617,846
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-011-014                                              /  /       /  /     11/14/07     /  /     2,16                           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-1515SC Visual Structural Inspection 0-011-SC1  05/18/07     DONE    DONE       DONE      05/04/07   05/04/07     /  /       /  /     16                         5,227             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          One Room Schoolhouse:
  -    DB Discovered Building          0-016-001                                              /  /       /  /     04/14/08     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          District Maintenance Facility:
04-1407DB Discovered Building          3-015-001  07/13/07     DONE    DONE       DONE      06/10/05   06/09/05   02/17/05     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HONEOYE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-14-01-04
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
02-2334FP Reconstruction               0-001-FP1  08/25/03     DONE    DONE       DONE      06/02/03     /  /       /  /       /  /     16                         3,700         3,700  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
02-2333FP Reconstruction               0-003-FP1  08/25/03     DONE    DONE       DONE      06/02/03     /  /       /  /       /  /     16                         4,380         4,380  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Green House:
  -    TQ Temporary Quarters           0-009-001                                              /  /       /  /     02/12/04     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Softball Storage Shed:
  -    DB Discovered Building          2-013-001                                              /  /       /  /     12/07/06     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Baseball Storqage Shed:
  -    DB Discovered Building          2-014-001                                              /  /       /  /     12/07/06     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VICTOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-17-01-06
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Education Center:
  -    XX Reconstruction               0-001-009                         CANCELLED            /  /       /  /     06/08/04     /  /     2,9,15,16                      0     1,740,042  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0114   Additions and Alterations    0-001-010  02/28/06     DONE    DONE       DONE      11/01/05   10/31/05   09/24/04   12/20/04   02 - 16                4,865,569     4,478,186  DDJ             0           0    1,171,281
                                                                                                                                                                                                                                 Stantec Architecture                
07-1493   Reconstruction               0-001-011  05/07/08     DONE    DONE       DONE      01/31/08   01/28/08   09/27/07   09/07/07   2,8,9,10,155,15,16     2,329,570             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Primary School:
05-0115   Reconstruction               0-002-009  02/28/06     DONE    DONE       DONE      11/01/05   10/31/05   09/24/04   12/20/04   9,10,155,15,16         2,373,378     2,373,378  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
  -       Reconstruction               0-002-010                                              /  /       /  /     09/27/07     /  /     2,4,7,8,15,16                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
07-1494   Reconstruction               0-002-010  05/07/08     DONE    DONE       DONE      01/31/08   01/28/08     /  /     09/07/07                            932,071             0                  0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Jr/Sr High(fmly Sr. High):
04-1315SR Additions and Alterations    0-005-012  06/10/05     DONE    DONE       DONE      07/13/05   07/12/05   09/24/04   12/20/04   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
05-0038   Reconstruction               0-005-012  08/26/05     DONE    DONE       DONE        /  /       /  /       /  /     12/20/04                          3,316,265     3,316,265  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0116   Additions and Alterations    0-005-013  02/28/06     DONE    DONE       DONE      11/01/05   10/31/05   04/08/05   12/20/04   02 - 16               10,700,480    10,700,480  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
07-1496   Additions and Alterations    0-005-014  05/07/08     DONE    DONE       DONE      01/31/08   01/28/08   09/27/07   09/07/07   02 - 16                5,381,392             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
05-0322SC Visual Structural Inspection 0-005-SC2  11/04/05     DONE    DONE       DONE      11/02/05   11/02/05     /  /       /  /     16                        28,464        28,464  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Maint.Annex(fmly Jr.H Annex):
  -    XX Reconstruction               0-007-006                         CANCELLED            /  /       /  /     09/24/04     /  /     2,4,7,8,9,155,15,16            0     1,006,920  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Intermediate:
04-1316SR Additions and Alterations    0-008-006  06/10/05     DONE    DONE       DONE      05/24/05   05/24/05   09/24/04   12/20/04   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
04-1474   Additions and Alterations    0-008-006  08/26/05     DONE    DONE       DONE      06/27/05   06/24/05   09/24/04   12/20/04   02 - 16                2,129,302     2,129,302  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
05-0117   Reconstruction               0-008-007  02/28/06     DONE    DONE       DONE      11/01/05   10/31/05   04/08/05   12/20/04   2,4,7,8,9,10,155,15,   2,924,829     2,924,829  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
07-1497   Additions and Alterations    0-008-008  05/07/08     DONE    DONE       DONE      01/31/08   01/28/08   09/24/07   09/07/07   02 - 16                2,262,848             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Health & Wellness Center:
  -       New Construction             0-027-001                                              /  /       /  /     03/14/05     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Storage Facility:
04-1475   Alterations                  4-028-001  08/26/05     DONE    DONE       DONE      06/27/05   06/24/05   04/08/05   12/20/04   02 - 16                  329,621       329,621  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                

          Bus Garage:
04-1317SR Additions and Alterations    5-003-007  06/10/05     DONE    DONE       DONE      05/24/05   05/24/05   09/24/04   12/20/04   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
04-1476   Additions and Alterations    5-003-007  08/26/05     DONE    DONE       DONE      06/27/05   06/24/05   09/24/04   12/20/04   02 - 16                2,056,056     2,056,056  DDJ             0           0            0
                                                                                                                                                                                                                                 Stantec Architecture                
07-1495   Reconstruction               5-003-008  05/07/08     DONE    DONE       DONE      01/31/08   01/28/08   09/27/07   09/07/07   2,155,15,16            1,066,019             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                

          Concession Stand:
  -    XX Additions and Alterations    7-004-001                         CANCELLED            /  /       /  /     09/24/04     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES WAYNE-FINGER LAKES STATUS REPORT ON CAPITAL PROJECTS
District No.: 43-90-00-00
last updated on 08/21/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Finger Lakes Educ. Center:
03-1620   Reconstruction               0-001-012  06/30/04     DONE    DONE       DONE      06/15/04   06/14/04   08/11/03   12/15/03   4,7,16                   349,634       349,634  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
04-0858   Reconstruction               0-001-013  05/09/05     DONE    DONE       DONE      03/01/05   02/26/05   11/10/04   01/10/05   2,4,8,9,155,15,16        816,793       816,793  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
06-0153   Reconstruction               0-001-014  12/07/06     DONE    DONE       DONE      08/07/06   08/03/06   07/20/05   06/05/06   8,155,15,16              682,643       656,853  JOD             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            

          Alt. HS Flint Campus(Admin):
03-1621   Reconstruction               0-002-002  06/30/04     DONE    DONE       DONE      06/15/04   06/14/04   08/11/03   12/15/03   7,16                     130,601       130,601  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
04-0859   Reconstruction               0-002-003  05/09/05     DONE    DONE       DONE      03/01/05   02/26/05   11/10/04   01/10/05   2,4,8,9,155,15,16        411,195       410,535  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
06-0154   Reconstruction               0-002-004  12/07/06     DONE    DONE       DONE      08/07/06   08/03/06   07/20/05   06/05/06   155,15,16                 71,312        71,312  JOD             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            

          Auto Shop:
06-0155   Reconstruction               0-012-001  12/07/06     DONE    DONE       DONE      08/07/06   08/03/06   06/21/06   06/05/06   155,16                    15,082        15,082  JOD             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            
  -       Reconstruction               0-012-002                                              /  /       /  /     05/14/08     /  /     10,155                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Occup. Center/Williamson:
03-0456   Reconstruction               0-014-012  05/05/04     DONE    DONE       DONE      10/15/03   08/27/03   09/04/02   12/17/02   16                       546,548       546,548  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
06-0001   Reconstruction               0-014-013  01/04/07     DONE    DONE       DONE      07/06/06   07/03/06   03/24/05   05/09/05   2,4,16                   124,315        63,500  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
05-1280   Reconstruction               0-014-014  07/10/06     DONE    DONE       DONE      05/22/06   05/19/06   07/20/05   12/17/02   155,15,16                406,500       406,500  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
06-0400   Reconstruction               0-014-015  12/07/06     DONE    DONE       DONE      12/07/06   10/25/06   10/11/06   06/05/06   155,15,16                632,885       632,885  JOD             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            
06-0707   Reconstruction               0-014-016  01/19/07     DONE    DONE       DONE      01/03/07   01/03/07   12/11/06   06/05/06   7                      1,110,800     1,110,800  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -       Reconstruction               0-014-017                                              /  /       /  /     10/01/07     /  /     2,4,8,155,15,16                0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-014-018                                              /  /       /  /     05/14/08     /  /     10,155                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Education Center Williamson:
03-0457   Additions and Alterations    0-025-003  05/05/04     DONE    DONE       DONE      10/15/03   08/27/03   09/04/02   12/17/02   02 - 16                1,323,221     1,300,234  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
05-1281   Reconstruction               0-025-004  07/10/06     DONE    DONE       DONE      05/22/06   05/19/06   07/20/05   12/17/02   155,15,16                325,000       325,000  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
06-0401   Reconstruction               0-025-005  12/07/06     DONE    DONE       DONE      12/07/06   10/25/06   10/11/06   06/05/06   155,15,16                322,215       322,215  JOD             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            
06-0708   Reconstruction               0-025-006  01/19/07     DONE    DONE       DONE      01/03/07   01/03/07   12/11/06   06/05/06   7                        255,200       255,200  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -       Reconstruction               0-025-007                                              /  /       /  /     10/01/07     /  /     2,4,8,9,155,15,16              0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Voc Training/Alt HS FL:
06-0156   Reconstruction               0-027-002  12/07/06     DONE    DONE       DONE      08/07/06   08/03/06   08/11/03   06/05/06   2,4,7,8,9,155,15,16       11,366             0  MAC             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            
  -       Reconstruction               0-027-004                                              /  /       /  /     06/20/06     /  /     155,16                         0       503,460  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Handicapped Workshop:
06-0389   Reconstruction               0-028-001  12/07/06     DONE    DONE       DONE      08/03/06   08/03/06     /  /     06/05/06   155,15,16                 15,114        15,114  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-028-002                                              /  /       /  /     05/01/08     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Day Care Teaching Center:
06-0157   Reconstruction               0-030-002  12/07/06     DONE    DONE       DONE      08/07/06   08/03/06   08/11/03   06/05/06   2,7,8,9,155,15,16         29,032        29,032  MAC             0           0            0
                                                                                                                                                                                                                                 Pathfinder Engineers LLP            
  -       Reconstruction               0-030-003                                              /  /       /  /       /  /       /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Pole Barn #5:
03-0557   New Construction             0-045-001  06/14/06     DONE    DONE       DONE      10/27/03   10/15/03   09/09/02   12/17/02   02 - 16                  478,000       478,000  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Wayne Education Center:
03-0458   New Construction             0-046-001  05/05/04     DONE    DONE       DONE      10/15/03   08/27/03   09/09/02   12/17/02   02 - 16                8,980,230     8,980,230  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Wayne Educational Cntr. Portables:
03-0532XX New Construction             0-047-001  06/29/04               CANCELLED          10/28/03   09/24/03   08/12/03   12/17/02   02 - 16                1,835,500             0  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          MAPLE BUILDING ADMINSTRATION:
05-1331   Reconstruction               1-052-001  11/06/06     DONE    DONE       DONE      06/07/06   06/06/06     /  /     04/24/06   2,4,10,14,16             714,811             0  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Seneca County Office Building:
07-1573TQ Temporary Quarters           1-053-001  03/25/08     DONE    DONE       DONE      02/08/08   02/06/08   05/22/07     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Pole Barn #2:
  -       Reconstruction               2-029-002                                              /  /       /  /     07/20/06     /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Special Ed. Storage @ Williamson:
03-0554   New Construction             2-042-001  06/13/06     DONE    DONE       DONE      10/27/03   10/15/03   09/09/02   12/17/02   02 - 16                   45,000             0  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Pole Barn #4:
03-0555   New Construction             2-043-001  06/14/06     DONE    DONE       DONE      10/27/03   10/15/03   09/09/02   12/17/02   02 - 16                  160,000             0  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Technical Facilities Storage:
03-0556   New Construction             2-044-001  06/13/06     DONE    DONE       DONE      10/27/03   10/15/03   09/09/02   12/17/02   02 - 16                  133,500             0  MAC             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Edu-Tech Receiving:
  -       Reconstruction               7-039-002                                              /  /       /  /     05/14/08     /  /     8                              0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          DISTRICTWIDE:
06-0535   Reconstruction               7-999-001  03/20/07     DONE    DONE       DONE      11/21/06   11/20/06   06/19/06   06/05/06   10,13,14,16              584,000       434,000  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -       Reconstruction               7-999-002                                              /  /       /  /     05/14/08     /  /     10,13,16                       0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Day Care/Teaching Center:
  -    XX Reconstruction               8-030-003                         CANCELLED            /  /       /  /     06/20/06     /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Newark Devel Ctr Maple Bldg:
06-1207   Reconstruction               8-033-002  04/25/07     DONE    DONE       DONE      03/22/07   03/21/07   09/25/06   09/25/06   8                        400,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   
  -       Reconstruction               8-033-003                                              /  /       /  /     10/01/07     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Newark Dev Ctr - Eisenhower Bldg:
06-1208   Reconstruction               8-035-002  04/25/07     DONE    DONE       DONE      03/22/07   03/21/07   09/25/06   09/25/06   8                        400,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          NDC:Arcadia/York:
06-1209   Reconstruction               8-037-002  04/25/07     DONE    DONE       DONE      03/22/07   03/21/07   09/25/06   09/25/06   8                        210,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates Arch.   

          Career Recource Center Canandaigua:
03-1548TQ Temporary Quarters           8-048-001  05/10/05     DONE    DONE       DONE      05/13/04   05/13/04   11/13/03     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Perkins Elementary:
  -    TQ Temporary Quarters           8-049-001                                              /  /       /  /     03/08/04     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Kelley Elementary School:
  -    TQ Temporary Quarters           8-050-001                                              /  /       /  /     03/08/04     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Techniplex III - Suite 2:
04-1219TQ Temporary Quarters           8-051-001                       ADDENDUM REQ'D       04/29/05   04/28/05   02/04/05     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED