Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/05/09 at 16:03:17




ADIRONDACK CENT SCH-BOONVILLE STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-04-01-06
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Boonville Central:
07-1516   Reconstruction               0-002-006  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/07/07   05/15/07   2,4,7,8,9,10,155,15,   2,500,000     2,500,000  HCM             0           0       50,000
                                                                                                                                                                                                                                 March Associates                    
06-1573SC Visual Structural Inspection 0-002-SC1  06/13/07     DONE    DONE       DONE      02/12/07   02/12/07     /  /       /  /     16                         1,910             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          West Leyden School:
07-1517   Reconstruction               0-013-006  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/07/07   05/15/07   2,4,7,8,9,155,15,16    1,015,052     1,015,052  HCM             0           0       20,301
                                                                                                                                                                                                                                 March Associates                    
06-1572SC Visual Structural Inspection 0-013-SC1  06/13/07     DONE    DONE       DONE      02/12/07   02/12/07     /  /       /  /     16                         1,810             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Forestport Elementary:
07-1518   Reconstruction               0-016-006  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/08/07   05/15/07   2,4,7,8,9,155,15,16      700,240       700,240  HCM             0           0       14,000
                                                                                                                                                                                                                                 March Associates                    
06-1571SC Visual Structural Inspection 0-016-SC1  06/13/07     DONE    DONE       DONE      02/12/07   02/12/07     /  /       /  /     16                         2,430             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Senior High School:
07-1519   Reconstruction               0-017-006  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/07/07   05/15/07   2,4,7,8,9,10,155,15,   4,891,027     4,891,027  HCM             0           0       97,821
                                                                                                                                                                                                                                 March Associates                    

          West Leyden Bus Garage(Now 4-022):
  -       Reconstruction               4-003-003                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               4-004-002                                              /  /       /  /     03/15/07     /  /     4,7                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New West Leyden Bus Garage:
07-1520   New Construction             4-022-001  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/15/07   05/15/07   02 - 16                  351,968       351,968  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Bus Garage:
07-1521   Reconstruction               5-001-004  08/11/08     DONE    DONE       DONE      02/01/08   01/31/08   03/08/07   05/15/07   2,4,8,9,155,15,16        245,953       245,953  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CAMDEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-06-01-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
04-0758   Reconstruction               0-001-019  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   11/23/04   11/18/04   10,16                    128,253       128,253  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
04-1051SR Additions and Alterations    0-001-020  04/01/05     DONE    DONE       DONE      03/29/05   03/25/05   03/23/05   03/17/05   02 - 16               10,890,000             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0466   Additions and Alterations    0-001-020  02/09/06     DONE    DONE       DONE      12/20/05   03/25/05   03/23/05   03/17/05   02 - 16               10,890,000     9,387,208  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
08-1592   Reconstruction               0-001-021  10/15/09     DONE    DONE       DONE      05/05/09   05/01/09   05/24/07   05/20/08   2,4,8,9,155,15,16     10,944,335             0  HCM             0           0      262,664
                                                                                                                                                                                                                                 King & King, Architects             

          Camden Elementary:
04-0759   Reconstruction               0-003-014  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   11/23/04   11/18/04   10,16                     91,434        91,434  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
06-0659   Reconstruction               0-003-015  05/04/07     DONE    DONE       DONE      12/22/06   12/21/06   03/23/05   03/17/05   2,8,9,155,15,16        5,858,000     5,743,000  HCM             0           0      550,652
                                                                                                                                                                                                                                 King & King, Architects             
07-1743   Reconstruction               0-003-016  11/05/08     DONE    DONE       DONE      03/04/08   02/29/08   05/23/07   05/15/07   2,8,9,155,15,16          629,009       629,009  HCM             0           0       15,725
                                                                                                                                                                                                                                 King & King, Architects             

          Annsville Area School:
04-0760   Reconstruction               0-004-012  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   05/14/04   11/18/04   9,10,155,15,16           198,031       198,031  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1744   Reconstruction               0-004-013  11/05/08     DONE    DONE       DONE      03/04/08   02/29/08   05/23/07   05/15/07   2,8,9,155,15,16          996,271             0  HCM             0           0       24,907
                                                                                                                                                                                                                                 King & King, Architects             

          North Bay Area School:
04-0761   Reconstruction               0-005-011  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   05/14/04   11/18/04   8,9,10,16                142,187       142,187  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1745   Reconstruction               0-005-012  11/05/08     DONE    DONE       DONE      03/04/08   02/29/08     /  /     05/15/07   2,8,9,155,15,16        1,191,060     1,191,060  HCM             0           0       29,777
                                                                                                                                                                                                                                 King & King, Architects             

          McConnellsville Elementary:
04-0762   Reconstruction               0-007-006  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   05/14/04   11/18/04   9,10,155,16              163,594       163,594  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1746   Reconstruction               0-007-007  11/05/08     DONE    DONE       DONE      03/04/08   02/29/08   05/24/07   05/15/07   8,9,155,16               637,189       637,189  HCM             0           0       15,930
                                                                                                                                                                                                                                 King & King, Architects             

          Camden High School:
04-0763   Reconstruction               0-012-015  03/24/05     DONE    DONE       DONE      02/02/05   02/01/05   05/14/04   11/18/04   7,10,155,16            1,826,500     1,826,500  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
05-0467   Reconstruction               0-012-016  02/09/06     DONE    DONE       DONE      12/20/05   12/16/05   03/23/05   03/17/05   2,8,10,155,15,16         789,700       789,700  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-012-017                                              /  /       /  /     05/24/07     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Maintenance Facility:
07-0113   Additions and Alterations    5-008-006  11/07/07     DONE    DONE       DONE      08/01/07   07/31/07   03/23/05   03/17/05   02 - 16                2,884,600     2,884,600  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Administration:
08-1593   Reconstruction               9-002-002  10/09/09     DONE    DONE       DONE      05/05/09   05/01/09   02/23/09   05/20/08   2,4,8,155,15,16          160,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CLINTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-11-01-06
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Chenango Elementary:
08-1001   Reconstruction               0-001-008  06/03/09     DONE    DONE       DONE      01/02/09   12/23/08   08/29/08   02/27/08   2,7,8,9,10,155,15,16   1,044,731       925,869  JOD             0           0      167,906
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Junior High:
08-1002   Reconstruction               0-002-009  06/03/09     DONE    DONE       DONE      01/02/09   12/23/08   08/29/08   02/27/08   2,4,7,8,9,10,155,15,     424,903       552,882  JOD             0           0       68,000
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Senior High:
07-1273   Reconstruction               0-005-007  09/16/07     DONE    DONE       DONE      12/31/07   12/24/07   07/23/07   07/24/07   2,13                     333,314       333,314  JOD             0           0       56,330
                                                                                                                                                                                                                                 Bernier Carr Associates             
08-1003   Reconstruction               0-005-008  06/03/09     DONE    DONE       DONE      01/02/09   12/23/08   08/29/08   02/27/08   2,4,7,8,9,10,155,15,   1,215,117     1,201,249  JOD             0           0      191,979
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Pool Changing Rm & Service Bldg.:
  -       Reconstruction               7-008-003                                              /  /       /  /     05/08/06     /  /     15                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEW HARTFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-15-01-06
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oxford Rd. ES/SHS:
05-1135   Reconstruction               0-005-014  09/22/06     DONE    DONE       DONE      04/13/06   04/10/06   12/21/05   05/16/00   2,4,9,10,155,15,16       364,241       364,241  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-0694   Additions and Alterations    0-005-015  05/13/08     DONE    DONE       DONE      11/01/07   10/30/07   06/20/06   03/13/07   02 - 16               24,621,940    22,117,266  HCM             0           0      851,141
                                                                                                                                                                                                                                 King & King, Architects             

          Hughes Elementary:
05-1136   Reconstruction               0-006-010  09/22/06     DONE    DONE       DONE      04/13/06   04/10/06   12/21/05   05/16/00   2,4,7,8,9,10,155,15,     391,793       391,793  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Robert E. Myles Elementary:
05-1137   Reconstruction               0-007-010  09/22/06     DONE    DONE       DONE      04/13/06   04/10/06   12/21/05   05/16/00   2,7,155,15,16            147,841       147,841  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Ralph W. Perry Jr. High:
05-1138   Reconstruction               0-008-008  09/22/06     DONE    DONE       DONE      04/13/06   04/10/06   12/21/05   05/16/00   2,7,9,155,15,16          242,391       242,391  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Office @ 29 Oxford Rd.:
04-1406TQ Temporary Quarters           1-014-001  10/11/05     DONE    DONE       DONE      06/10/05   06/09/05   01/05/05     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Building @ Perry Jr. High:
04-1171   Additions and Alterations    2-012-002  07/08/05     DONE    DONE       DONE      04/15/05   04/15/05   08/19/04   06/17/04   02 - 16                  210,000             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Lower Bus Garage:
07-0695   Reconstruction               4-002-002  05/13/08     DONE    DONE       DONE      11/01/07   10/30/07   06/20/06   03/13/07   4,7,155,16               208,790       176,000  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
07-0696   Reconstruction               5-001-003  05/13/08     DONE    DONE       DONE      11/01/07   10/30/07   06/20/06   03/13/07   8,15                     239,270       310,000  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEW YORK MILLS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-15-04-02
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 School:
07-0389PR Additions and Alterations    0-002-008                                            09/17/07     /  /     06/22/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 March Associates                    
08-0573   Additions and Alterations    0-002-008  04/03/09     DONE    DONE       DONE      10/23/08   10/20/08   06/22/07   05/20/08   02 - 16                2,696,113     2,696,113  DDJ             0           0      192,916
                                                                                                                                                                                                                                 March Associates                    

          Beekman Gym:
08-0574   Additions and Alterations    0-005-006  04/03/09     DONE    DONE       DONE      10/23/08   10/20/08   06/22/07   05/20/08   02 - 16                  240,512       240,512  DDJ             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SAUQUOIT VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-16-03-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sulphur Springs Elementary:
05-0606   Reconstruction               0-002-010  05/30/06     DONE    DONE       DONE      01/18/06   12/30/05   12/13/04   01/25/05   2,4,7,9,10,155,15,16   4,589,336     4,589,336  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1798   Reconstruction               0-002-011  12/08/08     DONE    DONE       DONE      03/15/08   03/13/08   11/30/06   09/25/07   2,4,8,9,10,155,15,16     867,242       867,242  MGL             0           0       42,160
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-002-012                                              /  /       /  /     12/11/06     /  /     2,4,8,9,10,155,15,16           0    12,153,404  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Jr/Sr High School:
05-0607   Reconstruction               0-003-009  05/30/06     DONE    DONE       DONE      01/18/06   12/30/05   12/13/04   01/25/05   2,4,7,8,9,10,155,15,   6,110,905     6,110,905  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1799   Reconstruction               0-003-010  12/08/08     DONE    DONE       DONE      03/15/08   03/13/08   11/30/06   09/25/07   2,4,8,9,10,155,15,16   1,242,330     1,242,330  MGL             0           0       61,000
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-003-011                                              /  /       /  /     12/11/06     /  /     2,4,8,9,10,155,15,16           0    11,428,557  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Middle School:
05-0608   Reconstruction               0-007-005  05/30/06     DONE    DONE       DONE      01/18/06   12/30/05   12/13/04   01/25/05   2,4,7,9,10,155,15,16   2,406,876     2,406,876  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1800   Reconstruction               0-007-006  12/08/08     DONE    DONE       DONE      03/15/08   03/13/08   11/30/06   09/25/07   2,4,8,10,13,155,15,1     907,837       907,837  MGL             0           0       44,000
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-007-007                                              /  /       /  /     12/11/06     /  /     2,4,8,10,155,15,16             0     7,685,198  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Building-Oneida Street:
07-1113DB Discovered Building          2-010-001  12/08/08     DONE    DONE       DONE      12/13/07   12/07/07   12/11/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
05-0609   Reconstruction               5-001-006  05/30/06     DONE    DONE       DONE      01/18/06   12/30/05   12/13/04   01/25/05   2,4,7,8,9,10,155,15,     755,883       755,883  RDR             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               5-001-007                                              /  /       /  /     11/30/06     /  /     2,4,8,9,10,155,15,16           0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          New Press Box:
07-1114DB Discovered Building          7-009-001  10/17/08     DONE    DONE       DONE      12/13/07   12/07/07   12/11/07     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




REMSEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-17-01-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior Senior High School:
06-1305   Reconstruction               0-001-010  05/14/07     DONE    DONE       DONE      04/12/07   04/11/07   03/15/07   04/26/07   2,9                      350,000       350,000  HCM             0           0       54,600
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-2295   Reconstruction               0-001-011  08/27/08     DONE    DONE       DONE      07/01/08   06/16/08   04/10/08   04/26/07   7                        250,260       318,850  HCM             0           0       54,600
                                                                                                                                                                                                                                 Bernier Carr Associates             
08-1541   Reconstruction               0-001-012  08/12/09     DONE    DONE       DONE      04/24/09   04/21/09   01/02/09   05/15/07   8,16                     156,000             0  HCM             0           0       25,740
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Remsen Elementary School:
06-1306   Reconstruction               0-006-005  05/14/07     DONE    DONE       DONE      04/12/07   04/11/07   03/15/07   04/26/07   9                        350,000       244,000  HCM             0           0       54,600
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Reconstruction               0-006-006                                              /  /       /  /     04/10/08     /  /     7                              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
08-1542   Reconstruction               0-006-007  08/12/09     DONE    DONE       DONE      04/24/09   04/21/09   01/02/09   05/15/07   8,16                      54,000             0  HCM             0           0        8,910
                                                                                                                                                                                                                                 Bernier Carr Associates             

          New Bus Garage:
07-1823   Reconstruction               5-007-002  03/18/08     DONE    DONE       DONE      03/17/08   03/11/08   11/28/07   11/26/07   4,155,15                 134,200       134,200  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROME CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-18-00-01
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Francis Bellamy School:
08-1300   Additions and Alterations    0-001-007  03/25/09     DONE    DONE       DONE      02/26/09   02/25/09   02/05/07   07/17/08   02 - 16               11,760,000     8,012,795  JOD             0           0    3,915,833
                                                                                                                                                                                                                                 March Associates                    
07-0886SC Visual Structural Inspection 0-001-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        45,640             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Jerry C. Clough Elementary:
08-1586   Reconstruction               0-004-010  06/01/09     DONE    DONE       DONE      05/05/09   04/27/09   02/01/07   06/20/00   2,4,7,8,9,10,155,15,   1,099,458     1,099,458  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-0883SC Visual Structural Inspection 0-004-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        46,344             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Gansevoort Elementary:
  -       Reconstruction               0-008-012                                              /  /       /  /     02/05/07     /  /     2,4,7,8,9,10,14,155,           0     6,090,147  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0888SC Visual Structural Inspection 0-008-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        56,232             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Strough Junior High:
05-0258   Reconstruction               0-012-019  01/18/06     DONE    DONE       DONE      10/12/05   10/11/05   06/29/05   06/20/00   2,8,9,155,15,16          185,084       185,084  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2321   Reconstruction               0-012-020  01/28/09     DONE    DONE       DONE      07/08/08   06/20/08   02/05/07   06/20/00   2,4,7,8,9,10,13,155,   7,500,000     7,500,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
05-0778SC Visual Structural Inspection 0-012-SC1  02/22/06     DONE    DONE       DONE      02/08/06   02/08/06     /  /       /  /     16                       142,920       116,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Ridge Mills School:
08-0855   Reconstruction               0-013-006  12/15/08     DONE    DONE       DONE      12/04/08   12/01/08   02/05/07   10/15/08   7                         70,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-0889SC Visual Structural Inspection 0-013-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        48,420             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Rome Free Academy High School:
06-1148   Reconstruction               0-014-012  05/25/05     DONE    DONE       DONE      03/19/07   03/12/07   06/08/06   06/20/00   2,155,15,16            3,324,500     1,959,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
  -       Reconstruction               0-014-013                                              /  /       /  /     02/05/07     /  /     2,4,7,8,9,10,14,155,           0    46,368,786  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Staley Junior High:
04-1018   Reconstruction               0-016-014  05/19/05     DONE    DONE       DONE      03/22/05   03/21/05   09/24/04   06/20/00   2,4,7                  2,008,120     2,008,120  JOD             0           0            0
                                                                                                                                                                                                                                 McDonald & Monterose LLP            
06-0938   Reconstruction               0-016-015  05/29/07     DONE    DONE       DONE      02/13/07   02/13/07   06/08/06   06/20/00   2,7,9,155,15,16        2,438,682     2,250,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Stokes Elementary:
05-1296   Reconstruction               0-017-013  07/28/06     DONE    DONE       DONE      05/26/06   05/26/06   02/21/06   05/16/06   2,4,7,8,9,10,155,15,   5,100,000     5,100,000  JOD             0           0      183,600
                                                                                                                                                                                                                                 March Associates                    
  -    PR Additions and Alterations    0-017-014                                              /  /       /  /     04/10/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0884SC Visual Structural Inspection 0-017-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        49,456             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          John Joy Elementary:
  -    PR Additions and Alterations    0-018-012                                              /  /       /  /     02/05/07     /  /     02 - 16                        0     5,800,140  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0890SC Visual Structural Inspection 0-018-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        47,570             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Fort Stanwix School:
  -       Reconstruction               0-021-013                                              /  /       /  /     02/01/07     /  /     2,155,16                       0     7,497,218  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Denti Elementary:
08-1299   Reconstruction               0-023-011  03/25/09     DONE    DONE       DONE      02/26/09   02/25/09   02/01/07   06/17/08   2,4,7,8,9,10,155,15,   3,900,000     3,900,000  JOD             0           0       81,900
                                                                                                                                                                                                                                 March Associates                    
07-0887SC Visual Structural Inspection 0-023-SC1  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                        68,745             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New High School:
05-0143   Reconstruction               0-026-002  09/16/05     DONE    DONE       DONE      08/22/05   08/19/05   03/14/05   06/20/00   2,8,9,10,16              230,752       230,752  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
06-0509SC Visual Structural Inspection 0-026-SC2  11/21/06     DONE    DONE       DONE      11/09/06   11/09/06     /  /       /  /     16                        54,500        54,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0885SC Visual Structural Inspection 0-026-SC3  11/21/07     DONE    DONE       DONE      09/21/07   09/21/07     /  /       /  /     16                         9,268             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Administrative Building:
  -       Reconstruction               1-003-007                                              /  /       /  /     02/01/07     /  /     2,155,16                       0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          St. Peter's Catholic School:
04-0428TQ Temporary Quarters           8-031-L01  08/17/05     DONE    DONE       DONE      11/19/04   11/19/04   09/30/04     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-19-02-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Memorial Park School:
04-0933   Reconstruction               0-003-009  05/04/05     DONE    DONE       DONE      03/09/05   03/07/05   05/27/04   05/27/04   155                       71,687        71,687  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
05-0507   Reconstruction               0-003-010  04/17/06     DONE    DONE       DONE      12/27/05   12/23/05   03/17/05   06/28/05   2,8,9,16               1,658,255     1,610,110  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-1835   Reconstruction               0-003-011  12/17/08     DONE    DONE       DONE      03/19/08   03/13/08   11/09/07   06/28/05   8,13                     100,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
08-0935   Reconstruction               0-003-012  07/16/09     DONE    DONE       DONE      12/16/08   12/12/08   11/21/07   06/24/08   2,7,8,9,10,155,15,16   1,481,247             0  DDJ             0           0       74,062
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          MS/High School:
05-0508   Additions and Alterations    0-008-009  04/17/06     DONE    DONE       DONE      12/27/05   12/23/05   03/17/05   06/28/05   02 - 16                5,661,058     5,409,697  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-1836   Reconstruction               0-008-010  12/17/08     DONE    DONE       DONE      03/19/08   03/13/08   11/09/07   06/28/05   8,13                     125,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
08-0936   Reconstruction               0-008-011  07/16/09     DONE    DONE       DONE      12/16/08   12/12/08   11/21/07   06/24/08   2,7,8,9,10,155,15,16   3,147,516             0  DDJ             0           0      157,376
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Bus Garage:
05-0509   Additions and Alterations    5-001-006  04/17/06     DONE    DONE       DONE      12/27/05   12/23/05   03/17/05   06/28/05   02 - 16                2,023,420     2,023,420  DDJ             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               5-001-007                                              /  /       /  /     11/21/07     /  /     2,7,8,9,155,15,16              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Waterville Library:
04-0766   New Construction             6-014-001  03/31/05     DONE    DONE       DONE      02/04/05   02/03/05   11/19/02   10/21/04   02 - 16                1,560,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 March Associates                    
  -    PR Additions and Alterations    6-014-002                                              /  /       /  /     07/28/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHERRILL CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-20-00-05
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          W.A. Wettel ES:
04-0360   Reconstruction               0-002-005  02/04/05     DONE    DONE       DONE      11/04/04   11/03/04   07/08/03   09/15/03   2,4,7,8,9,10,155,15,   1,029,779     1,029,779  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-1173   Reconstruction               0-002-006  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   07/24/07   10/17/07   2,4,7,8,9,10,155,15,     878,913       800,000  HCM             0           0       72,949
                                                                                                                                                                                                                                 King & King, Architects             

          J.D. George ES:
04-0361   Reconstruction               0-005-005  02/04/05     DONE    DONE       DONE      11/04/04   11/03/04   07/08/03   09/15/03   2,4,7,8,9,10,155,15,   1,001,297     1,001,297  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-1174   Reconstruction               0-005-006  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   07/24/07   10/17/07   2,4,7,8,9,10,155,15,     668,910       500,000  HCM             0           0       55,519
                                                                                                                                                                                                                                 King & King, Architects             

          VVS MS/HS:
04-0362   Additions and Alterations    0-006-009  02/04/05     DONE    DONE       DONE      11/04/04   11/03/04   07/08/03   09/15/03   02 - 16                5,369,216     5,369,216  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1175   Reconstruction               0-006-010  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   07/24/07   10/17/07   2,4,7,8,9,10,155,15,   1,950,288     2,240,000  HCM             0           0      161,873
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-006-011                                              /  /       /  /     07/24/07     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
04-0377XX Reconstruction               0-006-FP1  11/08/04               CANCELLED          11/08/04     /  /       /  /       /  /     16                             0    11,430,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          E.A. McAllister Elementary:
04-0363   Reconstruction               0-007-005  02/04/05     DONE    DONE       DONE      11/04/04   11/03/04   07/08/03   09/15/03   2,4,7,8,9,10,155,15,     923,723       923,723  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1176   Reconstruction               0-007-006  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   07/24/07   10/17/07   2,4,7,8,9,10,155,15,     984,334       870,000  HCM             0           0       81,699
                                                                                                                                                                                                                                 King & King, Architects             

          Maintenance Building:
07-1178   Reconstruction               3-004-001  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   01/21/09   10/17/07   2,13                     163,491             0  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
04-0364   Reconstruction               5-003-001  02/04/05     DONE    DONE       DONE      11/04/04   11/03/04   07/08/03   09/15/03   2,4,7,8,9,10,155,15,     155,297       155,297  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1177   Reconstruction               5-003-002  08/13/08     DONE    DONE       DONE      12/21/07   12/19/07   07/24/07   10/17/07   2,4,7,8,9,10,13,14,1   1,154,064     1,330,000  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Districtwide:
06-1211   Reconstruction               7-999-001  03/28/07     DONE    DONE       DONE      03/23/07   03/16/07   02/16/07   02/12/07   10,16                     79,874        79,874  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HOLLAND PATENT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-22-01-06
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Gen. Wm. Floyd Elementary:
04-0866   Reconstruction               0-001-008  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   2,8,9,155,15,16          301,647       301,647  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1244   Reconstruction               0-001-009  07/22/08     DONE    DONE       DONE      12/27/07   12/24/07   01/11/07   03/21/07   16                       287,633       472,300  HCM             0           0       25,613
                                                                                                                                                                                                                                 King & King, Architects             

          Middle School:
04-0867   Additions and Alterations    0-003-009  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   02 - 16                5,074,917     5,074,917  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
05-1200   Reconstruction               0-003-011  04/25/06     DONE    DONE       DONE      04/24/06   04/24/06   02/06/06   03/29/06   2,9,155,15,16            183,699       183,699  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1245   Reconstruction               0-003-012  07/22/08     DONE    DONE       DONE      12/27/07   12/24/07   01/12/07   03/21/07   2,9,155,15,16          1,000,881     1,000,881  HCM             0           0       91,085
                                                                                                                                                                                                                                 King & King, Architects             

          Garage and Shop:
04-0868   Reconstruction               0-004-007  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   2,7,9,155,15,16           35,046        35,046  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Holland Patent Elementary:
04-0869   Additions and Alterations    0-005-007  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   02 - 16                  419,166       419,166  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
05-1201   Reconstruction               0-005-008  04/24/06     DONE    DONE       DONE      04/24/06   04/24/06   02/06/06   03/29/06   2,9,155,15,16            426,301       426,301  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1246   Additions and Alterations    0-005-009  07/22/08     DONE    DONE       DONE      12/27/07   12/24/07   01/12/07   03/21/07   02 - 16                4,830,877     2,783,192  HCM             0           0      109,936
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-005-010                                              /  /       /  /     02/05/07     /  /     2,7,8,9,15                     0     6,262,003  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Senior High School:
04-0870   Additions and Alterations    0-008-009  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   02 - 16                  478,750       478,750  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
07-1247   Reconstruction               0-008-010  07/22/08     DONE    DONE       DONE      12/27/07   12/24/07   01/11/07   03/21/07   2,4,7,8,9,10,155,15,   3,668,559     3,668,559  HCM             0           0      342,182
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
04-0871   Reconstruction               5-006-006  03/17/05     DONE    DONE       DONE      03/01/05   03/01/05   09/11/03   05/10/04   2,10                     215,474       215,474  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               5-006-007                                              /  /       /  /       /  /       /  /     2,4,7,8,9,155,15,16            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UTICA CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-23-00-01
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Utica Sr. Academy At Proctor:
  -    PR Additions and Alterations    0-002-007                                              /  /       /  /     11/04/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-002-008                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
04-0624SC Visual Structural Inspection 0-002-SC1  01/06/05     DONE    DONE       DONE      12/24/04   12/24/04     /  /       /  /     16                        63,868        58,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Albany Street School:
09-0213   Additions and Alterations    0-003-006                         UNREVIEWED         09/14/09   09/14/09   11/04/08   07/29/08   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-003-007                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Proctor High Stadium:
07-0174FP Reconstruction               0-005-FP1  04/17/08     DONE    DONE       DONE      03/10/08   03/10/08   08/20/07     /  /     16                        16,308             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Chris Columbus School:
08-1539   Reconstruction               0-007-007  05/07/09     DONE    DONE       DONE      04/24/09   04/20/09   11/04/08   07/29/08   2,4,7,8,9,10,155,15,   1,950,000             0  HCM             0           0       39,000
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-007-008                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-007-009                                              /  /       /  /     03/24/09     /  /     7                              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Roscoe Conkling School:
09-0212   Reconstruction               0-008-006                         UNREVIEWED         09/14/09   09/14/09   11/04/08   07/29/08   2,4,7,155,15,16                0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-008-007                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          John F Hughes School:
08-1540   Reconstruction               0-009-006  05/07/09     DONE    DONE       DONE      04/24/09   04/20/09   11/04/08   07/29/08   2,4,7,8,9,10,155,15,     779,000       779,000  HCM             0           0       15,580
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-009-007                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Thomas Jefferson School:
09-0256   Additions and Alterations    0-010-008                         UNREVIEWED         09/22/09   09/21/09   11/04/08   07/29/08   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       

          Hugh R. Jones School:
  -       Reconstruction               0-011-008                                              /  /       /  /     11/04/08     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-011-009                                              /  /       /  /     11/04/08     /  /     10,13,16                       0     3,311,526  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Kernan School:
  -       Reconstruction               0-013-007                                              /  /       /  /     11/04/08     /  /     2,4,7,8,10,155,15,16           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-013-008                                              /  /       /  /     11/04/08     /  /     10,13,16                       0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-013-009                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-013-010                                              /  /       /  /     03/24/09     /  /     7                              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0177FP Reconstruction               0-013-FP1  04/17/08     DONE    DONE       DONE      03/10/07   03/10/07   08/20/07     /  /     16                         4,924             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Watson Williams - New K-6:
05-0655   Additions and Alterations    0-015-006  06/23/06     DONE    DONE       DONE      01/24/06   01/24/06   01/17/06   11/02/99   02 - 16                2,110,000       737,886  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
  -       Reconstruction               0-015-007                                              /  /       /  /     07/16/08     /  /     10,16                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-015-008                                              /  /       /  /     11/04/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-015-009                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0178FP Reconstruction               0-015-FP1  04/17/08     DONE    DONE       DONE      03/10/08   03/10/08   08/20/07     /  /     16                         4,137             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          M. L. King School:
  -    PR Additions and Alterations    0-016-007                                              /  /       /  /     12/13/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-016-008                                              /  /       /  /     11/04/08     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-016-009                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Gen. Herkimer School:
09-0214   Additions and Alterations    0-022-008                         UNREVIEWED         09/14/09   09/14/09   11/04/08   07/29/08   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-022-009                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Wetmore Street School:
  -       Reconstruction               0-023-001                                              /  /       /  /     11/04/08     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-023-002                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          John F Kennedy Junior H.S.:
05-0656   Reconstruction               0-026-007  06/23/06     DONE    DONE       DONE      01/24/06   01/24/06   01/17/06   11/02/99   2,4,7,9,14,155,15,16     582,000       582,000  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
08-1323   Additions and Alterations    0-026-008  05/13/09     DONE    DONE       DONE      03/10/09   03/02/09   11/04/08   07/29/08   02 - 16                  409,000             0  HCM             0           0        8,180
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
09-0255   Additions and Alterations    0-026-009               DONE    STARTED    STARTED   09/22/09   09/21/09   11/04/08   07/29/08   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-026-010                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0175FP Reconstruction               0-026-FP1  04/17/08     DONE    DONE       DONE      03/10/08   03/10/08   08/20/07     /  /     16                         3,762             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          J. Donovan Junior High School:
09-0254   Additions and Alterations    0-031-006                         UNREVIEWED         09/22/09   09/21/09   11/04/08   07/29/08   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Stieglitz Snyder Architecture       
  -       Reconstruction               0-031-007                                              /  /       /  /     11/05/08     /  /     10,13,16                       0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
07-0176FP Reconstruction               0-031-FP1  04/17/08     DONE    DONE       DONE      03/10/08   03/10/08   08/20/07     /  /     16                         3,837             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Leased Bus Garage:
  -    TQ Temporary Quarters           5-043-001                                              /  /       /  /     03/14/08     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Districtwide:
  -       New Construction             7-999-001                                              /  /       /  /     10/05/09     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WESTMORELAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-28-01-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Westmoreland Jr/SrHigh School:
06-1666   Reconstruction               0-001-011  12/20/07     DONE    DONE       DONE      06/27/07   06/26/07   11/02/06   01/16/07   2,4,7,8,9,10,13,14,1   3,207,000             0  MGL             0           0      249,942
                                                                                                                                                                                                                                 March Associates                    
04-0447SC Visual Structural Inspection 0-001-SC2  12/13/04     DONE    DONE       DONE      12/10/04   12/10/04     /  /       /  /     16                        15,700        15,700  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
04-1050   Reconstruction               0-003-008  09/21/05     DONE    DONE       DONE      03/29/05   03/28/05   04/23/04   10/26/04   155                      186,965       186,965  RDR             0           0            0
                                                                                                                                                                                                                                 Kernan Engineering                  
06-1667   Reconstruction               0-003-009  12/20/07     DONE    DONE       DONE      06/27/07   06/26/07   11/02/06   01/16/07   2,4,7,8,9,10,155,15,   1,046,000             0  MGL             0           0      100,000
                                                                                                                                                                                                                                 March Associates                    
04-0448SC Visual Structural Inspection 0-003-SC1  12/13/04     DONE    DONE       DONE      12/10/04   12/10/04     /  /       /  /     16                         3,925         3,925  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Middle School:
06-1668   Reconstruction               0-012-003  12/20/07     DONE    DONE       DONE      06/27/07   06/26/07   11/02/06   01/16/07   2,9,155,16               214,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 March Associates                    
04-0449SC Visual Structural Inspection 0-012-SC1  12/13/04     DONE    DONE       DONE      12/10/04   12/10/04     /  /       /  /     16                        11,525        11,525  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
06-1669   Reconstruction               5-004-005  12/20/07     DONE    DONE       DONE      06/27/07   06/26/07   11/02/06   01/16/07   2,4,7,8,9,155,15,16      177,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Press Box:
07-0604   New Construction             7-014-001  12/20/07     DONE    DONE       DONE      10/22/07   10/19/07   06/07/07   01/16/07   02 - 16                   56,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ORISKANY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-29-01-04
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior Senior High:
05-0461   Reconstruction               0-004-009  05/09/06     DONE    DONE       DONE      12/19/05   12/16/05   03/03/05   05/17/05   2,4,8,9,10,155,15,16   1,326,696     1,326,696  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
06-1013   Reconstruction               0-004-010  03/26/07     DONE    DONE       DONE      02/27/07   02/26/07   11/01/06   12/12/06   2,7                      790,000       790,000  JOD             0           0       73,470
                                                                                                                                                                                                                                 March Associates                    
  -       Reconstruction               0-004-011                                              /  /       /  /     08/19/09     /  /     2,4,7,8,9,10,155,15,           0     7,425,135  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          N. Walbran Elementary:
05-0462   Reconstruction               0-005-008  05/09/06     DONE    DONE       DONE      12/19/05   12/16/05   03/11/05   05/17/05   2,4,8,9,155,15,16      1,146,026     1,146,026  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
06-1014   Reconstruction               0-005-009  03/26/07     DONE    DONE       DONE      02/27/07   02/26/07   11/01/06   12/12/06   7                        817,335       849,000  JOD             0           0       76,012
                                                                                                                                                                                                                                 March Associates                    
  -       Reconstruction               0-005-010                                              /  /       /  /     08/19/09     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Upper Bus Garage:
06-1015   Reconstruction               4-003-005  03/26/07     DONE    DONE       DONE      02/27/07   02/26/07     /  /     12/12/06   2,7                       56,665        25,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Lower Bus Garage:
  -       Reconstruction               5-002-005                                              /  /       /  /     08/19/09     /  /     2,15,16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout/Storage:
  -    PR New Construction             7-010-001                                              /  /       /  /     03/17/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WHITESBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-29-02-06
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Parkway School:
  -    PR Additions and Alterations    0-001-011                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
09-0133   Reconstruction               0-001-012               STARTED DONE       DONE      08/19/09   08/17/09   07/02/09   04/28/09   10,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   

          Whitesboro Middle School:
  -    PR Additions and Alterations    0-002-011                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
08-1775   Reconstruction               0-002-012  07/03/09     DONE    DONE       DONE      07/01/09   06/29/09   05/29/09   04/28/09   2,4,7,8,9,16             343,765       343,765  DDJ             0           0       42,283
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   
09-0134   Reconstruction               0-002-013               STARTED DONE       DONE      08/19/09   08/17/09   05/29/09   04/28/09   2,155,15,16                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   
  -       Reconstruction               0-002-014                                              /  /       /  /     06/19/09     /  /     10,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Harts Hill Elementary:
09-0342   Additions and Alterations    0-004-015               STARTED STARTED    UNREVIEWED10/26/09   10/21/09   11/12/08   04/28/09   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   

          Marcy Elementary School:
09-0343   Additions and Alterations    0-006-014               STARTED STARTED    UNREVIEWED10/26/09   10/21/09   11/12/08   04/28/09   02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   

          Deerfield Elementary:
  -    PR Additions and Alterations    0-009-012                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Westmoreland Rd Elementary:
07-0150   Reconstruction               0-010-008  08/17/07     DONE    DONE       DONE      08/09/07   08/08/07   03/05/01   05/15/07   155                      435,000       435,000  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-010-010                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Senior High School:
09-0284PR Additions and Alterations    0-012-022                         UNREVIEWED         10/05/09   10/02/09   11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   
09-0344   Additions and Alterations    0-012-022               STARTED STARTED    UNREVIEWED10/26/09   10/21/09   11/12/08   04/28/09   02 - 16                        0    14,841,900  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   
09-0135   Reconstruction               0-012-023  11/03/09     DONE    DONE       DONE      08/19/09   08/17/09   05/29/09   04/28/09   2,155,15,16                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 TETRA TECH ARCHITECTS & ENGINEERS   

          Administration Bldg:
  -       Additions and Alterations    1-003-006                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Additions and Alterations    5-008-007                                              /  /       /  /     11/12/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES ONEIDA-HERKIMER-MADISON STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-90-00-00
last updated on 11/05/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Occ. Education:
07-1015   Additions and Alterations    0-011-006  06/24/08     DONE    DONE       DONE      12/03/07   12/03/07   05/05/06   05/15/07   02 - 16               38,550,000    38,550,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          SPECIAL EDUCATION BUILDING:
  -    PR Additions and Alterations    0-012-007                                              /  /       /  /     05/05/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Cims Proj. Ed. Comm.:
  -       Reconstruction               1-001-001                                              /  /       /  /     05/05/06     /  /     2,4,7,8,9,155,15,16            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Brodock Press Building:
08-0897TQ Temporary Quarters           1-029-001                       ADDENDUM REQ'D       12/09/08   12/08/08   03/06/03     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Holy Trinity Elementary School:
02-1131TQ Temporary Quarters           8-028-001  07/14/09     DONE    DONE       DONE      01/23/03     /  /     08/15/02     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED