REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Primary School:
04-1197SR Reconstruction 0-004-011 05/10/05 DONE DONE DONE 04/25/05 04/25/05 03/19/04 12/04/04 2,4,8,9,155,15,16 0 14,252,942 DDJ 0 0 0
05-0288 Reconstruction 0-004-011 03/16/06 DONE DONE DONE 10/24/05 04/25/05 03/19/04 12/14/04 2,4,8,9,155,15,16 1,913,393 1,913,393 DDJ 0 0 0
Stantec Architecture
- PR Additions and Alterations 0-004-012 / / / / 12/26/07 / / 02 - 16 0 0 DDJ 0 0 0
- PR Additions and Alterations 0-004-013 / / / / 06/10/08 / / 02 - 16 0 0 DDJ 0 0 0
- Reconstruction 0-004-014 / / / / 08/18/08 / / 2,8 0 0 DDJ 0 0 0
Elementary School:
- XX Reconstruction 0-005-009 CANCELLED / / / / 03/19/04 / / 2,4,7,8,9,155,15,16 0 10,659,000 DDJ 0 0 0
Field House Lockers:
- XX Reconstruction 0-006-001 CANCELLED / / / / 03/29/04 / / 2,7,9,10,155,15,16 0 0 DDJ 0 0 0
Canandaigua Middle School:
04-1198SR Additions and Alterations 0-007-015 05/10/05 DONE DONE DONE 04/25/05 04/25/05 03/19/04 12/04/04 02 - 16 0 0 DDJ 0 0 0
05-0289 Additions and Alterations 0-007-015 03/16/06 DONE DONE DONE 10/24/05 04/25/05 03/19/04 12/14/04 02 - 16 5,165,626 5,165,626 DDJ 0 0 0
Stantec Architecture
04-0082 Reconstruction 0-007-016 08/12/04 DONE DONE DONE 07/23/04 07/22/04 05/27/04 06/19/01 16 100,000 100,000 DDJ 0 0 0
Thomas Associates
- PR Additions and Alterations 0-007-017 / / / / 12/26/07 / / 02 - 16 0 0 DDJ 0 0 0
- PR Additions and Alterations 0-007-018 / / / / 06/10/08 / / 02 - 16 0 0 DDJ 0 0 0
- Reconstruction 0-007-019 / / / / 08/18/08 / / 2,8 0 0 DDJ 0 0 0
New Canandaigua Academy - SHS:
05-0290 Additions and Alterations 0-013-014 03/16/06 DONE DONE DONE 10/24/05 10/21/05 03/18/04 12/14/04 02 - 16 8,049,134 7,528,078 DDJ 0 0 0
Stantec Architecture
04-0083 Reconstruction 0-013-015 08/12/04 DONE DONE DONE 07/23/04 07/22/04 05/27/04 06/19/01 16 200,200 200,200 DDJ 0 0 0
Thomas Associates
- Reconstruction 0-013-016 / / / / 12/26/07 / / 2,7,8,9,155,15,16 0 0 DDJ 0 0 0
- PR Additions and Alterations 0-013-017 / / / / 06/10/08 / / 02 - 16 0 0 DDJ 0 0 0
- Reconstruction 0-013-018 / / / / 08/18/08 / / 2,7 0 0 DDJ 0 0 0
Bus Garage:
- XX Reconstruction 5-001-006 CANCELLED / / / / 03/19/04 / / 2,4,7,8,9,13,155,15, 0 0 DDJ 0 0 0
Transportation Facility:
04-1466 New Construction 5-021-001 09/13/05 DONE DONE DONE 06/24/05 06/23/05 04/14/04 12/14/04 02 - 16 9,003,700 9,003,700 DDJ 0 0 0
Stantec Architecture
Field House @ Academy:
- XX New Construction 7-022-001 CANCELLED / / / / 04/14/04 / / 02 - 16 0 0 DDJ 0 0 0
Press Box @ Evans Field:
05-0291 New Construction 7-023-001 03/16/06 DONE DONE DONE 10/24/05 10/21/05 04/14/04 12/14/04 02 - 16 45,824 0 DDJ 0 0 0
Stantec Architecture
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr. Sr. High School:
04-0833 Reconstruction 0-001-009 04/11/05 DONE DONE DONE 02/16/05 02/16/05 03/12/02 06/15/04 2,4,7,8,9,10,155,15, 888,493 888,493 DDJ 0 0 0
SWBR ARCHITECTS
04-1039 Reconstruction 0-001-010 08/24/05 DONE DONE DONE 03/28/05 03/25/05 03/11/05 06/30/98 2,8,9,155,15,16 495,256 495,256 DDJ 0 0 0
M/E Engineering
05-0757 Reconstruction 0-001-011 08/07/06 DONE DONE DONE 02/15/06 02/07/06 09/20/05 11/15/05 10,16 200,000 200,000 DDJ 0 0 0
SWBR Architects P.C.
07-0958 Reconstruction 0-001-012 05/09/08 DONE DONE DONE 11/20/07 11/19/07 11/09/07 10/30/07 2,7,8,9,10,155,15,16 2,047,923 0 DDJ 0 0 0
SWBR Architects P.C.
07-0858 Reconstruction 0-001-013 01/04/08 DONE DONE DONE 11/20/07 11/19/07 11/23/07 10/30/07 2,7,15,16 1,385,790 0 DDJ 0 0 0
SWBR Architects P.C.
08-0022 Reconstruction 0-001-014 UNREVIEWED 07/21/08 07/01/08 02/05/08 10/30/07 2,4,7,8,9,155,15,16 0 19,925,913 DDJ 0 0 0
SWBR Architects P.C.
Elementary School:
04-0834 Reconstruction 0-006-009 04/11/05 DONE DONE DONE 02/16/05 02/16/05 03/12/02 06/15/04 2,4,7,8,9,10,155,15, 166,225 166,225 DDJ 0 0 0
SWBR Architects P.C.
04-1040 Reconstruction 0-006-010 08/24/05 DONE DONE DONE 03/28/05 03/25/05 03/11/05 06/30/98 2,4,7,8,9,10,155,15, 1,039,565 1,039,565 DDJ 0 0 0
M/E Engineering
05-0758 Reconstruction 0-006-011 08/07/06 DONE DONE DONE 02/15/06 02/07/06 03/11/05 11/15/05 2,8,9,155,15,16 2,122,800 2,122,800 DDJ 0 0 353,787
SWBR Architects P.C.
07-0863 Reconstruction 0-006-012 05/09/08 DONE DONE DONE 11/21/07 11/19/07 11/09/07 10/30/07 2,8,16 235,533 235,533 DDJ 0 0 0
SWBR Architects P.C.
- XX Reconstruction 0-006-013 CANCELLED / / / / 11/20/07 / / 2,7,15,16 0 0 DDJ 0 0 0
08-0023 Reconstruction 0-006-014 UNREVIEWED 07/21/08 07/01/08 02/05/08 10/30/07 2,4,7,8,9,155,15,16 0 11,157,276 DDJ 0 0 0
SWBR Architects P.C.
NEW STORAGE BUILDING @ ELEMENTARY SC:
07-0864 New Construction 2-012-001 05/09/08 DONE DONE DONE 11/21/07 11/19/07 11/09/07 10/30/07 02 - 16 156,003 0 DDJ 0 0 0
SWBR Architects P.C.
NEW STORAGE BUILDING @ HIGH SCHOOL S:
07-0865 New Construction 2-013-001 05/09/08 DONE DONE DONE 11/21/07 11/19/07 11/09/07 10/30/07 02 - 16 155,239 0 DDJ 0 0 0
SWBR Architects P.C.
Bus Garage/Admin.:
03-1497 Reconstruction 5-002-006 05/04/04 DONE DONE DONE 04/30/04 04/30/04 12/31/99 02/11/04 2,4,7,8,9,155,15,16 86,185 86,185 DDJ 0 0 0
SWBR Architects P.C.
04-0835 Reconstruction 5-002-007 04/11/05 DONE DONE DONE 02/16/05 02/16/05 01/03/05 06/15/04 2,4,7 136,481 136,481 DDJ 0 0 0
SWBR Architects P.C.
04-1041 Reconstruction 5-002-008 08/24/05 DONE DONE DONE 03/28/05 03/25/05 03/11/05 06/30/98 2,8,9,155,15,16 72,027 72,027 DDJ 0 0 0
M/E Engineering
07-0859 Reconstruction 5-002-009 01/04/08 DONE DONE DONE 11/20/07 11/19/07 11/09/07 10/30/07 2,7 95,896 0 DDJ 0 0 0
SWBR Architects P.C.
08-0024 Reconstruction 5-002-010 UNREVIEWED 07/21/08 07/01/08 02/05/08 10/30/07 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0
SWBR Architects P.C.
District Wide:
06-1500 Reconstruction 7-999-001 06/13/07 DONE DONE DONE 05/16/07 05/16/07 05/01/07 11/05/05 10,16 79,900 79,900 DDJ 0 0 0
SWBR Architects P.C.
- Reconstruction 7-999-002 / / / / 11/09/07 / / 10,13,16 0 0 DDJ 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
West Street School:
05-1332SC Visual Structural Inspection 0-001-SC1 06/30/06 DONE DONE DONE 06/27/06 06/27/06 / / / / 16 4,125 4,125 JOD 0 0 0
05-1354SC Visual Structural Inspection 0-001-SC2 06/30/06 DONE DONE DONE 06/27/06 06/27/06 / / / / 16 3,818 3,818 JOD 0 0 0
New District Office Building:
06-1321 Reconstruction 1-013-002 05/30/07 DONE DONE DONE 04/13/07 04/13/07 11/30/06 01/08/07 7 30,000 0 HCM 0 0 0
Bonacci Architects, Pllc
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Gorham Elementary:
05-0423 Reconstruction 0-001-011 04/27/06 DONE DONE DONE 12/07/05 12/05/05 05/11/00 08/16/04 7 694,000 694,000 MAC 0 0 0
Thomas Associates
07-2119 Reconstruction 0-001-013 07/01/08 DONE DONE DONE 05/16/08 05/09/08 05/24/07 12/04/07 7,10,16 0 0 HCM 0 0 0
SEI Design Group
Middlesex Valley Bldg.:
05-0424 Reconstruction 0-006-007 04/27/06 DONE DONE DONE 12/07/05 12/05/05 10/16/95 08/16/04 4,8,9,155,15,16 696,000 696,000 MAC 0 0 0
Thomas Associates
07-2120 Reconstruction 0-006-011 07/01/08 DONE DONE DONE 05/16/08 05/09/08 05/24/07 12/04/07 7,16 0 0 HCM 0 0 0
SEI Design Group
Marcus Whitman Jr/Sr High:
04-1288 Reconstruction 0-012-011 06/27/05 DONE DONE DONE 05/19/05 05/17/05 03/10/00 02/15/05 155 191,400 191,400 MAC 0 0 0
Thomas Associates
05-0425 Reconstruction 0-012-013 04/27/06 DONE DONE DONE 12/07/05 12/05/05 10/07/05 08/16/04 2,8,10,155,15,16 3,218,600 3,218,600 HCM 0 0 0
Thomas Associates
06-1235 Reconstruction 0-012-014 06/19/07 DONE DONE DONE 03/27/07 03/20/07 / / 08/16/04 2,4,10,13,15,16 1,499,970 1,499,970 HCM 0 0 0
Sniedze Associates
07-2121 Reconstruction 0-012-015 07/01/08 DONE DONE DONE 05/16/08 05/09/08 05/24/07 12/04/07 7,10,16 0 0 HCM 0 0 0
SEI Design Group
07-1422 Reconstruction 0-012-016 01/22/08 DONE DONE DONE 01/18/08 12/24/07 01/17/08 / / 10,13,14,155,16 196,945 196,945 HCM 0 0 0
Sear-Brown Group Inc.
03-1528FP Reconstruction 0-012-FP1 06/04/04 DONE DONE DONE 05/07/04 / / / / / / 16 28,940 28,940 JOD 0 0 0
Environmental Classroom Opportunity:
- XX New Construction 0-015-001 CANCELLED / / / / 05/07/04 / / 02 - 16 0 0 MAC 0 0 0
:
05-0426XX New Construction 2-017-001 04/27/06 CANCELLED 12/07/05 12/05/05 08/09/05 08/16/04 02 - 16 83,160 0 HCM 0 0 0
Thomas Associates
New Transportation Building:
07-2122 Reconstruction 5-013-002 07/01/08 DONE DONE DONE 05/16/08 05/09/08 02/08/08 12/04/07 16 0 0 HCM 0 0 0
SEI Design Group
Water & Piping Building:
06-1236 New Construction 7-018-001 06/19/07 DONE DONE DONE 03/27/07 03/20/07 / / 08/16/04 02 - 16 0 0 HCM 0 0 0
Sniedze Associates
Cumming Nature Center:
- Reconstruction 8-016-L01 / / / / 06/08/05 / / 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Manchester-Shortsville Inst. Complex:
03-0864 Reconstruction 0-007-010 03/18/04 DONE DONE DONE 12/22/03 12/12/03 09/22/03 12/10/03 155 287,000 287,000 HCM 0 0 0
Patterson - Mossien Architects P.C.
03-0865 Reconstruction 0-007-011 03/18/04 DONE DONE DONE 12/22/03 12/12/03 09/22/03 12/10/03 2,4,7 1,514,377 1,514,377 HCM 0 0 0
Patterson - Mossien Architects P.C.
03-1188 Reconstruction 0-007-012 05/04/04 DONE DONE DONE 02/26/04 02/26/04 09/25/03 12/10/03 2,4,7,8,9,10,155,15, 2,038,623 2,038,623 HCM 0 0 0
Clark Patterson Associates
06-1662 Reconstruction 0-007-013 04/10/08 DONE DONE DONE 06/27/07 06/22/07 11/02/06 / / 2,4,8,9,155,15,16 2,903,000 2,903,000 HCM 0 0 298,348
William Taylor Architects, PLLC.
06-0418SC Visual Structural Inspection 0-007-SC1 11/06/06 DONE DONE DONE 10/23/06 10/23/06 / / / / 16 10,283 10,283 JOD 0 0 0
Storage #1:
- DB Discovered Building 2-011-001 / / / / / / / / 0 0 HCM 0 0 0
Bus Garage:
06-1663 Reconstruction 5-001-005 04/10/08 DONE DONE DONE 06/27/07 06/22/07 11/02/06 / / 2,4,7,8,9,155,15,16 527,000 527,000 HCM 0 0 0
William Taylor Architects, PLLC.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Naples High School:
07-0193 Additions and Alterations 0-001-010 12/31/07 DONE DONE DONE 08/17/07 08/16/07 10/04/06 02/15/07 02 - 16 2,368,600 0 MGL 0 0 111,482
Hunt Engineers,
- Reconstruction 0-001-011 / / / / 12/07/06 / / 7,10,16 0 10,220,238 MGL 0 0 0
02-2361FP Reconstruction 0-001-FP1 08/25/03 DONE DONE DONE 06/09/03 / / / / / / 16 5,950 5,950 MGL 0 0 0
04-1440SC Visual Structural Inspection 0-001-SC1 06/20/05 DONE DONE DONE 06/14/05 06/14/05 / / / / 16 14,646 14,646 JOD 0 0 0
Naples Elementary:
07-0194 Reconstruction 0-002-008 12/31/07 DONE DONE DONE 08/17/07 08/16/07 10/04/06 02/15/07 2,4,7,8,9,155,15,16 3,521,400 0 MGL 0 0 174,368
Hunt Engineers,
- Reconstruction 0-002-009 / / / / 12/07/06 / / 7,10,16 0 7,862,412 MGL 0 0 0
02-2360FP Reconstruction 0-002-FP1 08/25/03 DONE DONE DONE 06/09/03 / / / / / / 16 5,885 5,885 MGL 0 0 0
04-1439SC Visual Structural Inspection 0-002-SC1 06/20/05 DONE DONE DONE 06/14/05 06/14/05 / / / / 16 11,675 11,675 JOD 0 0 0
Districtwide:
- Reconstruction 7-999-000 / / / / / / / / 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Midlakes MS/bldg.sold now 0-011:
- XX Reconstruction 0-001-007 CANCELLED / / / / 11/14/07 / / 2,16 0 0 DDJ 0 0 0
Midlakes Middle/High School:
06-1338 Reconstruction 0-011-012 09/27/07 DONE DONE DONE 04/18/07 04/16/07 08/14/06 12/13/06 2,4,9,10,155,15,16 1,882,154 1,882,154 DDJ 0 0 0
Clark Patterson Associates
06-1339 Alterations 0-011-013 09/27/07 DONE DONE DONE 04/18/07 04/16/07 04/17/07 12/13/06 02 - 16 617,846 617,846 DDJ 0 0 617,846
Clark Patterson Associates
- Reconstruction 0-011-014 / / / / 11/14/07 / / 2,16 0 0 DDJ 0 0 0
06-1515SC Visual Structural Inspection 0-011-SC1 05/18/07 DONE DONE DONE 05/04/07 05/04/07 / / / / 16 5,227 0 JOD 0 0 0
One Room Schoolhouse:
- DB Discovered Building 0-016-001 / / / / 04/14/08 / / 0 0 DDJ 0 0 0
District Maintenance Facility:
04-1407DB Discovered Building 3-015-001 07/13/07 DONE DONE DONE 06/10/05 06/09/05 02/17/05 / / 0 0 DDJ 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
02-2334FP Reconstruction 0-001-FP1 08/25/03 DONE DONE DONE 06/02/03 / / / / / / 16 3,700 3,700 MGL 0 0 0
Elementary School:
02-2333FP Reconstruction 0-003-FP1 08/25/03 DONE DONE DONE 06/02/03 / / / / / / 16 4,380 4,380 MGL 0 0 0
Green House:
- TQ Temporary Quarters 0-009-001 / / / / 02/12/04 / / 0 0 MGL 0 0 0
Softball Storage Shed:
- DB Discovered Building 2-013-001 / / / / 12/07/06 / / 0 0 MGL 0 0 0
Baseball Storqage Shed:
- DB Discovered Building 2-014-001 / / / / 12/07/06 / / 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Education Center:
- XX Reconstruction 0-001-009 CANCELLED / / / / 06/08/04 / / 2,9,15,16 0 1,740,042 DDJ 0 0 0
05-0114 Additions and Alterations 0-001-010 02/28/06 DONE DONE DONE 11/01/05 10/31/05 09/24/04 12/20/04 02 - 16 4,865,569 4,478,186 DDJ 0 0 1,171,281
Stantec Architecture
07-1493 Reconstruction 0-001-011 05/07/08 DONE DONE DONE 01/31/08 01/28/08 09/27/07 09/07/07 2,8,9,10,155,15,16 2,329,570 0 DDJ 0 0 0
SWBR Architects P.C.
Primary School:
05-0115 Reconstruction 0-002-009 02/28/06 DONE DONE DONE 11/01/05 10/31/05 09/24/04 12/20/04 9,10,155,15,16 2,373,378 2,373,378 DDJ 0 0 0
Stantec Architecture
- Reconstruction 0-002-010 / / / / 09/27/07 / / 2,4,7,8,15,16 0 0 DDJ 0 0 0
07-1494 Reconstruction 0-002-010 05/07/08 DONE DONE DONE 01/31/08 01/28/08 / / 09/07/07 932,071 0 0 0 0
SWBR Architects P.C.
Jr/Sr High(fmly Sr. High):
04-1315SR Additions and Alterations 0-005-012 06/10/05 DONE DONE DONE 07/13/05 07/12/05 09/24/04 12/20/04 02 - 16 0 0 DDJ 0 0 0
Stantec Architecture
05-0038 Reconstruction 0-005-012 08/26/05 DONE DONE DONE / / / / / / 12/20/04 3,316,265 3,316,265 DDJ 0 0 0
05-0116 Additions and Alterations 0-005-013 02/28/06 DONE DONE DONE 11/01/05 10/31/05 04/08/05 12/20/04 02 - 16 10,700,480 10,700,480 DDJ 0 0 0
Stantec Architecture
07-1496 Additions and Alterations 0-005-014 05/07/08 DONE DONE DONE 01/31/08 01/28/08 09/27/07 09/07/07 02 - 16 5,381,392 0 DDJ 0 0 0
SWBR Architects P.C.
05-0322SC Visual Structural Inspection 0-005-SC2 11/04/05 DONE DONE DONE 11/02/05 11/02/05 / / / / 16 28,464 28,464 JOD 0 0 0
Maint.Annex(fmly Jr.H Annex):
- XX Reconstruction 0-007-006 CANCELLED / / / / 09/24/04 / / 2,4,7,8,9,155,15,16 0 1,006,920 DDJ 0 0 0
Intermediate:
04-1316SR Additions and Alterations 0-008-006 06/10/05 DONE DONE DONE 05/24/05 05/24/05 09/24/04 12/20/04 02 - 16 0 0 DDJ 0 0 0
Stantec Architecture
04-1474 Additions and Alterations 0-008-006 08/26/05 DONE DONE DONE 06/27/05 06/24/05 09/24/04 12/20/04 02 - 16 2,129,302 2,129,302 DDJ 0 0 0
Stantec Architecture
05-0117 Reconstruction 0-008-007 02/28/06 DONE DONE DONE 11/01/05 10/31/05 04/08/05 12/20/04 2,4,7,8,9,10,155,15, 2,924,829 2,924,829 DDJ 0 0 0
Stantec Architecture
07-1497 Additions and Alterations 0-008-008 05/07/08 DONE DONE DONE 01/31/08 01/28/08 09/24/07 09/07/07 02 - 16 2,262,848 0 DDJ 0 0 0
SWBR Architects P.C.
Health & Wellness Center:
- New Construction 0-027-001 / / / / 03/14/05 / / 02 - 16 0 0 DDJ 0 0 0
Bus Storage Facility:
04-1475 Alterations 4-028-001 08/26/05 DONE DONE DONE 06/27/05 06/24/05 04/08/05 12/20/04 02 - 16 329,621 329,621 DDJ 0 0 0
Stantec Architecture
Bus Garage:
04-1317SR Additions and Alterations 5-003-007 06/10/05 DONE DONE DONE 05/24/05 05/24/05 09/24/04 12/20/04 02 - 16 0 0 DDJ 0 0 0
Stantec Architecture
04-1476 Additions and Alterations 5-003-007 08/26/05 DONE DONE DONE 06/27/05 06/24/05 09/24/04 12/20/04 02 - 16 2,056,056 2,056,056 DDJ 0 0 0
Stantec Architecture
07-1495 Reconstruction 5-003-008 05/07/08 DONE DONE DONE 01/31/08 01/28/08 09/27/07 09/07/07 2,155,15,16 1,066,019 0 DDJ 0 0 0
SWBR Architects P.C.
Concession Stand:
- XX Additions and Alterations 7-004-001 CANCELLED / / / / 09/24/04 / / 02 - 16 0 0 DDJ 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Finger Lakes Educ. Center:
03-1620 Reconstruction 0-001-012 06/30/04 DONE DONE DONE 06/15/04 06/14/04 08/11/03 12/15/03 4,7,16 349,634 349,634 MAC 0 0 0
Beardsley Design Associates Arch.
04-0858 Reconstruction 0-001-013 05/09/05 DONE DONE DONE 03/01/05 02/26/05 11/10/04 01/10/05 2,4,8,9,155,15,16 816,793 816,793 JOD 0 0 0
Beardsley Design Associates Arch.
06-0153 Reconstruction 0-001-014 12/07/06 DONE DONE DONE 08/07/06 08/03/06 07/20/05 06/05/06 8,155,15,16 682,643 656,853 JOD 0 0 0
Pathfinder Engineers LLP
Alt. HS Flint Campus(Admin):
03-1621 Reconstruction 0-002-002 06/30/04 DONE DONE DONE 06/15/04 06/14/04 08/11/03 12/15/03 7,16 130,601 130,601 MAC 0 0 0
Beardsley Design Associates Arch.
04-0859 Reconstruction 0-002-003 05/09/05 DONE DONE DONE 03/01/05 02/26/05 11/10/04 01/10/05 2,4,8,9,155,15,16 411,195 410,535 JOD 0 0 0
Beardsley Design Associates Arch.
06-0154 Reconstruction 0-002-004 12/07/06 DONE DONE DONE 08/07/06 08/03/06 07/20/05 06/05/06 155,15,16 71,312 71,312 JOD 0 0 0
Pathfinder Engineers LLP
Auto Shop:
06-0155 Reconstruction 0-012-001 12/07/06 DONE DONE DONE 08/07/06 08/03/06 06/21/06 06/05/06 155,16 15,082 15,082 JOD 0 0 0
Pathfinder Engineers LLP
- Reconstruction 0-012-002 / / / / 05/14/08 / / 10,155 0 0 JOD 0 0 0
Occup. Center/Williamson:
03-0456 Reconstruction 0-014-012 05/05/04 DONE DONE DONE 10/15/03 08/27/03 09/04/02 12/17/02 16 546,548 546,548 MAC 0 0 0
Beardsley Design Associates Arch.
06-0001 Reconstruction 0-014-013 01/04/07 DONE DONE DONE 07/06/06 07/03/06 03/24/05 05/09/05 2,4,16 124,315 63,500 JOD 0 0 0
Beardsley Design Associates Arch.
05-1280 Reconstruction 0-014-014 07/10/06 DONE DONE DONE 05/22/06 05/19/06 07/20/05 12/17/02 155,15,16 406,500 406,500 JOD 0 0 0
Beardsley Design Associates Arch.
06-0400 Reconstruction 0-014-015 12/07/06 DONE DONE DONE 12/07/06 10/25/06 10/11/06 06/05/06 155,15,16 632,885 632,885 JOD 0 0 0
Pathfinder Engineers LLP
06-0707 Reconstruction 0-014-016 01/19/07 DONE DONE DONE 01/03/07 01/03/07 12/11/06 06/05/06 7 1,110,800 1,110,800 JOD 0 0 0
Beardsley Design Associates Arch.
- Reconstruction 0-014-017 / / / / 10/01/07 / / 2,4,8,155,15,16 0 0 JOD 0 0 0
- Reconstruction 0-014-018 / / / / 05/14/08 / / 10,155 0 0 JOD 0 0 0
Education Center Williamson:
03-0457 Additions and Alterations 0-025-003 05/05/04 DONE DONE DONE 10/15/03 08/27/03 09/04/02 12/17/02 02 - 16 1,323,221 1,300,234 MAC 0 0 0
Beardsley Design Associates Arch.
05-1281 Reconstruction 0-025-004 07/10/06 DONE DONE DONE 05/22/06 05/19/06 07/20/05 12/17/02 155,15,16 325,000 325,000 JOD 0 0 0
Beardsley Design Associates Arch.
06-0401 Reconstruction 0-025-005 12/07/06 DONE DONE DONE 12/07/06 10/25/06 10/11/06 06/05/06 155,15,16 322,215 322,215 JOD 0 0 0
Pathfinder Engineers LLP
06-0708 Reconstruction 0-025-006 01/19/07 DONE DONE DONE 01/03/07 01/03/07 12/11/06 06/05/06 7 255,200 255,200 JOD 0 0 0
Beardsley Design Associates Arch.
- Reconstruction 0-025-007 / / / / 10/01/07 / / 2,4,8,9,155,15,16 0 0 JOD 0 0 0
Voc Training/Alt HS FL:
06-0156 Reconstruction 0-027-002 12/07/06 DONE DONE DONE 08/07/06 08/03/06 08/11/03 06/05/06 2,4,7,8,9,155,15,16 11,366 0 MAC 0 0 0
Pathfinder Engineers LLP
- Reconstruction 0-027-004 / / / / 06/20/06 / / 155,16 0 503,460 JOD 0 0 0
Handicapped Workshop:
06-0389 Reconstruction 0-028-001 12/07/06 DONE DONE DONE 08/03/06 08/03/06 / / 06/05/06 155,15,16 15,114 15,114 JOD 0 0 0
- Reconstruction 0-028-002 / / / / 05/01/08 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
Day Care Teaching Center:
06-0157 Reconstruction 0-030-002 12/07/06 DONE DONE DONE 08/07/06 08/03/06 08/11/03 06/05/06 2,7,8,9,155,15,16 29,032 29,032 MAC 0 0 0
Pathfinder Engineers LLP
- Reconstruction 0-030-003 / / / / / / / / 155,16 0 0 JOD 0 0 0
Pole Barn #5:
03-0557 New Construction 0-045-001 06/14/06 DONE DONE DONE 10/27/03 10/15/03 09/09/02 12/17/02 02 - 16 478,000 478,000 MAC 0 0 0
Beardsley Design Associates Arch.
Wayne Education Center:
03-0458 New Construction 0-046-001 05/05/04 DONE DONE DONE 10/15/03 08/27/03 09/09/02 12/17/02 02 - 16 8,980,230 8,980,230 MAC 0 0 0
Beardsley Design Associates Arch.
Wayne Educational Cntr. Portables:
03-0532XX New Construction 0-047-001 06/29/04 CANCELLED 10/28/03 09/24/03 08/12/03 12/17/02 02 - 16 1,835,500 0 MAC 0 0 0
Beardsley Design Associates Arch.
MAPLE BUILDING ADMINSTRATION:
05-1331 Reconstruction 1-052-001 11/06/06 DONE DONE DONE 06/07/06 06/06/06 / / 04/24/06 2,4,10,14,16 714,811 0 JOD 0 0 0
Beardsley Design Associates Arch.
Seneca County Office Building:
07-1573TQ Temporary Quarters 1-053-001 03/25/08 DONE DONE DONE 02/08/08 02/06/08 05/22/07 / / 0 0 JOD 0 0 0
Pole Barn #2:
- Reconstruction 2-029-002 / / / / 07/20/06 / / 155,16 0 0 JOD 0 0 0
Special Ed. Storage @ Williamson:
03-0554 New Construction 2-042-001 06/13/06 DONE DONE DONE 10/27/03 10/15/03 09/09/02 12/17/02 02 - 16 45,000 0 MAC 0 0 0
Beardsley Design Associates Arch.
Pole Barn #4:
03-0555 New Construction 2-043-001 06/14/06 DONE DONE DONE 10/27/03 10/15/03 09/09/02 12/17/02 02 - 16 160,000 0 MAC 0 0 0
Beardsley Design Associates Arch.
Technical Facilities Storage:
03-0556 New Construction 2-044-001 06/13/06 DONE DONE DONE 10/27/03 10/15/03 09/09/02 12/17/02 02 - 16 133,500 0 MAC 0 0 0
Beardsley Design Associates Arch.
Edu-Tech Receiving:
- Reconstruction 7-039-002 / / / / 05/14/08 / / 8 0 0 JOD 0 0 0
DISTRICTWIDE:
06-0535 Reconstruction 7-999-001 03/20/07 DONE DONE DONE 11/21/06 11/20/06 06/19/06 06/05/06 10,13,14,16 584,000 434,000 JOD 0 0 0
Beardsley Design Associates Arch.
- Reconstruction 7-999-002 / / / / 05/14/08 / / 10,13,16 0 0 JOD 0 0 0
Day Care/Teaching Center:
- XX Reconstruction 8-030-003 CANCELLED / / / / 06/20/06 / / 155,16 0 0 JOD 0 0 0
Newark Devel Ctr Maple Bldg:
06-1207 Reconstruction 8-033-002 04/25/07 DONE DONE DONE 03/22/07 03/21/07 09/25/06 09/25/06 8 400,000 0 JOD 0 0 0
Beardsley Design Associates Arch.
- Reconstruction 8-033-003 / / / / 10/01/07 / / 2,4,7,8,9,155,15,16 0 0 JOD 0 0 0
Newark Dev Ctr - Eisenhower Bldg:
06-1208 Reconstruction 8-035-002 04/25/07 DONE DONE DONE 03/22/07 03/21/07 09/25/06 09/25/06 8 400,000 0 JOD 0 0 0
Beardsley Design Associates Arch.
NDC:Arcadia/York:
06-1209 Reconstruction 8-037-002 04/25/07 DONE DONE DONE 03/22/07 03/21/07 09/25/06 09/25/06 8 210,000 0 JOD 0 0 0
Beardsley Design Associates Arch.
Career Recource Center Canandaigua:
03-1548TQ Temporary Quarters 8-048-001 05/10/05 DONE DONE DONE 05/13/04 05/13/04 11/13/03 / / 0 0 MAC 0 0 0
Perkins Elementary:
- TQ Temporary Quarters 8-049-001 / / / / 03/08/04 / / 0 0 MAC 0 0 0
Kelley Elementary School:
- TQ Temporary Quarters 8-050-001 / / / / 03/08/04 / / 0 0 MAC 0 0 0
Techniplex III - Suite 2:
04-1219TQ Temporary Quarters 8-051-001 ADDENDUM REQ'D 04/29/05 04/28/05 02/04/05 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED