Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 09/04/08 at 11:26:58




BRIGHTON CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-01-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Twelve Corners Middle School:
03-0735   Reconstruction               0-002-015  03/09/04     DONE    DONE       DONE      11/21/03   11/19/03   09/18/03   06/03/03   2,4,7                    146,928       146,928  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-0490   Reconstruction               0-002-016  02/11/05     DONE    DONE       DONE      12/09/04   12/07/04   11/02/04   05/18/04   4                         77,837        77,837  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0536   Reconstruction               0-002-017  01/31/07     DONE    DONE       DONE      11/21/06   11/20/06   05/19/06   05/16/06   2,4                       73,200        73,200  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-002-018                                              /  /       /  /     07/09/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Brighton Senior High:
03-0736   Reconstruction               0-003-016  03/09/04     DONE    DONE       DONE      11/21/03   11/19/03   09/18/03   06/03/03   2,7,9                    237,817       237,817  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-0491   Reconstruction               0-003-017  02/11/05     DONE    DONE       DONE      12/09/04   12/07/04   11/02/04   05/18/04   9,10,15                1,034,075     1,034,075  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0367   Reconstruction               0-003-018  03/03/06     DONE    DONE       DONE      11/28/05   11/23/05   08/26/05   05/17/05   10                     1,202,296     1,202,296  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0537   Reconstruction               0-003-019  01/31/07     DONE    DONE       DONE      11/21/06   11/20/06   05/19/06   05/16/06   2,4,7                  1,464,000     1,464,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
07-1081   Reconstruction               0-003-020  05/22/08     DONE    DONE       DONE      12/10/07   12/10/07   06/25/07   05/15/07   2,4,9,10                 507,860             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Council Rock Elementary:
03-0737   Reconstruction               0-004-014  03/09/04     DONE    DONE       DONE      11/21/03   11/19/03   09/18/03   06/03/03   2,7,16                   389,086       389,086  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-0146   Additions and Alterations    0-004-015  12/14/04     DONE    DONE       DONE      08/20/04   08/17/04   09/22/03   03/16/04   02 - 16                2,970,000     2,384,407  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0538   Reconstruction               0-004-016  01/31/07     DONE    DONE       DONE      11/21/06   11/20/06   05/19/06   05/16/06   2,7,9                    902,800       902,800  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -       Reconstruction               0-004-017                                              /  /       /  /     07/09/08     /  /     8                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          French Road School:
03-0738   Reconstruction               0-006-016  03/09/04     DONE    DONE       DONE      11/21/03   11/19/03   09/18/03   06/03/03   2,155                    238,433       238,433  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-0147   Additions and Alterations    0-006-017  12/14/04     DONE    DONE       DONE      08/20/04   08/17/04   09/22/03   03/16/04   02 - 16                7,360,000     3,070,298  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-0147PR Additions and Alterations    0-006-017  12/14/04     DONE    DONE       DONE        /  /       /  /     09/22/03     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -       Reconstruction               0-006-018                                              /  /       /  /     07/09/08     /  /     8                              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Admin Bldg (Old Twelve Crn ES-0005):
07-1082   Reconstruction               1-005-001  05/22/08     DONE    DONE       DONE      12/10/07   12/10/07   06/26/07   05/15/07   2,8                      779,740             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GATES CHILI CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-04-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Gates Chili High:
  -       Reconstruction               0-001-009                                              /  /       /  /     05/14/04     /  /     155,15,16                      0    36,819,849  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0897   Reconstruction               0-001-010  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   05/14/04   03/29/05   8,9,16                 1,252,366             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
05-0536   Additions and Alterations    0-001-011  05/11/06     DONE    DONE       DONE      01/03/06   12/20/05   12/22/04   03/29/05   02 - 16               46,162,580    28,039,559  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
  -    PR Additions and Alterations    0-001-012                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0813   Additions and Alterations    0-001-012  03/09/06     DONE    DONE       DONE      02/24/06   02/23/06     /  /     03/29/05   02 - 16                  552,000       552,000  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
  -       Reconstruction               0-001-013                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0483FP Reconstruction               0-001-FP1  10/28/03     DONE    DONE       DONE      10/20/03     /  /       /  /       /  /     16                             0    12,318,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Florence Brasser:
04-1068   Reconstruction               0-002-008  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                334,399       334,399  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
06-0886   Reconstruction               0-002-009  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   2,4,7,8,9,14,155,15,     604,900             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
  -       Reconstruction               0-002-010                                              /  /       /  /     11/21/05     /  /     13,155,15,16                   0     5,026,758  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-002-011                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0480FP Reconstruction               0-002-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     1,548,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Washington Irving School:
04-1069   Reconstruction               0-005-008  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                202,623       202,623  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -    PR Additions and Alterations    0-005-009                                              /  /       /  /     12/22/04     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0887   Additions and Alterations    0-005-009  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   02 - 16                  266,300             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
05-0898   Reconstruction               0-005-010  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   11/21/05   03/29/05   10,155,15,16              13,243             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               0-005-011                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0479FP Reconstruction               0-005-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     2,280,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Middle School:
04-1070   Reconstruction               0-006-006  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                854,657       854,657  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -    PR Additions and Alterations    0-006-007                                              /  /       /  /     12/22/04     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0888   Additions and Alterations    0-006-007  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   02 - 16                3,324,701             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
05-0899   Reconstruction               0-006-008  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   11/21/05   03/29/05   10,155,15,16             307,573             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               0-006-009                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0485FP Reconstruction               0-006-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     9,078,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Paul Rd Elementary:
04-1071   Reconstruction               0-007-009  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                363,297       363,297  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
06-0889   Reconstruction               0-007-010  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   2,10,155,15,16           501,400             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
05-0900   Reconstruction               0-007-011  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   11/21/05   03/29/05   10,155,15,16             148,892             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               0-007-012                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0481FP Reconstruction               0-007-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     3,402,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Walt Disney School:
04-1072   Reconstruction               0-008-008  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                234,393       234,393  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -    PR Additions and Alterations    0-008-009                                              /  /       /  /     12/22/04     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0890   Additions and Alterations    0-008-009  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   02 - 16                  528,900             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
05-0901   Reconstruction               0-008-010  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   11/21/05   03/29/05   10,155,15,16               7,677             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               0-008-011                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0484FP Reconstruction               0-008-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     3,024,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Neil Armstrong Elementary:
04-1073   Reconstruction               0-009-008  08/08/05     DONE    DONE       DONE      04/01/05   03/31/05   05/14/04   03/29/05   155,15,16                260,747       260,747  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -    PR Additions and Alterations    0-009-009                                              /  /       /  /     12/22/04     /  /     02 - 16                        0     9,280,224  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0891   Additions and Alterations    0-009-009  12/26/07     DONE    DONE       DONE      02/07/07   02/05/07   12/22/04   03/29/05   02 - 16                1,074,700     1,074,700  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 
05-0902   Reconstruction               0-009-010  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   11/21/05   03/29/05   10,155,15,16               7,677             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               0-009-011                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
03-0482FP Reconstruction               0-009-FP1  10/29/03     DONE    DONE       DONE      10/23/03     /  /       /  /       /  /     16                             0     5,184,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Administration Building:
05-0903   Reconstruction               1-003-005  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   05/14/04   03/29/05   155,15,16                161,750             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               1-003-006                                              /  /       /  /     12/22/04     /  /     2,4,9,155,15,16                0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               1-003-007                                              /  /       /  /     05/25/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Trans.& Facilities Complex:
05-0904   Reconstruction               5-004-006  05/24/07     DONE    DONE       DONE      03/08/06   03/06/06   05/14/04   03/29/05   155,15,16                 65,784             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Saren Engineering, INC.             
  -       Reconstruction               5-004-007                                              /  /       /  /     12/22/04     /  /     2,4,7,8,9,13,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-004-008                                              /  /       /  /     05/24/07     /  /     13,16                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Transportation Building:
05-0052   New Construction             5-016-001  09/07/05     DONE    DONE       DONE      07/15/05   07/14/05   12/22/04   03/29/05   02 - 16                4,647,830     4,647,830  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 

          Press Box:
05-1166   New Construction             7-018-001  05/11/06     DONE    DONE       DONE      04/18/06   04/17/06   03/31/06   03/29/05   02 - 16                   44,500             0  DDJ             0           0            0
                                                                                                                                                                                                                                 La Bella Associates                 


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREECE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-05-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Barnard Elementary:
06-0582   Reconstruction               0-001-013  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06   09/08/06   05/16/06   15                        25,610        25,610  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
06-0657   Reconstruction               0-001-014  05/15/07     DONE    DONE       DONE      12/22/06   12/22/06   09/13/06   05/16/06   2,4,7,8,9,10,155,15,     272,000       272,000  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-001-015                                              /  /       /  /     04/20/07     /  /     2,7,8,155,15,16                0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Craig Hill Elementary:
  -       Reconstruction               0-003-008                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0     8,661,252  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Greece Olympia High School:
03-0596   Reconstruction               0-004-022  06/30/04     DONE    DONE       DONE      11/04/03   11/03/03   06/09/03   12/09/03   7                        191,680       191,680  JOD             0           0            0
                                                                                                                                                                                                                                                                     
03-0605   Reconstruction               0-004-023  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   06/09/03   05/18/04   7                      1,521,854     1,521,854  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
04-1239   Reconstruction               0-004-024  08/10/05     DONE    DONE       DONE      05/10/05   05/05/05   10/13/04   05/17/05   2                        457,780       457,780  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
06-0165   Reconstruction               0-004-025  11/13/06     DONE    DONE       DONE      08/09/06   08/03/06   12/20/05   05/16/06   10                        22,544        22,544  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-004-026                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0    25,156,218  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-004-027                                              /  /       /  /     08/01/08     /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Odyssey Mid/High (fmly Hoover):
05-1128   Reconstruction               0-005-016  11/10/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   2,10,155,15,16            92,492        92,492  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-005-017                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0    10,792,496  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Longridge School:
03-0597   Reconstruction               0-006-009  06/30/04     DONE    DONE       DONE      11/04/03   11/03/03   06/06/03   12/09/03   2                        180,427             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-006-010                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,14,155,           0    11,310,273  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-006-011                                              /  /       /  /     08/01/08     /  /     16                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Paddy Hill School:
02-1301   Additions and Alterations    0-007-009  11/14/03     DONE    DONE       DONE      02/04/03   11/26/02   03/20/00   06/21/00   02 - 16                3,904,120     3,335,578  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
03-0598   Reconstruction               0-007-011  06/30/04     DONE    DONE       DONE      11/04/03   11/03/03   06/09/03   12/09/03   155                    1,506,770     1,506,770  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
05-1129   Reconstruction               0-007-012  11/10/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   8,9,10,155,15,16         138,461       138,461  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-007-013                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0     5,939,773  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          West Ridge School:
06-0166   Reconstruction               0-008-011  11/13/06     DONE    DONE       DONE      08/09/06   08/03/06   12/20/05   05/16/06   10,16                     46,909        46,909  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-008-012                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,14,155,           0     7,097,097  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Autumn Lane Elementary:
03-0599   Reconstruction               0-009-011  06/30/04     DONE    DONE       DONE      11/04/03   11/03/03   06/06/03   12/09/03   7,9,155                  495,307       495,307  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-009-012                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0     6,380,154  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          English Village Elementary:
03-0600   Reconstruction               0-010-015  06/30/04     DONE    DONE       DONE      11/04/03   11/03/03   06/06/03   12/09/03   7                        406,637       406,637  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-010-016                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,14,155,           0     6,090,147  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Lake Shore Elementary:
03-0606   Reconstruction               0-011-010  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   06/09/03   05/18/04   7                        406,637       406,637  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
04-1240   Reconstruction               0-011-011  08/10/05     DONE    DONE       DONE      05/10/05   05/05/05   10/13/04   05/17/05   2                        206,220       206,220  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-011-012                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0     5,800,140  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Arcadia High/Middle School:
02-1302   Additions and Alterations    0-012-025  11/14/03     DONE    DONE       DONE      02/04/03   11/26/02   04/17/00   06/21/00   02 - 16               13,109,000    13,109,000  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
03-0601XX Reconstruction               0-012-028  06/30/04               CANCELLED          11/04/03   11/03/03   06/06/03   12/09/03   4,8,9,155,16             323,799       323,799  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
05-1130   Reconstruction               0-012-029  11/10/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   2,7,8,9,10,155,15,16     345,659       345,659  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
06-0167   Reconstruction               0-012-030  12/05/06     DONE    DONE       DONE      08/09/06   08/03/06   08/04/06   05/16/06   10                        22,544        22,544  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-012-031                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,14,155,           0    23,108,814  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0583   Reconstruction               0-012-032  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06   09/08/06   05/16/06   16                       113,701       113,701  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
06-1103   Reconstruction               0-012-033  04/10/07     DONE    DONE       DONE      03/14/07   03/12/07   01/22/07   05/16/06   13                       114,290        70,000  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
07-0795   Reconstruction               0-012-034  11/27/07     DONE    DONE       DONE      11/13/07   11/09/07   10/02/07   05/15/07   7                      2,000,000     2,000,000  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Buckman Heights Elementary:
03-0602   Reconstruction               0-013-008  06/30/04     DONE    DONE       DONE      11/03/03   11/03/03     /  /     05/18/04   8                        283,209       283,209  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-013-009                                              /  /       /  /     08/10/06     /  /     2,4,7,8,9,10,155,15,           0     7,344,130  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Brookside Elementary:
04-1241   Reconstruction               0-014-010  08/10/05     DONE    DONE       DONE      05/10/05   05/05/05   10/13/04   05/17/05   2,16                      66,400        66,400  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-014-011                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0     6,173,356  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0584   Reconstruction               0-014-012  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06     /  /     05/16/06   2                        179,270       179,270  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
  -       Reconstruction               0-014-013                                              /  /       /  /     08/01/08     /  /     155,15,16                      0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Parkland Elementary:
04-1242   Reconstruction               0-015-009  08/10/05     DONE    DONE       DONE      05/10/05   05/05/05   10/13/04   05/17/05   2,16                      40,640        40,640  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-015-010                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0     4,930,119  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-015-011                                              /  /       /  /     08/01/08     /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Holmes Road Elementary:
05-1131   Reconstruction               0-016-006  11/11/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   2,7,10,15                975,718       975,718  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-016-007                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,14,155,           0     6,999,071  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0585   Reconstruction               0-016-008  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06   09/08/06   05/16/06   2,155,15,16              384,150       384,150  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
  -       Reconstruction               0-016-009                                              /  /       /  /     08/11/08     /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Athena Middle/High School:
03-0607   Reconstruction               0-017-028  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   06/09/03   05/18/04   14                       164,050       164,050  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
05-1132   Reconstruction               0-017-029  11/10/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   2,7,8,9,10,155,15,16     786,748       786,748  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-017-030                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0    46,905,690  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-017-031                                              /  /       /  /     09/08/06     /  /     2                              0    46,905,690  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-017-032                                              /  /       /  /       /  /       /  /     155,16                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Kirk Road Elem.:
02-1303   Additions and Alterations    0-018-012  11/14/03     DONE    DONE       DONE      02/04/03   11/26/02   03/20/00   06/21/00   02 - 16                3,904,120     3,231,944  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0168   Reconstruction               0-018-014  12/05/06     DONE    DONE       DONE      08/09/06   08/03/06   12/20/05   05/16/06   10                        17,903        17,903  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-018-015                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0     7,173,636  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Apollo Middle School:
03-0610   Reconstruction               0-031-015  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   06/06/03   05/18/04   8,155                    455,813       455,813  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
05-1133   Reconstruction               0-031-016  11/10/06     DONE    DONE       DONE      04/13/06   04/03/06   12/20/05   05/17/05   2,8,10                   660,334       660,334  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-031-017                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0    23,985,602  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0586   Reconstruction               0-031-018  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06   09/08/06   05/16/06   4,7,8,9,155,15,16        422,560       422,560  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey
  -       Reconstruction               0-031-019                                              /  /       /  /     08/01/08     /  /     9,155,16                       0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Pine Brook Elementary:
02-1304   Additions and Alterations    0-036-003  11/14/03     DONE    DONE       DONE      02/04/03   11/26/02   02/08/01   06/21/00   02 - 16                1,318,871       941,323  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0169   Reconstruction               0-036-004  12/05/06     DONE    DONE       DONE      08/09/06   08/03/06   12/20/05   05/16/06   10                        17,903        17,903  HCM             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               0-036-005                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0     8,055,735  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0587   Reconstruction               0-036-006  05/08/07     DONE    DONE       DONE      12/04/06   12/01/06   09/08/06   05/16/06   16                       102,114       102,114  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Greece Ridge Mall-Continuing Ed.:
03-1040TQ Temporary Quarters           0-042-002  01/28/04     DONE    DONE       DONE      01/27/04   01/26/04   12/03/01     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-042-003                                              /  /       /  /     08/11/06     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout/Storage @ Athena High School:
07-0692DB Discovered Building          2-046-001  11/20/07     DONE    DONE       DONE      11/01/07   10/29/07   04/25/01     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Dugout/Storage @ Arcadia High School:
07-0693DB Discovered Building          2-047-001  11/20/07     DONE    DONE       DONE      11/01/07   10/29/07   04/25/01     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Dugout/Storage @ Olympia High School:
07-0711DB Discovered Building          2-048-001  11/20/07     DONE    DONE       DONE      11/05/07   10/29/07   04/25/01     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Longridge Storage Building:
04-1235   New Construction             2-050-001  09/20/05     DONE    DONE       DONE      05/10/05   05/05/05   02/23/04     /  /     02 - 16                   90,791             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               2-050-002                                              /  /       /  /       /  /       /  /     2,4,7,8,9,10,14,155,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -    XX New Construction             2-052-001                         CANCELLED            /  /       /  /     10/08/04     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Trlr @ Athena Highschool:
07-0712DB Discovered Building          2-054-001  11/20/07     DONE    DONE       DONE      11/05/07   10/29/07   12/15/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Storage Trailer @ Olympic Highschool:
07-0713DB Discovered Building          2-055-001  11/20/07     DONE    DONE       DONE      11/05/07   10/29/07   12/18/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Storage Trailer @ West Ridge ES:
07-0714DB Discovered Building          2-056-001  11/20/07     DONE    DONE       DONE      11/05/07   10/29/07   12/18/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Gas Equipment storage@longridge es:
07-0715DB Discovered Building          2-057-001  11/20/07     DONE    DONE       DONE      11/05/07   10/29/07     /  /       /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers & Architects & Survey

          Maintenance Garage:
  -       Reconstruction               3-002-002                                              /  /       /  /     04/20/07     /  /     2,8,155,15,16                  0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Transportation Annex:
03-0603XX Reconstruction               5-023-008  06/30/04               CANCELLED          11/04/03   11/03/03   06/09/03   12/09/03   4,8,9,155,15,16          243,579       243,579  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
03-0608   Reconstruction               5-023-009  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   06/09/03   05/18/04   155,15,16                270,954       270,954  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               5-023-010                                              /  /       /  /     08/14/06     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-023-011                                              /  /       /  /     08/01/08     /  /     2,155                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bldg Grounds/Bus Storage:
03-0609   Reconstruction               5-024-007  06/30/04     DONE    DONE       DONE      11/05/03   11/03/03   07/31/03   05/18/04   155                        9,086             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               5-024-008                                              /  /       /  /     12/20/05     /  /     8,9,155,15,16                  0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-024-009                                              /  /       /  /     08/14/06     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-024-010                                              /  /       /  /     08/01/08     /  /     13                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Apollo Concession/Storage:
04-1236   Reconstruction               7-035-002  09/20/05     DONE    DONE       DONE      05/10/05   05/05/05   10/13/04     /  /     8,10,155,15,16            15,960             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               7-035-003                                              /  /       /  /     08/14/06     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Toilet Rm. Bldg. @ Apollo MS:
04-1237   New Construction             7-051-001  09/20/05     DONE    DONE       DONE      05/10/05   05/05/05   10/08/04     /  /     02 - 16                  314,500             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               7-051-002                                              /  /       /  /     08/14/06     /  /     2,4,7,8,9,10,14,155,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Pressbox/Storage @ Athena Middle/HS:
04-1238   Reconstruction               7-053-001  09/20/05     DONE    DONE       DONE      05/10/05   05/05/05   10/21/04     /  /                               60,460             0  JOD             0           0            0
                                                                                                                                                                                                                                 SWBR Architects P.C.                
  -       Reconstruction               7-053-002                                              /  /       /  /     08/14/06     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Districtwide:
  -       Reconstruction               7-999-003                                              /  /       /  /     08/22/08     /  /     10,16                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




EAST IRONDEQUOIT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-08-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pardee School-Helendale Rd School:
05-0632   Reconstruction               0-001-011  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   2,4,7,8,9,10,155,15,           0     5,965,628  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1503   Reconstruction               0-001-012  10/02/07     DONE    DONE       DONE      05/16/07   05/16/07   12/04/06   02/28/07   2,4,7,8,9,10,13,14,1     263,499       263,499  MGL             0           0       70,091
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-001-013                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
03-1238SC Visual Structural Inspection 0-001-SC1  03/09/04     DONE    DONE       DONE      02/27/04   02/27/04     /  /       /  /     16                         1,500         1,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Eastridge Sr High:
05-0633   Reconstruction               0-002-016  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   2,4,7,8,9,155,15,16    1,038,533     1,038,533  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1504   Reconstruction               0-002-017  10/02/07     DONE    DONE       DONE      05/16/07   05/16/07   12/04/06   02/28/07   2,4,7,8,9,10,13,14,1   1,719,782     1,719,782  MGL             0           0      305,263
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-002-018                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Ivan L. Green  School:
05-0634   Reconstruction               0-004-013  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   2,4,7,9,155,15,16      1,208,059     1,208,059  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1505   Reconstruction               0-004-014  10/02/07     DONE    DONE       DONE      05/16/07   05/16/07   12/04/06   02/28/07   2,4,7,8,9,10,13,14,1     661,966       661,966  MGL             0           0      176,083
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-004-015                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
03-1239SC Visual Structural Inspection 0-004-SC1  03/09/04     DONE    DONE       DONE      02/03/04   02/03/04     /  /       /  /     16                         1,500         1,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Laurelton Pardee School:
05-0635   Reconstruction               0-005-014  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   2,4,7,8,9,155,15,16    1,421,502     1,421,502  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1506   Reconstruction               0-005-015  10/02/07     DONE    DONE       DONE      05/16/07   05/16/07   12/04/06   02/28/07   2,4,7,8,9,10,13,14,1   1,901,379     1,901,379  MGL             0           0      405,767
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-005-016                                              /  /       /  /     11/15/07     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Durand Eastman:
04-1090PR Additions and Alterations    0-007-013  09/26/05     DONE    DONE       DONE      04/06/05   04/04/05   10/12/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
05-0636   Additions and Alterations    0-007-013  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   02 - 16                8,885,136     8,164,292  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    XX Additions and Alterations    0-007-014                         CANCELLED            /  /       /  /     11/10/04     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-1507   Reconstruction               0-007-015  10/02/07     DONE    DONE       DONE      05/16/07   05/16/07   12/04/06   02/28/07   2,4,7,8,9,10,13,14,1     543,374       543,374  MGL             0           0      144,537
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-007-016                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
03-1240SC Visual Structural Inspection 0-007-SC1  03/09/04     DONE    DONE       DONE      02/27/03   02/27/03     /  /       /  /     16                         1,500         1,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Middle School:
05-0637   Reconstruction               0-013-003  03/27/06     DONE    DONE       DONE      01/19/06   01/19/06   10/12/04   03/22/05   2,8,9,10,13,16            46,770        46,770  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-013-004                                              /  /       /  /     12/04/06     /  /     2,4,7,8,9,10,13,14,1           0    25,183,608  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-013-005                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Athletic Storage Building:
  -    XX Reconstruction               2-014-003                         CANCELLED            /  /       /  /     10/12/04     /  /     8,9,16                         0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               2-014-004                                              /  /       /  /     11/15/07     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Maintenance Bldg:
  -    XX Reconstruction               3-009-005                         CANCELLED            /  /       /  /     10/12/04     /  /     2,8,9,15                       0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               3-009-006                                              /  /       /  /     11/15/07     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -    XX Reconstruction               5-003-004                         CANCELLED            /  /       /  /     10/13/04     /  /     8,9                            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               5-003-005                                              /  /       /  /     11/15/07     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Transporation Building:
  -       New Construction             5-016-001                                              /  /       /  /     11/15/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Stand:
  -    PR New Construction             7-017-001                                              /  /       /  /     05/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Grandstand with Pressbox:
  -    PR New Construction             7-018-001                                              /  /       /  /     05/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          District Wide:
  -       Reconstruction               7-999-003                                              /  /       /  /     01/17/08     /  /     16                             0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bishop Kearney High School:
05-1413TQ Temporary Quarters           8-015-L01  08/07/06     DONE    DONE       DONE      06/22/06   06/19/06   02/17/05     /  /                               85,400        85,400  RDR             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WEST IRONDEQUOIT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-08-03-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Irondequoit High School:
03-1597   Reconstruction               0-001-019  08/20/04     DONE    DONE       DONE      06/02/04   06/02/04   12/19/03   05/18/04   2,10,16                1,885,159     1,885,159  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
04-1156   Reconstruction               0-001-020  06/02/05     DONE    DONE       DONE      04/13/05   04/11/05   03/14/05   05/17/05   8                        364,022       364,022  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
05-0427   Reconstruction               0-001-021  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                        78,566        78,566  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-0297   Reconstruction               0-001-022  01/24/07     DONE    DONE       DONE      10/04/06   10/04/06   06/05/06   05/16/06   9,16                     172,000       172,000  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0528   Additions and Alterations    0-001-023  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   06/20/06   05/15/07   02 - 16                5,273,315             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0529   Reconstruction               0-001-024  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,8,155,15,16            288,088             0  MGL             0           0       50,703
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0512   Reconstruction               0-001-025  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   8,9,13,16                 80,700        80,700  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
03-0380SC Visual Structural Inspection 0-001-SC4  10/06/03     DONE    DONE       DONE      09/18/03     /  /       /  /       /  /     16                        18,966        18,966  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0065SC Visual Structural Inspection 0-001-SC5  08/07/06     DONE    DONE       DONE      06/12/06   06/12/06     /  /       /  /     16                        12,663        12,663  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Ruben Dake JH School 7-8:
04-1155   Reconstruction               0-002-008  06/02/05     DONE    DONE       DONE      04/13/05   04/11/05   03/14/05   05/17/05   8                        234,222       234,222  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
05-0428   Reconstruction               0-002-009  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   9,16                      28,571        28,571  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-0298   Reconstruction               0-002-010  01/24/07     DONE    DONE       DONE      10/04/06   10/04/06   06/05/06   05/16/06   9,10,16                  132,763       132,763  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0530   Reconstruction               0-002-011  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,8,9,155,15,16          453,380             0  MGL             0           0       79,795
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0513   Reconstruction               0-002-012  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   7,9,13,16                103,000             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
04-0580SC Visual Structural Inspection 0-002-SC2  12/01/04     DONE    DONE       DONE      10/28/04   10/28/04     /  /       /  /     16                         1,392         1,392  JOD             0           0            0
                                                                                                                                                                                                                                                                     
05-0130SC Visual Structural Inspection 0-002-SC3  08/17/05     DONE    DONE       DONE      08/02/05   08/02/05     /  /       /  /     16                         7,992         7,992  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0066SC Visual Structural Inspection 0-002-SC5  08/07/06     DONE    DONE       DONE      06/12/06   06/12/06     /  /       /  /     16                         2,412         2,412  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Rogers/Southlawn School:
05-0429   Reconstruction               0-003-010  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                         2,259             0  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-003-011                                              /  /       /  /     11/15/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0787   Additions and Alterations    0-003-011  01/24/07     DONE    DONE       DONE      01/18/07   01/18/07   11/15/06   05/16/06   02 - 16                   14,000        14,000  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0531   Reconstruction               0-003-012  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,7,8,155,15,16          967,722             0  MGL             0           0      170,319
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0514   Reconstruction               0-003-013  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   9                         21,750             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Iroquois/Colebrook School:
05-0430   Reconstruction               0-004-008  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   10,16                     72,903        72,903  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-0788   Reconstruction               0-004-009  01/24/07     DONE    DONE       DONE      01/18/07   01/18/07   07/26/06   05/16/06   2,8,9                     19,500        19,500  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-004-010                                              /  /       /  /     11/15/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-0532   Reconstruction               0-004-011  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   7,8,9,13,155,16        1,056,800             0  MGL             0           0      185,997
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0515   Reconstruction               0-004-012  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   2,9                       80,800             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Seneca Elem School K-3:
05-0431   Reconstruction               0-006-005  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   9,10,16                   16,486        16,486  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0533   Reconstruction               0-006-006  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,8,155,16               430,698             0  MGL             0           0       75,803
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Listwood Elem Sch K-3:
03-1307XX Reconstruction               0-008-004  04/21/04               CANCELLED          03/23/04   03/22/04   01/26/04   12/07/99   2                        120,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Gym Building:
07-0534   Reconstruction               0-021-003  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   13,155,16                125,000             0  MGL             0           0       22,000
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0516   Reconstruction               0-021-004  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   2                         43,800             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          New Listwood School:
05-0432   Reconstruction               0-027-002  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                         1,086             0  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0535   Additions and Alterations    0-027-003  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   02 - 16                   26,500             0  MGL             0           0        4,664
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0517   Reconstruction               0-027-004  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   13                        20,200             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          New Brookview Elementary:
05-0433   Reconstruction               0-028-002  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                         1,086             0  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0536   Reconstruction               0-028-003  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,13,16                   58,200             0  MGL             0           0       10,243
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0518   Reconstruction               0-028-004  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   2,9,16                    67,200             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          New Briarwood Elementary:
05-0434   Reconstruction               0-029-002  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                         1,086             0  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0537   Reconstruction               0-029-003  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   16                        26,500             0  MGL             0           0        4,664
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0519   Reconstruction               0-029-004  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   2,9,13                    20,200             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Colebrook:
05-0435   Reconstruction               0-032-002  03/31/06     DONE    DONE       DONE      12/08/05   12/07/05   04/19/05   05/17/05   16                         1,086             0  RDR             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0538   Reconstruction               0-032-003  03/19/08     DONE    DONE       DONE      10/11/07   10/09/07   03/06/07   05/15/07   2,16                      28,300             0  MGL             0           0        4,981
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0520   Reconstruction               0-032-004  03/12/08     DONE    DONE       DONE      10/09/07   10/05/07   03/26/07   05/15/07   2,13,16                   36,350             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          New Administration Building:
03-1598   New Construction             1-033-001  08/09/04     DONE    DONE       DONE      06/02/04   06/02/04   01/26/04   05/18/04   02 - 16                1,472,500             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    1-033-002                                              /  /       /  /     11/15/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0789   Additions and Alterations    1-033-002  01/24/07     DONE    DONE       DONE      01/18/07   01/18/07   11/15/06   05/16/06   02 - 16                    8,700             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Environmental Svcs. Building:
  -    XX Reconstruction               3-020-003                         CANCELLED            /  /       /  /     08/25/04     /  /     7                              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HONEOYE FALLS - LIMA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 26-09-01-06
last updated on 09/04/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Manor Elementary:
07-0842   Reconstruction               0-001-009  05/13/08     DONE    DONE       DONE      11/19/07   11/16/07   01/19/07   05/15/07   4,7,8,9,155,15,16      1,560,300             0  MGL             0           0            0
                                                                                                                                                                                                                                 Design Group Educ. Fac. Dept.       

          Middle School-Joined to H.S.-003 '89:
  -    XX Reconstruction               0-002-008                         CANCELLED            /  /       /  /     01/19/07     /  /     4,7,8,9,155,15,16              0     6,037,349  MGL             0           0            0