REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Twelve Corners Middle School:
04-0490 Reconstruction 0-002-016 02/11/05 DONE DONE DONE 12/09/04 12/07/04 11/02/04 05/18/04 4 77,837 77,837 DDJ 0 0 0
Thomas Associates
06-0536 Reconstruction 0-002-017 01/31/07 DONE DONE DONE 11/21/06 11/20/06 05/19/06 05/16/06 2,4 73,200 73,200 DDJ 0 0 0
Thomas Associates
08-0272 Additions and Alterations 0-002-018 02/13/09 DONE DONE DONE 09/08/08 09/03/08 07/09/08 05/20/08 02 - 16 441,490 0 DDJ 0 0 134,213
Thomas Associates
09-0166 Reconstruction 0-002-019 ADDENDUM REQ'D 08/27/09 08/25/09 07/17/09 05/19/09 7,155,15,16 0 18,569,234 DDJ 0 0 0
Tetra Tech Architects & Engineers
Brighton Senior High:
04-0491 Reconstruction 0-003-017 02/11/05 DONE DONE DONE 12/09/04 12/07/04 11/02/04 05/18/04 9,10,15 1,034,075 1,034,075 DDJ 0 0 0
Thomas Associates
05-0367 Reconstruction 0-003-018 03/03/06 DONE DONE DONE 11/28/05 11/23/05 08/26/05 05/17/05 10 1,202,296 1,202,296 DDJ 0 0 0
Thomas Associates
06-0537 Reconstruction 0-003-019 01/31/07 DONE DONE DONE 11/21/06 11/20/06 05/19/06 05/16/06 2,4,7 1,464,000 1,464,000 DDJ 0 0 0
Thomas Associates
07-1081 Reconstruction 0-003-020 05/22/08 DONE DONE DONE 12/10/07 12/10/07 06/25/07 05/15/07 2,4,9,10 507,860 0 DDJ 0 0 0
Thomas Associates
09-0167 Reconstruction 0-003-021 ADDENDUM REQ'D 08/27/09 08/25/09 07/14/09 05/19/09 2,9,155,15,16 0 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
Council Rock Elementary:
04-0146 Additions and Alterations 0-004-015 12/14/04 DONE DONE DONE 08/20/04 08/17/04 09/22/03 03/16/04 02 - 16 3,203,481 2,384,407 DDJ 0 0 0
Thomas Associates
06-0538 Reconstruction 0-004-016 01/31/07 DONE DONE DONE 11/21/06 11/20/06 05/19/06 05/16/06 2,7,9 902,800 902,800 DDJ 0 0 0
Thomas Associates
08-0273 Reconstruction 0-004-017 02/13/09 DONE DONE DONE 09/08/08 09/03/08 07/09/08 05/20/08 8 962,830 962,830 DDJ 0 0 292,701
Thomas Associates
French Road School:
04-0147 Additions and Alterations 0-006-017 12/14/04 DONE DONE DONE 08/20/04 08/17/04 09/22/03 03/16/04 02 - 16 6,790,029 3,436,278 DDJ 0 0 0
Thomas Associates
04-0147PR Additions and Alterations 0-006-017 12/14/04 DONE DONE DONE / / / / 09/22/03 / / 02 - 16 0 0 DDJ 0 0 0
Thomas Associates
08-0274 Reconstruction 0-006-018 02/13/09 DONE DONE DONE 09/08/08 09/03/08 07/09/08 05/20/08 8 71,680 0 DDJ 0 0 21,791
Thomas Associates
Admin Bldg (Old Twelve Crn ES-0005):
07-1082 Reconstruction 1-005-001 05/22/08 DONE DONE DONE 12/10/07 12/10/07 06/26/07 05/15/07 2,8 779,740 0 DDJ 0 0 0
Thomas Associates
09-0168 Reconstruction 1-005-002 ADDENDUM REQ'D 08/27/09 08/25/09 07/17/09 05/19/09 2,7,9,155,15,16 0 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
Athletic Storage Building:
09-0169 New Construction 2-016-001 ADDENDUM REQ'D 08/27/09 08/25/09 07/17/09 05/19/09 02 - 16 0 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
District-Wide:
09-0170 Reconstruction 7-999-002 ADDENDUM REQ'D 08/27/09 08/25/09 07/17/09 05/19/09 13 0 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Gates Chili High:
05-0897 Reconstruction 0-001-010 05/24/07 DONE DONE DONE 03/08/06 03/06/06 05/14/04 03/29/05 8,9,16 1,252,366 1,252,366 DDJ 0 0 0
Saren Engineering, INC.
05-0536 Additions and Alterations 0-001-011 05/11/06 DONE DONE DONE 01/03/06 12/20/05 12/22/04 03/29/05 02 - 16 47,562,580 31,788,465 DDJ 0 0 0
La Bella Associates
- PR Additions and Alterations 0-001-012 / / / / / / / / 02 - 16 0 0 DDJ 0 0 0
05-0813 Additions and Alterations 0-001-012 03/09/06 DONE DONE DONE 02/24/06 02/23/06 / / 03/29/05 02 - 16 843,032 770,976 DDJ 0 0 0
La Bella Associates
- Reconstruction 0-001-013 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
08-1246 Reconstruction 0-001-015 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 8,155,15,16 0 43,079,538 DDJ 0 0 0
La Bella Associates
Florence Brasser:
04-1068 Reconstruction 0-002-008 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 334,399 334,399 DDJ 0 0 0
Saren Engineering, INC.
06-0886 Reconstruction 0-002-009 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 2,4,7,8,9,14,155,15, 1,053,348 1,053,348 DDJ 0 0 0
La Bella Associates
- Reconstruction 0-002-010 / / / / 11/21/05 / / 13,155,15,16 0 5,026,758 DDJ 0 0 0
- Reconstruction 0-002-011 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
08-1247 Reconstruction 0-002-012 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 8 0 0 DDJ 0 0 0
La Bella Associates
Washington Irving School:
04-1069 Reconstruction 0-005-008 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 202,623 202,623 DDJ 0 0 0
Saren Engineering, INC.
- PR Additions and Alterations 0-005-009 / / / / 12/22/04 / / 02 - 16 0 0 DDJ 0 0 0
06-0887 Additions and Alterations 0-005-009 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 02 - 16 129,140 129,140 DDJ 0 0 0
La Bella Associates
05-0898 Reconstruction 0-005-010 05/24/07 DONE DONE DONE 03/08/06 03/06/06 11/21/05 03/29/05 10,155,15,16 13,243 13,243 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 0-005-011 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
Middle School:
04-1070 Reconstruction 0-006-006 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 854,657 854,657 DDJ 0 0 0
Saren Engineering, INC.
- PR Additions and Alterations 0-006-007 / / / / 12/22/04 / / 02 - 16 0 0 DDJ 0 0 0
06-0888 Additions and Alterations 0-006-007 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 02 - 16 3,733,929 3,040,018 DDJ 0 0 0
La Bella Associates
05-0899 Reconstruction 0-006-008 05/24/07 DONE DONE DONE 03/08/06 03/06/06 11/21/05 03/29/05 10,155,15,16 307,573 307,573 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 0-006-009 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
08-1248 Reconstruction 0-006-010 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 13,15,16 0 0 DDJ 0 0 0
La Bella Associates
Paul Rd Elementary:
04-1071 Reconstruction 0-007-009 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 363,297 363,297 DDJ 0 0 0
Saren Engineering, INC.
06-0889 Reconstruction 0-007-010 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 2,10,155,15,16 381,128 381,128 DDJ 0 0 0
La Bella Associates
05-0900 Reconstruction 0-007-011 05/24/07 DONE DONE DONE 03/08/06 03/06/06 11/21/05 03/29/05 10,155,15,16 148,892 148,892 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 0-007-012 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
Walt Disney School:
04-1072 Reconstruction 0-008-008 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 234,393 234,393 DDJ 0 0 0
Saren Engineering, INC.
- PR Additions and Alterations 0-008-009 / / / / 12/22/04 / / 02 - 16 0 0 DDJ 0 0 0
06-0890 Additions and Alterations 0-008-009 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 02 - 16 455,425 455,425 DDJ 0 0 0
La Bella Associates
05-0901 Reconstruction 0-008-010 05/24/07 DONE DONE DONE 03/08/06 03/06/06 11/21/05 03/29/05 10,155,15,16 7,677 0 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 0-008-011 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
08-1249 Reconstruction 0-008-012 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 155,15,16 0 0 DDJ 0 0 0
La Bella Associates
Neil Armstrong Elementary:
04-1073 Reconstruction 0-009-008 08/08/05 DONE DONE DONE 04/01/05 03/31/05 05/14/04 03/29/05 155,15,16 260,747 260,747 DDJ 0 0 0
Saren Engineering, INC.
- PR Additions and Alterations 0-009-009 / / / / 12/22/04 / / 02 - 16 0 9,280,224 DDJ 0 0 0
06-0891 Additions and Alterations 0-009-009 12/26/07 DONE DONE DONE 02/07/07 02/05/07 12/22/04 03/29/05 02 - 16 1,025,250 1,025,250 DDJ 0 0 0
La Bella Associates
05-0902 Reconstruction 0-009-010 05/24/07 DONE DONE DONE 03/08/06 03/06/06 11/21/05 03/29/05 10,155,15,16 7,677 0 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 0-009-011 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
08-1250 Reconstruction 0-009-012 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 155,15,16 0 0 DDJ 0 0 0
La Bella Associates
Administration Building:
05-0903 Reconstruction 1-003-005 05/24/07 DONE DONE DONE 03/08/06 03/06/06 05/14/04 03/29/05 155,15,16 161,750 0 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 1-003-006 / / / / 12/22/04 / / 2,4,9,155,15,16 0 0 DDJ 0 0 0
- Reconstruction 1-003-007 / / / / 05/25/07 / / 13,16 0 0 DDJ 0 0 0
08-1251 Reconstruction 1-003-008 ADDENDUM REQ'D 02/23/09 02/17/09 12/29/08 05/01/05 155,15,16 0 0 DDJ 0 0 0
La Bella Associates
Trans.& Facilities Complex:
05-0904 Reconstruction 5-004-006 05/24/07 DONE DONE DONE 03/08/06 03/06/06 05/14/04 03/29/05 155,15,16 65,784 65,784 DDJ 0 0 0
Saren Engineering, INC.
- Reconstruction 5-004-007 / / / / 12/22/04 / / 2,4,7,8,9,13,155,15, 0 0 DDJ 0 0 0
- Reconstruction 5-004-008 / / / / 05/24/07 / / 13,16 0 0 DDJ 0 0 0
- Reconstruction 5-004-009 / / / / 12/29/08 / / 155,16 0 0 DDJ 0 0 0
New Transp Bldg-project canceled:
05-0052XX New Construction 5-016-001 09/07/05 CANCELLED 07/15/05 07/14/05 12/22/04 03/29/05 02 - 16 4,647,830 4,647,830 DDJ 0 0 0
La Bella Associates
Press Box:
05-1166 New Construction 7-018-001 05/11/06 DONE DONE DONE 04/18/06 04/17/06 03/31/06 03/29/05 02 - 16 44,500 0 DDJ 0 0 0
La Bella Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Barnard Elementary:
06-0582 Reconstruction 0-001-013 05/08/07 DONE DONE DONE 12/04/06 12/01/06 09/08/06 05/16/06 15 10,467 10,467 JOD 0 0 0
Hunt Engineers & Architects & Survey
06-0657 Reconstruction 0-001-014 05/15/07 DONE DONE DONE 12/22/06 12/22/06 09/13/06 05/16/06 2,4,7,8,9,10,155,15, 252,795 252,795 JOD 0 0 0
Clark Patterson Associates
- Reconstruction 0-001-015 / / / / 04/20/07 / / 2,7,8,155,15,16 0 0 JOD 0 0 0
Craig Hill Elementary:
08-0644 Reconstruction 0-003-008 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 1,114,251 0 JOD 0 0 398,337
Clark Patterson Associates
Greece Olympia High School:
04-1239 Reconstruction 0-004-024 08/10/05 DONE DONE DONE 05/10/05 05/05/05 10/13/04 05/17/05 2 73,195 73,195 JOD 0 0 0
SWBR Architects P.C.
06-0165 Reconstruction 0-004-025 11/13/06 DONE DONE DONE 08/09/06 08/03/06 12/20/05 05/16/06 10 22,544 22,544 HCM 0 0 0
SWBR Architects P.C.
08-0645 Reconstruction 0-004-026 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 3,415,192 0 JOD 0 0 1,062,847
Clark Patterson Associates
08-1034 Reconstruction 0-004-027 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 155,16 255,100 0 JOD 0 0 0
Clark Patterson Associates
08-1749 Reconstruction 0-004-028 07/08/09 DONE DONE DONE 06/29/09 06/22/09 05/14/09 05/20/09 2,13 112,331 84,500 JOD 0 0 0
Clark Patterson Associates
09-0226 Reconstruction 0-004-029 STARTED ADD. REQ'D STARTED 09/16/09 09/15/09 07/09/09 05/19/09 2,4,8,9,155,15,16 0 26,500,821 JOD 0 0 0
Clark Patterson Associates
Odyssey Mid/High (fmly Hoover):
05-1128 Reconstruction 0-005-016 11/10/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 2,10,155,15,16 92,492 92,492 HCM 0 0 0
SWBR Architects P.C.
08-0646 Reconstruction 0-005-017 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 423,197 0 JOD 0 0 75,329
Clark Patterson Associates
09-0227 Reconstruction 0-005-018 STARTED ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 2,8,15 0 0 JOD 0 0 0
Clark Patterson Associates
Longridge School:
08-0647 Reconstruction 0-006-010 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,14,155, 15,538 0 JOD 0 0 2,766
Clark Patterson Associates
08-1035 Reconstruction 0-006-011 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 16 36,650 0 JOD 0 0 0
Clark Patterson Associates
09-0228 Reconstruction 0-006-012 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 7,10,16 0 0 JOD 0 0 0
Clark Patterson Associates
Paddy Hill School:
05-1129 Reconstruction 0-007-012 11/10/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 8,9,10,155,15,16 138,461 138,461 HCM 0 0 0
SWBR Architects P.C.
08-0648 Reconstruction 0-007-013 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 452,476 0 JOD 0 0 80,541
Clark Patterson Associates
West Ridge School:
06-0166 Reconstruction 0-008-011 11/13/06 DONE DONE DONE 08/09/06 08/03/06 12/20/05 05/16/06 10,16 23,209 23,209 HCM 0 0 0
SWBR Architects P.C.
08-0643 Reconstruction 0-008-012 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,14,155, 225,976 0 JOD 0 0 40,224
Clark Patterson Associates
Autumn Lane Elementary:
08-0649 Reconstruction 0-009-012 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 254,933 254,933 JOD 0 0 45,378
Clark Patterson Associates
09-0229 Reconstruction 0-009-013 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 10,16 0 0 JOD 0 0 0
Clark Patterson Associates
English Village Elementary:
08-0650 Reconstruction 0-010-016 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,14,155, 538,130 0 JOD 0 0 95,787
Clark Patterson Associates
09-0230 Reconstruction 0-010-017 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 10,16 0 0 JOD 0 0 0
Clark Patterson Associates
Lake Shore Elementary:
04-1240 Reconstruction 0-011-011 08/10/05 DONE DONE DONE 05/10/05 05/05/05 10/13/04 05/17/05 2 220,390 220,390 JOD 0 0 0
SWBR Architects P.C.
08-0651 Reconstruction 0-011-012 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 541,540 0 JOD 0 0 96,394
Clark Patterson Associates
09-0231 Reconstruction 0-011-013 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 10,16 0 0 JOD 0 0 0
Clark Patterson Associates
Arcadia Middle/High School:
05-1130 Reconstruction 0-012-029 11/10/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 2,7,8,9,10,155,15,16 318,733 318,733 JOD 0 0 0
SWBR Architects P.C.
06-0167 Reconstruction 0-012-030 12/05/06 DONE DONE DONE 08/09/06 08/03/06 08/04/06 05/16/06 10 22,544 22,544 HCM 0 0 0
SWBR Architects P.C.
08-0652 Reconstruction 0-012-031 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/10/06 12/13/07 2,4,7,8,9,10,14,155, 1,082,372 0 JOD 0 0 192,662
Clark Patterson Associates
06-0583 Reconstruction 0-012-032 05/08/07 DONE DONE DONE 12/04/06 12/01/06 09/08/06 05/16/06 16 108,445 108,445 JOD 0 0 0
Hunt Engineers & Architects & Survey
06-1103 Reconstruction 0-012-033 04/10/07 DONE DONE DONE 03/14/07 03/12/07 01/22/07 05/16/06 13 107,595 107,595 JOD 0 0 0
Hunt Engineers & Architects & Survey
07-0795 Reconstruction 0-012-034 11/27/07 DONE DONE DONE 11/13/07 11/09/07 10/02/07 05/15/07 7 2,000,000 2,000,000 JOD 0 0 0
Hunt Engineers & Architects & Survey
09-0232 Reconstruction 0-012-035 STARTED ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 2,4,8,9,155,15,16 0 0 JOD 0 0 0
Clark Patterson Associates
Buckman Heights Elementary:
08-0653 Reconstruction 0-013-009 09/08/09 DONE DONE DONE 11/03/08 08/22/08 08/10/06 12/13/07 2,4,7,8,9,10,155,15, 742,148 0 JOD 0 0 132,102
Clark Patterson Associates
Brookside Elementary:
04-1241 Reconstruction 0-014-010 08/10/05 DONE DONE DONE 05/10/05 05/05/05 10/13/04 05/17/05 2,16 29,891 29,891 JOD 0 0 0
SWBR Architects P.C.
08-0654 Reconstruction 0-014-011 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 425,762 0 JOD 0 0 75,786
Clark Patterson Associates
06-0584 Reconstruction 0-014-012 05/08/07 DONE DONE DONE 12/04/06 12/01/06 / / 05/16/06 2 153,937 153,937 JOD 0 0 0
Hunt Engineers & Architects & Survey
08-1036 Reconstruction 0-014-013 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 155,15,16 275,300 0 JOD 0 0 0
Clark Patterson Associates
09-0233 Reconstruction 0-014-014 STARTED ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 10,16 0 0 JOD 0 0 0
Clark Patterson Associates
Parkland Elementary:
04-1242 Reconstruction 0-015-009 08/10/05 DONE DONE DONE 05/10/05 05/05/05 10/13/04 05/17/05 2,16 6,562 40,640 JOD 0 0 0
SWBR Architects P.C.
08-0655 Reconstruction 0-015-010 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 1,900,445 0 JOD 0 0 338,279
Clark Patterson Associates
08-1037 Reconstruction 0-015-011 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 155,16 227,750 0 JOD 0 0 0
Clark Patterson Associates
09-0234 Reconstruction 0-015-012 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 10,16 0 5,112,342 JOD 0 0 0
Clark Patterson Associates
Holmes Road Elementary:
05-1131 Reconstruction 0-016-006 11/11/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 2,7,10,15 975,718 975,718 HCM 0 0 0
SWBR Architects P.C.
08-0656 Reconstruction 0-016-007 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,14,155, 202,961 0 JOD 0 0 36,127
Clark Patterson Associates
06-0585 Reconstruction 0-016-008 05/08/07 DONE DONE DONE 12/04/06 12/01/06 09/08/06 05/16/06 2,155,15,16 221,934 221,934 JOD 0 0 0
Hunt Engineers & Architects & Survey
08-1038 Reconstruction 0-016-009 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/11/08 05/20/08 155,16 228,950 0 JOD 0 0 0
Clark Patterson Associates
Athena Middle/High School:
05-1132 Reconstruction 0-017-029 11/10/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 2,7,8,9,10,155,15,16 786,748 786,748 HCM 0 0 0
SWBR Architects P.C.
08-0657 Reconstruction 0-017-030 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 1,722,006 0 JOD 0 0 606,517
Clark Patterson Associates
- Reconstruction 0-017-031 / / / / 09/08/06 / / 2 0 46,905,690 JOD 0 0 0
- Reconstruction 0-017-032 / / / / / / / / 155,16 0 0 JOD 0 0 0
09-0235 Reconstruction 0-017-033 DONE ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 9,15 0 0 JOD 0 0 0
Clark Patterson Associates
Kirk Road Elementary:
06-0168 Reconstruction 0-018-014 12/05/06 DONE DONE DONE 08/09/06 08/03/06 12/20/05 05/16/06 10 17,903 17,903 HCM 0 0 0
SWBR Architects P.C.
08-0658 Reconstruction 0-018-015 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 44,588 0 JOD 0 0 7,937
Clark Patterson Associates
Apollo Middle School:
05-1133 Reconstruction 0-031-016 11/10/06 DONE DONE DONE 04/13/06 04/03/06 12/20/05 05/17/05 2,8,10 622,347 622,347 HCM 0 0 0
SWBR Architects P.C.
08-0659 Reconstruction 0-031-017 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 3,220,932 0 JOD 0 0 973,326
Clark Patterson Associates
06-0586 Reconstruction 0-031-018 05/08/07 DONE DONE DONE 12/04/06 12/01/06 09/08/06 05/16/06 4,7,8,9,155,15,16 261,979 261,979 JOD 0 0 0
Hunt Engineers & Architects & Survey
08-1039 Reconstruction 0-031-019 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 9,155,16 538,500 0 JOD 0 0 0
Clark Patterson Associates
09-0236 Reconstruction 0-031-020 STARTED ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 2,8,155,15,16 0 0 JOD 0 0 0
Clark Patterson Associates
Pine Brook Elementary:
06-0169 Reconstruction 0-036-004 12/05/06 DONE DONE DONE 08/09/06 08/03/06 12/20/05 05/16/06 10 17,903 17,903 HCM 0 0 0
SWBR Architects P.C.
08-0660 Reconstruction 0-036-005 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/11/06 12/13/07 2,4,7,8,9,10,155,15, 196,455 0 JOD 0 0 34,969
Clark Patterson Associates
06-0587 Reconstruction 0-036-006 05/08/07 DONE DONE DONE 12/04/06 12/01/06 09/08/06 05/16/06 16 101,417 101,417 JOD 0 0 0
Hunt Engineers & Architects & Survey
Greece Ridge Mall-Continuing Ed.:
- Reconstruction 0-042-003 / / / / 08/11/06 / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0
Dugout/Storage @ Athena High School:
07-0692DB Discovered Building 2-046-001 11/20/07 DONE DONE DONE 11/01/07 10/29/07 04/25/01 / / 0 0 MGL 0 0 0
Hunt Engineers & Architects & Survey
Dugout/Storage @ Arcadia High School:
07-0693DB Discovered Building 2-047-001 11/20/07 DONE DONE DONE 11/01/07 10/29/07 04/25/01 / / 0 0 MGL 0 0 0
Hunt Engineers & Architects & Survey
Dugout/Storage @ Olympia High School:
07-0711DB Discovered Building 2-048-001 11/20/07 DONE DONE DONE 11/05/07 10/29/07 04/25/01 / / 0 0 MGL 0 0 0
Hunt Engineers & Architects & Survey
Longridge Storage Building:
04-1235 New Construction 2-050-001 09/20/05 DONE DONE DONE 05/10/05 05/05/05 02/23/04 / / 02 - 16 90,791 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 2-050-002 / / / / / / / / 2,4,7,8,9,10,14,155, 0 0 JOD 0 0 0
Storage Trlr @ Athena Highschool:
07-0712DB Discovered Building 2-054-001 11/20/07 DONE DONE DONE 11/05/07 10/29/07 12/15/06 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailer @ Olympic Highschool:
07-0713DB Discovered Building 2-055-001 11/20/07 DONE DONE DONE 11/05/07 10/29/07 12/18/06 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailer #1 @ Arcadia HS:
07-0714DB Discovered Building 2-056-001 11/20/07 DONE DONE DONE 11/05/07 10/29/07 12/18/06 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Gas Equipment Storage @ Longridge ES:
07-0715DB Discovered Building 2-057-001 11/20/07 DONE DONE DONE 11/05/07 10/29/07 / / / / 02 - 16 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailier #2 @ Arcadia High:
08-0953DB Discovered Building 2-058-001 01/06/09 DONE DONE DONE 12/19/08 12/16/08 11/18/08 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailer #3 @ Arcadia High:
08-0954DB Discovered Building 2-059-001 01/06/09 DONE DONE DONE 12/19/08 12/16/08 11/18/08 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailer @ Apollo MS:
08-0955DB Discovered Building 2-060-001 01/06/09 DONE DONE DONE 12/19/08 12/16/08 11/18/08 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Storage Trailer @ Transportation Bld:
08-0956DB Discovered Building 2-061-001 01/06/09 DONE DONE DONE 12/19/08 12/16/08 11/18/08 / / 0 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Maintenance Garage:
- Reconstruction 3-002-002 / / / / 04/20/07 / / 2,8,155,15,16 0 0 JOD 0 0 0
Transportation Annex:
08-0661 Reconstruction 5-023-010 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/14/06 12/13/07 2,4,7,8,9,10,155,15, 749,358 0 JOD 0 0 0
Clark Patterson Associates
08-0774 Reconstruction 5-023-011 02/02/09 DONE DONE DONE 11/20/08 11/19/08 08/01/08 05/20/08 2,155 200,000 200,000 JOD 0 0 0
Clark Patterson Associates
Bldg Grounds/Bus Storage:
- Reconstruction 5-024-008 / / / / 12/20/05 / / 8,9,155,15,16 0 0 JOD 0 0 0
08-0662 Reconstruction 5-024-009 09/08/09 DONE DONE DONE 11/03/08 10/22/08 08/14/06 12/13/07 2,4,7,8,9,10,155,15, 1,036,976 0 JOD 0 0 0
Clark Patterson Associates
08-1040 Reconstruction 5-024-010 07/23/09 DONE DONE DONE 01/06/09 01/02/09 08/01/08 05/20/08 13 59,830 0 JOD 0 0 0
Clark Patterson Associates
08-1429 Reconstruction 5-024-011 05/28/09 DONE DONE DONE 03/26/09 03/24/09 12/02/08 06/10/08 14 42,074 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Apollo Concession/Storage:
04-1236 Reconstruction 7-035-002 09/20/05 DONE DONE DONE 05/10/05 05/05/05 10/13/04 / / 8,10,155,15,16 13,259 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 7-035-003 / / / / 08/14/06 / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0
Toilet Rm. Bldg. @ Apollo MS:
04-1237 New Construction 7-051-001 09/20/05 DONE DONE DONE 05/10/05 05/05/05 10/08/04 / / 02 - 16 241,040 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 7-051-002 / / / / 08/14/06 / / 2,4,7,8,9,10,14,155, 0 0 JOD 0 0 0
Pressbox/Storage @ Athena Middle/HS:
04-1238 Reconstruction 7-053-001 09/20/05 DONE DONE DONE 05/10/05 05/05/05 10/21/04 / / 60,460 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 7-053-002 / / / / 08/14/06 / / 2,4,7,8,9,10,155,15, 0 0 JOD 0 0 0
Districtwide:
08-1735 Reconstruction 7-999-003 10/23/09 DONE DONE DONE 06/24/09 06/15/09 08/22/08 12/18/07 10,16 979,305 0 JOD 0 0 174,319
Clark Patterson Associates
09-0237 Reconstruction 7-999-004 UNREVIEWED
ADD. REQ'D STARTED 09/16/09 09/15/09 07/08/09 05/19/09 16 0 0 JOD 0 0 0
Clark Patterson Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Helendale Rd Primary School:
05-0632 Reconstruction 0-001-011 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 2,4,7,8,9,10,155,15, 0 5,965,628 RDR 0 0 0
Clark Patterson Associates
06-1503 Reconstruction 0-001-012 10/02/07 DONE DONE DONE 05/16/07 05/16/07 12/04/06 02/28/07 2,4,7,8,9,10,13,14,1 221,208 221,208 MGL 0 0 46,675
Clark Patterson Associates
08-1043PR Additions and Alterations 0-001-013 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 7,756,404 DDJ 0 0 0
Clark Patterson Associates
09-0280 Additions and Alterations 0-001-013 STARTED STARTED UNREVIEWED10/02/09 10/02/09 11/15/07 12/09/08 02 - 16 0 7,756,404 DDJ 0 0 0
Clark Patterson Associates
Eastridge Sr High:
05-0633 Reconstruction 0-002-016 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 2,4,7,8,9,155,15,16 948,731 948,731 RDR 0 0 0
Clark Patterson Associates
06-1504 Reconstruction 0-002-017 10/02/07 DONE DONE DONE 05/16/07 05/16/07 12/04/06 02/28/07 2,4,7,8,9,10,13,14,1 2,246,501 2,246,501 MGL 0 0 474,012
Clark Patterson Associates
08-1044PR Additions and Alterations 0-002-018 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 29,382,498 DDJ 0 0 0
Clark Patterson Associates
08-1082SR Additions and Alterations 0-002-018 05/07/09 DONE DONE DONE 01/20/09 01/09/09 11/15/07 12/09/08 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
09-0281 Additions and Alterations 0-002-018 STARTED STARTED UNREVIEWED10/02/09 10/02/09 11/15/07 12/09/08 02 - 16 0 29,442,330 DDJ 0 0 0
Clark Patterson Associates
Ivan L. Green School:
05-0634 Reconstruction 0-004-013 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 2,4,7,9,155,15,16 767,969 1,208,059 RDR 0 0 0
Clark Patterson Associates
06-1505 Reconstruction 0-004-014 10/02/07 DONE DONE DONE 05/16/07 05/16/07 12/04/06 02/28/07 2,4,7,8,9,10,13,14,1 610,326 610,326 MGL 0 0 128,779
Clark Patterson Associates
08-1045PR Additions and Alterations 0-004-015 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1535 Additions and Alterations 0-004-015 10/23/09 DONE DONE DONE 04/24/09 04/20/09 11/15/07 12/09/08 02 - 16 2,956,421 0 DDJ 0 0 0
Clark Patterson Associates
Laurelton Pardee School:
05-0635 Reconstruction 0-005-014 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 2,4,7,8,9,155,15,16 1,786,284 1,786,284 RDR 0 0 0
Clark Patterson Associates
06-1506 Reconstruction 0-005-015 10/02/07 DONE DONE DONE 05/16/07 05/16/07 12/04/06 02/28/07 2,4,7,8,9,10,13,14,1 1,336,647 1,336,647 MGL 0 0 282,032
Clark Patterson Associates
08-1046PR Reconstruction 0-005-016 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 2,4,7,8,9,155,15,16 2,594,650 2,551,647 DDJ 0 0 0
Clark Patterson Associates
09-0282 Reconstruction 0-005-016 STARTED STARTED UNREVIEWED10/02/09 10/02/09 11/15/07 12/09/08 2,4,7,8,9,155,15,16 2,594,650 2,551,647 DDJ 0 0 0
Clark Patterson Associates
Durand Eastman:
04-1090PR Additions and Alterations 0-007-013 09/26/05 DONE DONE DONE 04/06/05 04/04/05 10/12/04 / / 02 - 16 0 0 MGL 0 0 0
Clark Patterson Associates
05-0636 Additions and Alterations 0-007-013 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 02 - 16 8,715,279 8,150,672 RDR 0 0 0
Clark Patterson Associates
06-1507 Reconstruction 0-007-015 10/02/07 DONE DONE DONE 05/16/07 05/16/07 12/04/06 02/28/07 2,4,7,8,9,10,13,14,1 675,318 675,318 MGL 0 0 142,492
Clark Patterson Associates
08-1047PR Additions and Alterations 0-007-016 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 8,860,512 DDJ 0 0 0
Clark Patterson Associates
08-1536 Additions and Alterations 0-007-016 10/23/09 DONE DONE DONE 04/24/09 04/20/09 11/15/07 12/09/08 02 - 16 2,159,961 0 DDJ 0 0 0
Clark Patterson Associates
New Middle School:
05-0637 Reconstruction 0-013-003 03/27/06 DONE DONE DONE 01/19/06 01/19/06 10/12/04 03/22/05 2,8,9,10,13,16 44,625 44,625 RDR 0 0 0
Clark Patterson Associates
- Reconstruction 0-013-004 / / / / 12/04/06 / / 2,4,7,8,9,10,13,14,1 0 25,183,608 MGL 0 0 0
08-1048PR Additions and Alterations 0-013-005 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1083SR Additions and Alterations 0-013-005 05/07/09 DONE DONE DONE 01/20/09 01/09/09 11/15/07 12/09/08 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1537 Additions and Alterations 0-013-005 10/23/09 DONE DONE DONE 04/24/09 04/20/09 11/15/07 12/09/08 02 - 16 1,130,416 0 DDJ 0 0 0
Clark Patterson Associates
Ath. Storage (demolished '09):
- XX Reconstruction 2-014-004 CANCELLED / / / / 11/15/07 / / 2,4,7,8,9,155,15,16 0 0 MGL 0 0 0
Maintenance Bldg:
- Reconstruction 3-009-006 / / / / 11/15/07 / / 2,4,7,8,9,155,15,16 0 0 MGL 0 0 0
Bus Garage:
- Reconstruction 5-003-005 / / / / 11/15/07 / / 2,4,7,8,9,155,15,16 0 0 MGL 0 0 0
Transporation Building:
08-1049PR New Construction 5-016-001 UNREVIEWED 01/06/09 12/30/08 11/15/07 / / 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1084SR New Construction 5-016-001 05/07/09 DONE DONE DONE 01/20/09 01/09/09 11/15/07 12/09/08 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1538 New Construction 5-016-001 10/23/09 DONE DONE DONE 04/24/09 04/20/09 11/15/07 12/09/08 02 - 16 16,651,745 0 DDJ 0 0 0
Clark Patterson Associates
Storage/Restrooms:
08-1050PR New Construction 7-017-001 UNREVIEWED 01/06/09 12/30/08 05/27/08 / / 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
09-0283 New Construction 7-017-001 STARTED STARTED UNREVIEWED10/02/09 10/02/09 05/27/08 12/09/08 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
Pressbox:
08-1051PR New Construction 7-018-001 UNREVIEWED 01/06/09 12/30/08 05/27/08 12/09/08 02 - 16 0 0 DDJ 0 0 0
Clark Patterson Associates
08-1085 New Construction 7-018-001 10/23/09 DONE DONE DONE 01/20/09 01/09/09 05/27/08 12/09/08 02 - 16 113,027 0 DDJ 0 0 0
Clark Patterson Associates
District Wide:
- Reconstruction 7-999-003 / / / / 01/17/08 / / 16 0 0 MGL 0 0 0
Bishop Kearney High School:
05-1413TQ Temporary Quarters 8-015-L01 08/07/06 DONE DONE DONE 06/22/06 06/19/06 02/17/05 / / 85,400 85,400 RDR 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Irondequoit High School:
04-1156 Reconstruction 0-001-020 06/02/05 DONE DONE DONE 04/13/05 04/11/05 03/14/05 05/17/05 8 364,022 364,022 RDR 0 0 0
Clark Patterson Associates
05-0427 Reconstruction 0-001-021 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 78,566 78,566 RDR 0 0 0
Clark Patterson Associates
06-0297 Reconstruction 0-001-022 01/24/07 DONE DONE DONE 10/04/06 10/04/06 06/05/06 05/16/06 9,16 249,035 249,035 MGL 0 0 0
Clark Patterson Associates
07-0528 Additions and Alterations 0-001-023 03/19/08 DONE DONE DONE 10/11/07 10/09/07 06/20/06 05/15/07 02 - 16 5,849,990 4,656,210 MGL 0 0 0
Clark Patterson Associates
07-0529 Reconstruction 0-001-024 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,8,155,15,16 418,852 418,852 MGL 0 0 52,357
Clark Patterson Associates
07-0512 Reconstruction 0-001-025 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 8,9,13,16 80,700 80,700 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-001-026 / / / / 09/16/09 / / 155,16 0 0 DDJ 0 0 0
06-0065SC Visual Structural Inspection 0-001-SC5 08/07/06 DONE DONE DONE 06/12/06 06/12/06 / / / / 16 12,663 12,663 JOD 0 0 0
Ruben Dake JH School 7-8:
04-1155 Reconstruction 0-002-008 06/02/05 DONE DONE DONE 04/13/05 04/11/05 03/14/05 05/17/05 8 234,222 234,222 RDR 0 0 0
Clark Patterson Associates
05-0428 Reconstruction 0-002-009 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 9,16 28,571 28,571 RDR 0 0 0
Clark Patterson Associates
06-0298 Reconstruction 0-002-010 01/24/07 DONE DONE DONE 10/04/06 10/04/06 06/05/06 05/16/06 9,10,16 129,292 129,292 MGL 0 0 0
Clark Patterson Associates
07-0530 Reconstruction 0-002-011 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,8,9,155,15,16 331,832 331,832 MGL 0 0 48,779
Clark Patterson Associates
07-0513 Reconstruction 0-002-012 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 7,9,13,16 103,000 103,000 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-002-013 / / / / 03/04/09 / / 2,8,9,155,15,16 0 0 DDJ 0 0 0
- XX Reconstruction 0-002-014 CANCELLED / / / / 05/29/09 / / 155,15 0 12,575,108 DDJ 0 0 0
04-0580SC Visual Structural Inspection 0-002-SC2 12/01/04 DONE DONE DONE 10/28/04 10/28/04 / / / / 16 1,392 1,392 JOD 0 0 0
05-0130SC Visual Structural Inspection 0-002-SC3 08/17/05 DONE DONE DONE 08/02/05 08/02/05 / / / / 16 7,992 7,992 JOD 0 0 0
06-0066SC Visual Structural Inspection 0-002-SC5 08/07/06 DONE DONE DONE 06/12/06 06/12/06 / / / / 16 2,412 2,412 JOD 0 0 0
Rogers/Southlawn School:
05-0429 Reconstruction 0-003-010 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 2,259 0 RDR 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 0-003-011 / / / / 11/15/06 / / 02 - 16 0 0 MGL 0 0 0
06-0787 Additions and Alterations 0-003-011 01/24/07 DONE DONE DONE 01/18/07 01/18/07 11/15/06 05/16/06 02 - 16 14,431 14,431 MGL 0 0 0
Clark Patterson Associates
07-0531 Reconstruction 0-003-012 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,7,8,155,15,16 947,484 947,484 MGL 0 0 139,280
Clark Patterson Associates
07-0514 Reconstruction 0-003-013 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 9 21,750 21,750 MGL 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 0-003-014 / / / / 03/04/09 / / 02 - 16 0 0 DDJ 0 0 0
Iroquois/Colebrook School:
05-0430 Reconstruction 0-004-008 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 10,16 72,903 72,903 RDR 0 0 0
Clark Patterson Associates
06-0788 Reconstruction 0-004-009 01/24/07 DONE DONE DONE 01/18/07 01/18/07 07/26/06 05/16/06 2,8,9 12,569 12,569 MGL 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 0-004-010 / / / / 11/15/06 / / 02 - 16 0 0 MGL 0 0 0
07-0532 Reconstruction 0-004-011 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 7,8,9,13,155,16 851,434 851,434 MGL 0 0 125,161
Clark Patterson Associates
07-0515 Reconstruction 0-004-012 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 2,9 80,800 0 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-004-013 / / / / 03/04/09 / / 2,9,155,16 0 0 DDJ 0 0 0
- Reconstruction 0-004-014 / / / / 05/29/09 / / 155,15 0 0 DDJ 0 0 0
Seneca Elem School K-3:
05-0431 Reconstruction 0-006-005 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 9,10,16 16,486 16,486 RDR 0 0 0
Clark Patterson Associates
07-0533 Reconstruction 0-006-006 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,8,155,16 315,911 315,911 MGL 0 0 46,439
Clark Patterson Associates
- Reconstruction 0-006-007 / / / / 03/04/09 / / 155,16 0 0 DDJ 0 0 0
Listwood Elem Sch K-3:
03-1307XX Reconstruction 0-008-004 04/21/04 CANCELLED 03/23/04 03/22/04 01/26/04 12/07/99 2 120,000 0 HCM 0 0 0
Clark Patterson Associates
Brookview E.S.(11/2003 demolished):
- XX Reconstruction 0-011-004 CANCELLED / / / / 03/04/09 / / 8,9,155,16 0 2,559,231 DDJ 0 0 0
Gym Building:
07-0534 Reconstruction 0-021-003 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 13,155,16 125,000 125,000 MGL 0 0 22,000
Clark Patterson Associates
07-0516 Reconstruction 0-021-004 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 2 43,800 43,800 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-021-005 / / / / 03/04/09 / / 2,8,9,16 0 0 DDJ 0 0 0
Pinegrove Site #2/WOW Building:
00-1772DB Discovered Building 0-024-001 08/27/09 DONE DONE DONE 05/10/01 / / 09/22/98 / / 0 0 BJB 0 0 0
New Listwood School:
05-0432 Reconstruction 0-027-002 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 1,086 0 RDR 0 0 0
Clark Patterson Associates
07-0535 Additions and Alterations 0-027-003 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 02 - 16 4,000 0 MGL 0 0 0
Clark Patterson Associates
07-0517 Reconstruction 0-027-004 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 13 20,200 20,200 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-027-005 / / / / 03/04/09 / / 8,9,155,16 0 0 DDJ 0 0 0
New Brookview Elementary:
05-0433 Reconstruction 0-028-002 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 1,086 0 RDR 0 0 0
Clark Patterson Associates
07-0536 Reconstruction 0-028-003 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,13,16 5,000 0 MGL 0 0 0
Clark Patterson Associates
07-0518 Reconstruction 0-028-004 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 2,9,16 67,200 67,200 MGL 0 0 0
Clark Patterson Associates
- Reconstruction 0-028-005 / / / / 03/04/09 / / 2,8,9,155,16 0 0 DDJ 0 0 0
New Briarwood Elementary:
05-0434 Reconstruction 0-029-002 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 1,086 0 RDR 0 0 0
Clark Patterson Associates
07-0537 Reconstruction 0-029-003 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 16 4,500 0 MGL 0 0 0
Clark Patterson Associates
07-0519 Reconstruction 0-029-004 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 2,9,13 20,200 20,200 MGL 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 0-029-005 / / / / 03/04/09 / / 02 - 16 0 0 DDJ 0 0 0
Colebrook:
05-0435 Reconstruction 0-032-002 03/31/06 DONE DONE DONE 12/08/05 12/07/05 04/19/05 05/17/05 16 1,086 0 RDR 0 0 0
Clark Patterson Associates
07-0538 Reconstruction 0-032-003 03/19/08 DONE DONE DONE 10/11/07 10/09/07 03/06/07 05/15/07 2,16 5,500 0 MGL 0 0 0
Clark Patterson Associates
07-0520 Reconstruction 0-032-004 03/12/08 DONE DONE DONE 10/09/07 10/05/07 03/26/07 05/15/07 2,13,16 36,350 36,350 MGL 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 0-032-005 / / / / 03/04/09 / / 02 - 16 0 0 DDJ 0 0 0
New Administration Building:
- PR Additions and Alterations 1-033-002 / / / / 11/15/06 / / 02 - 16 0 0 MGL 0 0 0
06-0789 Additions and Alterations 1-033-002 01/24/07 DONE DONE DONE 01/18/07 01/18/07 11/15/06 05/16/06 02 - 16 8,700 0 MGL 0 0 0
Clark Patterson Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Manor Elementary:
07-0842 Reconstruction 0-001-009 05/13/08 DONE DONE DONE 11/19/07 11/16/07 01/19/07 05/15/07 4,7,8,9,155,15,16 1,438,707 1,159,300 MGL 0 0 71,935
Design Group Educ. Fac. Dept.
- Reconstruction 0-001-010 / / / / 08/26/09 / / 2,4,7,8,9,155,15,16 0 0 HCM 0 0 0
Middle School-Joined to H.S.-003 '89:
- XX Reconstruction 0-002-008 CANCELLED / / / / 01/19/07 / / 4,7,8,9,155,15,16 0 6,037,349 MGL 0 0 0
- XX Reconstruction 0-002-009 CANCELLED 04/09/07 04/06/07 02/23/07 / / 7 0 6,037,349 MGL 0 0 0
SEI Design Group
High School:
07-0843 Reconstruction 0-003-010 05/13/08 DONE DONE DONE 11/19/07 11/16/07 01/19/07 05/15/07 2,4,7,8,9,155,15,16 4,241,011 4,795,345 MGL 0 0 212,051
Design Group Educ. Fac. Dept.
07-0672 Reconstruction 0-003-011 11/28/07 DONE DONE DONE 10/30/07 10/29/07 10/11/07 05/15/07 2 108,500 108,500 MGL 0 0 0
SEI Design Group
- Reconstruction 0-003-012 / / / / 08/26/09 / / 2,7,155,15,16 0 0 HCM 0 0 0
06-0528SC Visual Structural Inspection 0-003-SC1 11/21/06 DONE DONE DONE 11/14/06 11/14/06 / / / / 16 9,498 9,498 JOD 0 0 0
Lima Elementary:
07-0844 Reconstruction 0-004-008 05/13/08 DONE DONE DONE 11/19/07 11/16/07 01/19/07 05/15/07 2,4,7,8,9,155,15,16 2,018,516 2,147,400 MGL 0 0 100,926
Design Group Educ. Fac. Dept.
07-0673 Reconstruction 0-004-009 11/28/07 DONE DONE DONE 10/30/07 10/29/07 10/11/07 05/15/07 2 117,672 233,900 MGL 0 0 0
SEI Design Group
- Reconstruction 0-004-010 / / / / 08/26/09 / / 2,4,7,8,9,10,14,155, 0 0 HCM 0 0 0
New Middle School:
06-1290 Reconstruction 0-013-004 05/16/07 DONE DONE DONE 04/09/07 04/06/07 04/10/07 05/15/07 7 1,424,805 1,441,400 MGL 0 0 71,240
SEI Design Group
07-0845 Reconstruction 0-013-005 05/13/08 DONE DONE DONE 11/19/07 11/16/07 04/10/07 05/15/07 2,7,155,16 1,525,145 1,668,800 MGL 0 0 76,257
Design Group Educ. Fac. Dept.
- PR Additions and Alterations 0-013-006 / / / / 08/26/09 / / 02 - 16 0 0 HCM 0 0 0
- Reconstruction 0-013-007 / / / / 08/26/09 / / 2,7,9,10,155,15,16 0 0 HCM 0 0 0
Storage garage:
07-0846 Reconstruction 2-006-003 05/13/08 DONE DONE DONE 11/19/07 11/16/07 01/19/07 05/15/07 7,155,16 74,325 0 MGL 0 0 0
Design Group Educ. Fac. Dept.
- Reconstruction 2-006-004 / / / / 08/26/09 / / 2,7,155,15,16 0 0 HCM 0 0 0
Support Service Bus Garage:
07-0847 Reconstruction 5-011-005 05/13/08 DONE DONE DONE 11/19/07 11/16/07 01/19/07 05/15/07 7,155,16 128,855 0 MGL 0 0 0
Design Group Educ. Fac. Dept.
Toilet/Storage Building:
- New Construction 7-016-001 / / / / 09/01/09 / / 02 - 16 0 0 JOD 0 0 0
District Wide:
08-0261 Reconstruction 7-999-002 01/05/09 DONE DONE DONE 09/08/08 09/02/08 03/07/08 05/15/07 10,13,16 1,265,000 0 MGL 0 0 63,250
SEI Design Group
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Admin/BOCES Bldg:
07-0615 Reconstruction 0-001-005 04/07/08 DONE DONE DONE 10/23/07 10/22/07 / / 03/27/07 7 1,002,440 1,002,440 MGL 0 0 142,347
Thomas Associates
Leo Bernabi Elem (fmly IS):
06-0539 Reconstruction 0-002-007 04/20/07 DONE DONE DONE 11/21/06 11/15/06 12/18/00 05/16/06 2,7,9 354,736 890,000 MGL 0 0 0
Thomas Associates
06-0346 Reconstruction 0-002-008 02/02/07 DONE DONE DONE 10/23/06 10/20/06 02/17/06 05/16/06 4,7,8,9,10,155,16 1,407,742 1,048,600 MGL 0 0 0
Thomas Associates
07-0608 Reconstruction 0-002-009 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 2,8,9,10,155,15,16 1,697,572 1,697,572 MGL 0 0 241,055
Thomas Associates
04-0606FP Reconstruction 0-002-FP1 01/13/05 DONE DONE DONE 01/03/05 / / / / / / 16 3,700 3,700 JOD 0 0 0
Cosgrove MS 7-8(fmly Wilson HS):
06-0540 Additions and Alterations 0-005-010 04/20/07 DONE DONE DONE 11/21/06 11/15/06 08/12/02 05/16/06 02 - 16 34,858 218,000 MGL 0 0 0
Thomas Associates
06-0347 Reconstruction 0-005-011 02/02/07 DONE DONE DONE 10/23/06 10/20/06 02/17/06 05/16/06 2,4,10,155,15,16 1,439,357 1,498,000 MGL 0 0 0
Thomas Associates
07-0609 Reconstruction 0-005-012 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 2,155 3,440,778 3,440,778 MGL 0 0 0
Thomas Associates
07-0610 Reconstruction 0-005-013 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 2,9,10,155,16 187,464 187,464 MGL 0 0 26,620
Thomas Associates
- Reconstruction 0-005-014 / / / / 11/10/09 / / 2,8,9,10,155,15,16 0 0 DDJ 0 0 0
04-0605FP Reconstruction 0-005-FP1 01/13/05 DONE DONE DONE 01/03/05 / / / / / / 16 7,400 7,400 JOD 0 0 0
08-0447SC Visual Structural Inspection 0-005-SC1 10/02/08 DONE DONE DONE 06/18/08 06/18/08 / / / / 16 5,374 0 JOD 0 0 0
09-0019SC Visual Structural Inspection 0-005-SC2 07/20/09 DONE DONE DONE 06/24/09 06/24/09 / / / / 16 5,263 0 JOD 0 0 0
Wm Munn Elementary:
06-0541 Reconstruction 0-006-007 04/20/07 DONE DONE DONE 11/21/06 11/15/06 12/18/00 05/16/06 2,7,9 376,469 574,000 MAC 0 0 0
Thomas Associates
06-0348 Reconstruction 0-006-008 02/02/07 DONE DONE DONE 10/23/06 10/20/06 02/17/06 05/16/06 2,7,8,9,155,16 1,141,602 898,800 MGL 0 0 0
Thomas Associates
06-0433 Reconstruction 0-006-009 11/07/06 DONE DONE DONE 11/06/06 11/03/06 09/12/06 05/16/06 16 374,000 374,000 MGL 0 0 0
Thomas Associates
07-0611 Reconstruction 0-006-010 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 2,8,9,155,16 425,695 425,695 MGL 0 0 60,449
Thomas Associates
04-0603FP Reconstruction 0-006-FP1 01/13/05 DONE DONE DONE 01/03/05 / / / / / / 16 3,700 3,700 JOD 0 0 0
Terry A. Taylor ES (fmly Town Line):
06-0542 Reconstruction 0-007-007 04/20/07 DONE DONE DONE 11/21/06 11/15/06 12/19/00 05/16/06 2,7,9 61,445 72,000 MAC 0 0 0
Thomas Associates
06-0349 Reconstruction 0-007-008 02/02/07 DONE DONE DONE 10/23/06 10/20/06 02/17/06 05/16/06 7,9,155,16 1,289,544 869,000 MGL 0 0 0
Thomas Associates
07-0612 Reconstruction 0-007-009 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 9,10 217,970 217,970 MGL 0 0 30,952
Thomas Associates
04-0604FP Reconstruction 0-007-FP1 01/13/05 DONE DONE DONE 01/03/05 / / / / / / 16 11,100 11,100 JOD 0 0 0
S'port HS 9-12(fmly CosgroveJHS):
06-0513 Reconstruction 0-008-009 04/20/07 DONE DONE DONE 11/16/06 11/15/06 02/17/06 05/16/06 2,4,7,8,9,10,13,155, 8,347,471 6,999,000 MGL 0 0 0
Thomas Associates
07-0613 Reconstruction 0-008-010 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 2,4,7,9,10,155,15,16 4,972,461 4,972,461 MGL 0 0 706,089
Thomas Associates
- Reconstruction 0-008-011 / / / / 11/10/09 / / 2,8,9,10,155,15,16 0 0 DDJ 0 0 0
04-0607FP Reconstruction 0-008-FP1 01/13/05 DONE DONE DONE 01/03/05 / / / / / / 16 3,700 3,700 JOD 0 0 0
08-0448SC Visual Structural Inspection 0-008-SC1 10/03/08 DONE DONE DONE 06/19/08 06/19/08 / / / / 16 15,840 0 JOD 0 0 0
09-0018SC Visual Structural Inspection 0-008-SC2 07/20/09 DONE DONE DONE 06/24/09 06/24/09 / / / / 16 12,026 0 JOD 0 0 0
CANAL VEIW ELEMENTARY (FRM. NEW ELM):
- Reconstruction 0-015-002 / / / / 02/17/06 / / 9 0 10,222,713 MGL 0 0 0
07-0614 Reconstruction 0-015-003 04/07/08 DONE DONE DONE 10/23/07 10/22/07 02/13/07 03/27/07 9,155 82,771 82,771 MGL 0 0 11,753
Thomas Associates
Administration Bldg:
06-0514 Reconstruction 1-001-004 04/20/07 DONE DONE DONE 11/16/06 11/15/06 02/17/06 05/16/06 15,16 172,220 0 MGL 0 0 0
Thomas Associates
- XX Reconstruction 1-001-005 CANCELLED 10/23/07 10/22/07 02/13/07 03/27/07 7 0 0 MGL 0 0 0
Thomas Associates
Athletic Storage:
07-1907 Reconstruction 2-010-001 04/07/08 DONE DONE DONE 04/03/08 04/02/08 03/27/08 03/27/07 16 5,993 0 DDJ 0 0 0
Thomas Associates
Football Storage:
04-0399 New Construction 2-019-001 04/29/05 DONE DONE DONE 11/16/04 11/12/04 05/11/04 / / 02 - 16 24,000 0 RDR 0 0 0
Thomas Associates
Track Storage:
04-0400 New Construction 2-020-001 04/29/05 DONE DONE DONE 11/16/04 11/12/04 05/11/04 / / 02 - 16 12,800 0 RDR 0 0 0
Thomas Associates
New Bus Facility:
06-0515 Reconstruction 5-014-003 04/20/07 DONE DONE DONE 11/16/06 11/15/06 02/17/06 05/16/06 2,16 149,825 80,000 MGL 0 0 0
Thomas Associates
Concession/Ticket:
04-0401 New Construction 7-017-001 04/29/05 DONE DONE DONE 11/16/04 11/12/04 05/11/04 / / 02 - 16 28,000 0 RDR 0 0 0
Thomas Associates
Soccer Toilets:
04-0402 New Construction 7-018-001 04/29/05 DONE DONE DONE 11/16/04 11/12/04 05/11/04 / / 02 - 16 11,200 0 RDR 0 0 0
Thomas Associates
07-1908 Reconstruction 7-018-002 04/07/08 DONE DONE DONE 04/03/08 04/02/08 03/27/08 03/27/07 2,10,155,15,16 30,968 0 DDJ 0 0 0
Thomas Associates
Press Box w/ Bleachers:
07-1909 New Construction 7-021-001 04/07/08 DONE DONE DONE 04/03/08 03/19/08 02/28/08 03/27/07 02 - 16 99,205 0 DDJ 0 0 0
Thomas Associates
Soccer Field Storage Building:
07-1910 New Construction 7-022-001 04/07/08 DONE DONE DONE 04/03/08 03/19/08 02/28/08 03/27/07 02 - 16 28,218 0 DDJ 0 0 0
Thomas Associates
Soccer Field Toilets:
07-1911 New Construction 7-023-001 04/02/08 DONE DONE DONE 04/03/08 03/19/08 03/05/08 03/27/07 02 - 16 250,465 0 DDJ 0 0 0
Thomas Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
West Avenue Elementary:
06-0088 Reconstruction 0-001-009 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,8,9,155,15,16 74,240 74,240 MGL 0 0 0
Thomas Associates
07-0066 Reconstruction 0-001-010 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 2,4,7,8,9,155,15,16 640,127 640,127 MGL 0 0 81,296
Thomas Associates
08-1753 Reconstruction 0-001-011 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 2,4,8,9 281,976 0 DDJ 0 0 37,511
Tetra Tech Architects & Engineers
Northwood Elementary School:
06-0089 Reconstruction 0-003-010 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,8,9,16 49,063 49,063 MGL 0 0 0
Thomas Associates
07-0067 Reconstruction 0-003-011 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 2,4,7,8,9,155,15,16 4,913,931 4,913,931 MGL 0 0 624,069
Thomas Associates
08-1754 Reconstruction 0-003-012 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 2,4,8,9,10,155,15 443,604 443,604 DDJ 0 0 59,011
Tetra Tech Architects & Engineers
Village Elementary:
06-0090 Reconstruction 0-004-008 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,8,15,16 46,371 46,371 MGL 0 0 0
Thomas Associates
07-0068 Reconstruction 0-004-009 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 2,4,7,8,9,155,15,16 1,423,677 1,423,677 MGL 0 0 180,807
Thomas Associates
08-1755 Reconstruction 0-004-010 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 2,4,8,9,10,155,15,16 296,002 0 DDJ 0 0 39,376
Tetra Tech Architects & Engineers
Merton Williams Middle School:
06-0091 Reconstruction 0-005-009 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,4,8,10,15,16 96,192 96,192 MGL 0 0 0
Thomas Associates
07-0069 Reconstruction 0-005-010 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 2,4,7,8,9,155,15,16 266,529 266,529 MGL 0 0 33,849
Thomas Associates
08-1756 Reconstruction 0-005-011 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 4,8,9,155,16 495,670 0 DDJ 0 0 65,938
Tetra Tech Architects & Engineers
High School:
06-0092 Reconstruction 0-007-010 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,4,8,10,155,15,16 247,810 247,810 MGL 0 0 0
Thomas Associates
07-0070 Reconstruction 0-007-011 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 2,4,7,8,9,155,15,16 2,120,275 2,120,275 MGL 0 0 269,275
Thomas Associates
08-1757 Reconstruction 0-007-012 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 2,8,9,10,155,16 375,682 0 DDJ 0 0 49,976
Tetra Tech Architects & Engineers
Transportation Maint. Facility:
06-0093 Reconstruction 5-010-010 04/16/07 DONE DONE DONE 07/20/06 07/19/06 11/23/05 12/04/01 2,8,16 40,439 40,439 MGL 0 0 0
Thomas Associates
07-0071 Reconstruction 5-010-011 11/19/07 DONE DONE DONE 07/16/07 07/16/07 12/05/06 01/30/07 4,7,8,16 135,461 135,461 MGL 0 0 0
Thomas Associates
08-1758 Reconstruction 5-010-012 10/07/09 DONE DONE DONE 06/29/09 06/24/09 10/22/08 01/13/09 155 64,423 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
Concession Stand/Press Box:
08-1759 Reconstruction 7-012-002 10/07/09 DONE DONE DONE 06/29/09 06/24/09 06/01/09 01/13/09 155 27,642 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
District Wide:
- Reconstruction 7-999-003 / / / / 12/05/06 / / 13,16 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Indian Landing Elementary:
04-0677 Reconstruction 0-002-007 03/22/05 DONE DONE DONE 01/13/05 01/12/05 12/18/03 05/18/04 10 11,772 11,772 RDR 0 0 0
Thomas Associates
09-0325 Reconstruction 0-002-008 STARTED STARTED UNREVIEWED10/21/09 10/19/09 08/25/05 05/15/07 2,4,7,8,9 0 8,158,115 DDJ 0 0 0
Tetra Tech Architects & Engineers
- XX Reconstruction 0-002-009 CANCELLED / / / / 03/21/06 / / 13,16 0 7,744,261 MGL 0 0 0
Penfield Senior High:
04-1421 Reconstruction 0-005-011 07/15/05 DONE DONE DONE 06/17/05 06/14/05 03/24/05 05/17/04 2 90,727 90,727 RDR 0 0 0
Thomas Associates
07-0358PR Additions and Alterations 0-005-012 11/05/07 DONE DONE DONE 09/13/07 / / 08/25/05 / / 02 - 16 0 0 MGL 0 0 0
Thomas Associates
07-1093 Additions and Alterations 0-005-012 04/09/08 DONE DONE DONE 12/12/07 12/10/07 08/25/05 05/15/07 02 - 16 44,897,931 42,095,058 MGL 0 0 1,555,192
Thomas Associates
- Reconstruction 0-005-013 / / / / 03/21/06 / / 13,16 0 19,551,030 MGL 0 0 0
- XX Reconstruction 0-005-014 CANCELLED / / / / 09/11/06 / / 2,15 0 19,551,030 MGL 0 0 0
Cobbles Elementary:
04-0678 Reconstruction 0-006-009 03/22/05 DONE DONE DONE 01/13/05 01/12/05 12/18/03 05/18/04 10,155,15,16 1,316,800 1,316,800 RDR 0 0 0
Thomas Associates
09-0326 Reconstruction 0-006-010 STARTED STARTED UNREVIEWED10/21/09 10/19/09 08/25/05 05/15/07 2,8,9,10,15,16 0 11,978,235 DDJ 0 0 0
Tetra Tech Architects & Engineers
- XX Reconstruction 0-006-011 CANCELLED / / / / 03/21/06 / / 13,16 0 11,370,663 MGL 0 0 0
06-1268 Reconstruction 0-006-012 05/01/07 DONE DONE DONE 04/04/07 04/03/07 06/16/06 / / 2 92,048 92,048 MGL 0 0 0
Thomas Associates
Scribner Rd Elem:
07-1091 Reconstruction 0-007-008 04/30/08 DONE DONE DONE 12/12/07 12/10/07 08/25/05 05/15/07 2,4,7,8,9,10,13,155, 605,079 605,079 MGL 0 0 0
Thomas Associates
- XX Reconstruction 0-007-009 CANCELLED / / / / 03/21/06 / / 13,16 0 7,890,579 MGL 0 0 0
09-0327 Reconstruction 0-007-010 STARTED STARTED UNREVIEWED10/21/09 10/19/09 06/19/09 05/15/07 2,9,10,155,15,16 0 8,312,175 DDJ 0 0 0
Tetra Tech Architects & Engineers
Bay Trail Junior High School:
04-0679 Reconstruction 0-008-007 03/22/05 DONE DONE DONE 01/13/05 01/12/05 11/09/04 05/18/04 10 14,923 14,923 RDR 0 0 0
Thomas Associates
07-0359PR Additions and Alterations 0-008-008 10/23/07 DONE DONE DONE 09/13/07 / / 08/12/05 / / 02 - 16 0 0 MGL 0 0 0
Thomas Associates
07-1092 Additions and Alterations 0-008-008 04/30/08 DONE DONE DONE 12/12/07 12/10/07 08/12/05 05/15/07 02 - 16 22,665,701 22,469,304 MGL 0 0 0
Thomas Associates
- Reconstruction 0-008-009 / / / / 03/21/06 / / 13,16 0 23,151,368 MGL 0 0 0
Harris Hill Elementary:
04-0680 Reconstruction 0-009-009 03/22/05 DONE DONE DONE 01/13/05 01/12/05 12/18/03 05/18/04 10 12,623 12,623 RDR 0 0 0
Thomas Associates
09-0328 Reconstruction 0-009-011 STARTED STARTED UNREVIEWED10/21/09 10/19/09 08/12/05 05/15/07 2,4,7,8,9,10,13,155, 0 6,110,100 DDJ 0 0 0
Tetra Tech Architects & Engineers
- XX Reconstruction 0-009-012 CANCELLED / / / / 03/21/06 / / 13,16 0 5,800,140 MGL 0 0 0
District Office:
- Additions and Alterations 1-001-005 / / / / 08/25/05 / / 02 - 16 0 0 MGL 0 0 0
- XX Reconstruction 1-001-006 CANCELLED / / / / 03/21/06 / / 13,16 0 0 MGL 0 0 0
Maintenance Bldg:
- XX Additions and Alterations 3-004-002 CANCELLED / / / / 08/25/05 / / 02 - 16 0 0 MGL 0 0 0
New Maintenance Facility:
- XX New Construction 3-026-001 CANCELLED / / / / 09/28/05 / / 02 - 16 0 0 MGL 0 0 0
Bus Garage:
04-0681 Reconstruction 5-010-003 03/22/05 DONE DONE DONE 01/13/05 01/12/05 12/18/03 05/18/04 13 437,475 437,475 RDR 0 0 0
Thomas Associates
- Additions and Alterations 5-010-004 / / / / 08/25/05 / / 02 - 16 0 0 MGL 0 0 0
- XX Reconstruction 5-010-005 CANCELLED / / / / 03/21/06 / / 13,16 0 0 MGL 0 0 0
09-0329 Reconstruction 5-010-006 STARTED STARTED UNREVIEWED10/21/09 10/19/09 08/09/07 05/15/07 14,15,16 0 0 DDJ 0 0 0
Tetra Tech Architects & Engineers
Transportation Facility:
- XX New Construction 5-027-001 CANCELLED / / / / 09/28/05 / / 02 - 16 0 0 MGL 0 0 0
Concession Building:
- XX New Construction 7-025-001 CANCELLED / / / / 08/22/05 / / 02 - 16 0 0 MGL 0 0 0
Press Box & Public Restroom Facility:
07-1094 New Construction 7-028-001 04/09/08 DONE DONE DONE 12/12/07 12/10/07 08/17/07 05/15/07 02 - 16 504,725 0 MGL 0 0 0
Thomas Associates
Districtwide:
06-0239 Reconstruction 7-999-002 12/06/06 DONE DONE DONE 09/26/06 09/22/06 07/06/06 05/16/06 16 1,100,000 1,100,000 MGL 0 0 0
Thomas Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
J. Perrin Middle School:
07-0229PR Additions and Alterations 0-001-009 UNREVIEWED 08/23/07 08/17/07 02/04/00 05/16/00 02 - 16 10,122,000 8,998,840 DDJ 0 0 0
Clark Patterson Associates
07-0744 Additions and Alterations 0-001-009 04/18/08 DONE DONE DONE 11/06/07 11/01/07 02/04/00 05/15/07 02 - 16 10,122,000 9,083,058 DDJ 0 0 1,004,776
Clark Patterson Associates
05-1084 Reconstruction 0-001-011 05/19/06 DONE DONE DONE 03/31/06 03/31/06 07/06/05 05/16/06 7 1,484,070 1,484,070 DDJ 0 0 375,936
Clark Patterson Associates
Minerva Deland HS (9-12):
07-2235PR Additions and Alterations 0-002-012 UNREVIEWED 06/09/08 05/12/08 02/04/00 / / 02 - 16 5,696,692 4,979,999 DDJ 0 0 0
Clark Patterson Associates
08-0610 Additions and Alterations 0-002-012 03/30/09 DONE DONE DONE 10/29/08 10/28/08 02/04/00 12/06/07 02 - 16 5,247,373 4,634,468 DDJ 0 0 0
Clark Patterson Associates
04-0690 Reconstruction 0-002-014 01/28/05 DONE DONE DONE 01/19/05 01/18/05 09/29/04 11/17/04 4,13 519,312 519,312 DDJ 0 0 0
Clark Patterson Associates
05-1085 Reconstruction 0-002-015 05/19/06 DONE DONE DONE 03/31/06 03/31/06 07/06/05 05/16/06 7 355,999 355,999 DDJ 0 0 89,356
Clark Patterson Associates
Martha Brown Middle School:
07-2236PR Additions and Alterations 0-003-010 UNREVIEWED 06/09/08 05/12/08 02/04/00 / / 02 - 16 7,753,664 6,711,789 DDJ 0 0 0
Clark Patterson Associates
08-0611 Additions and Alterations 0-003-010 03/30/09 DONE DONE DONE 10/29/08 10/28/08 02/04/00 12/06/07 02 - 16 8,797,833 5,507,615 DDJ 0 0 0
Clark Patterson Associates
05-1086 Reconstruction 0-003-011 05/19/06 DONE DONE DONE 03/31/06 03/31/06 06/24/05 05/16/06 7 1,318,662 1,318,662 DDJ 0 0 276,243
Clark Patterson Associates
Brooks Hill Elem (K-5):
05-1069 Reconstruction 0-004-009 04/26/06 DONE DONE DONE 03/31/06 03/30/06 11/29/00 03/15/06 7 85,902 85,902 DDJ 0 0 0
Clark Patterson Associates
05-1087 Reconstruction 0-004-010 05/19/06 DONE DONE DONE 03/31/06 03/31/06 07/06/05 05/16/06 7 722,784 722,784 DDJ 0 0 181,419
Clark Patterson Associates
07-2231PR Additions and Alterations 0-004-011 UNREVIEWED 06/09/08 05/12/08 07/06/05 / / 02 - 16 8,671,978 6,196,323 DDJ 0 0 0
Clark Patterson Associates
08-0612 Additions and Alterations 0-004-011 03/30/09 DONE DONE DONE 10/29/08 10/28/08 07/06/05 12/06/07 02 - 16 8,338,873 6,699,882 DDJ 0 0 0
Clark Patterson Associates
06-1489 Additions and Alterations 0-004-012 09/05/07 DONE DONE DONE 05/14/07 05/14/07 04/30/07 04/25/07 02 - 16 412,809 0 DDJ 0 0 0
Clark Patterson Associates
Jefferson Ave Elem (K-5):
05-1088 Reconstruction 0-006-012 05/19/06 DONE DONE DONE 03/31/06 03/31/06 07/06/05 05/16/06 7 1,216,590 1,216,590 DDJ 0 0 262,353
Clark Patterson Associates
07-2232PR Additions and Alterations 0-006-013 UNREVIEWED 06/09/08 05/12/08 07/06/05 / / 02 - 16 3,533,156 2,570,077 DDJ 0 0 0
Clark Patterson Associates
08-0613 Additions and Alterations 0-006-013 03/30/09 DONE DONE DONE 10/29/08 10/28/08 07/06/05 12/06/07 02 - 16 2,817,066 2,499,583 DDJ 0 0 0
Clark Patterson Associates
Fairport High School (9-12):
05-1301 Reconstruction 0-007-012 07/18/06 DONE DONE DONE 05/31/06 05/31/06 02/04/00 04/26/06 15 93,911 93,911 DDJ 0 0 0
Clark Patterson Associates
07-0587 Alterations 0-007-013 02/22/08 DONE DONE DONE 10/19/07 10/18/07 07/06/05 05/15/07 02 - 16 1,666,000 1,666,000 DDJ 0 0 0
Clark Patterson Associates
08-0614 Reconstruction 0-007-014 03/30/09 DONE DONE DONE 12/15/08 12/15/08 12/11/07 12/06/07 9,16 676,382 676,400 DDJ 0 0 0
Clark Patterson Associates
Northside Elem (3-5):
07-2233PR Additions and Alterations 0-008-006 UNREVIEWED 06/09/08 05/12/08 07/06/05 / / 02 - 16 2,579,915 2,201,007 DDJ 0 0 0
Clark Patterson Associates
08-0615 Additions and Alterations 0-008-006 03/30/09 DONE DONE DONE 10/29/08 10/28/08 07/06/05 12/06/07 02 - 16 1,936,664 1,708,751 DDJ 0 0 0
Clark Patterson Associates
05-1089 Reconstruction 0-008-007 05/19/06 DONE DONE DONE 03/31/06 03/31/06 06/24/05 05/16/06 7 188,834 188,834 DDJ 0 0 47,398
Clark Patterson Associates
Dudley Elem (K-2):
07-2234PR Reconstruction 0-009-010 UNREVIEWED 06/09/08 05/12/08 06/24/05 / / 2,4,8,9,155,15,16 2,007,002 1,637,828 DDJ 0 0 0
Clark Patterson Associates
08-0616 Reconstruction 0-009-010 03/30/09 DONE DONE DONE 10/29/08 10/28/08 06/24/05 12/06/07 2,4,8,9,155,15,16 2,085,809 1,811,558 DDJ 0 0 0
Clark Patterson Associates
05-1090 Reconstruction 0-009-011 05/19/06 DONE DONE DONE 03/31/06 03/31/06 07/06/05 05/16/06 7 188,834 188,834 DDJ 0 0 47,398
Clark Patterson Associates
Streppa Building:
- PR Additions and Alterations 1-005-003 / / / / 06/30/05 / / 02 - 16 0 0 DDJ 0 0 0
New Administration Office Bldg.:
- Reconstruction 1-023-003 / / / / 07/06/05 / / 2,7,8,9,155,15,16 0 0 DDJ 0 0 0
Storage Container BUS 4679:
07-1056DB Discovered Building 2-029-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container MD 10193:
07-1057DB Discovered Building 2-030-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container MD 1309:
07-1058DB Discovered Building 2-031-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container MD 420:
07-1059DB Discovered Building 2-032-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container JP9027:
07-1060DB Discovered Building 2-033-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container:
07-1061DB Discovered Building 2-034-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container BH382:
07-1062DB Discovered Building 2-035-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Contanier BH99020:
07-1063DB Discovered Building 2-036-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container MB 55073:
07-1064DB Discovered Building 2-037-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Storage Container MB 60136:
07-1065DB Discovered Building 2-038-001 01/17/08 DONE DONE DONE 12/06/07 11/30/07 09/05/07 / / 0 0 DDJ 0 0 0
Design Professionals
Maintenance Bldg.:
- Reconstruction 3-011-003 / / / / 07/06/05 / / 2,8,9,155,15,16 0 0 DDJ 0 0 0
Bus Center:
04-1425 Reconstruction 5-010-009 08/19/05 DONE DONE DONE 06/17/05 06/15/05 04/12/05 05/17/05 2,155,16 99,643 99,643 DDJ 0 0 0
Clark Patterson Associates
- PR Additions and Alterations 5-010-010 / / / / 07/06/05 / / 02 - 16 0 0 DDJ 0 0 0
Transportation Substation @ Dudley:
- New Construction 5-024-001 / / / / 06/27/05 / / 02 - 16 0 0 DDJ 0 0 0
Concession\Bathrooms:
07-0588 New Construction 7-025-001 02/22/08 DONE DONE DONE 10/19/07 10/18/07 06/27/05 05/15/07 02 - 16 388,000 0 DDJ 0 0 0
Clark Patterson Associates
Bleachers/Coaches Booth/Press Box:
07-0589 New Construction 7-026-001 02/22/08 DONE DONE DONE 10/19/07 10/18/07 06/27/05 05/15/07 02 - 16 460,000 0 DDJ 0 0 0
Clark Patterson Associates
Track Storage Bldg:
07-1837DB Discovered Building 7-027-001 12/10/08 DONE DONE DONE 03/19/08 03/14/08 02/15/06 / / 02 - 16 0 0 DDJ 0 0 0
SWBR Architects P.C.
Football Storage Bldg:
07-1838DB Discovered Building 7-028-001 12/10/08 DONE DONE DONE 03/19/08 03/14/08 02/15/06 / / 02 - 16 0 0 DDJ 0 0 0
SWBR Architects P.C.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
E. Rochester Educ. Cmplx.(O'Bourn):
05-0247 Additions and Alterations 0-001-013 05/19/06 DONE DONE DONE 10/07/05 10/06/05 02/13/03 05/17/05 02 - 16 2,233,000 2,233,000 RDR 0 0 0
EDGE Architecture
03-1556 Reconstruction 0-001-014 04/13/05 DONE DONE DONE 05/17/04 05/17/04 02/02/04 12/18/03 9,155,15,16 1,025,000 1,025,000 RDR 0 0 0
EDGE Architecture
05-1245 Additions and Alterations 0-001-015 07/10/06 DONE DONE DONE 05/08/06 05/04/06 04/06/05 05/17/05 02 - 16 42,884 42,884 RDR 0 0 0
EDGE Architecture
07-1782 Reconstruction 0-001-016 09/30/08 DONE DONE DONE 03/09/08 03/05/08 07/16/07 10/16/07 2,4,7,8,9,10,155,15, 7,150,000 7,150,000 JOD 0 0 376,860
EDGE Architecture
LE BIRD/TLRMorgan Middle School:
05-1323 Reconstruction 0-002-009 07/10/06 DONE DONE DONE 06/06/06 06/05/06 12/05/05 01/17/06 2,4,7,9 19,717 19,717 JOD 0 0 0
SWBR Architects P.C.
06-0807 Reconstruction 0-002-010 04/27/07 DONE DONE DONE 01/24/07 01/24/07 01/19/07 12/19/06 2,9,155,15,16 99,221 99,221 JOD 0 0 0
SWBR Architects P.C.
Lois E. Bird Elementary:
05-1324 Reconstruction 0-003-008 07/10/06 DONE DONE DONE 06/06/06 06/05/06 11/02/05 01/17/06 2,4,7,9 78,867 78,867 JOD 0 0 0
SWBR Architects P.C.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jefferson Rd. Elementary:
05-0016 Reconstruction 0-002-020 03/30/06 DONE DONE DONE 07/06/05 07/01/05 08/09/04 12/03/02 2,16 0 8,351,880 JOD 0 0 0
Thomas Associates
04-1488 Reconstruction 0-002-021 04/17/06 DONE DONE DONE 06/30/05 06/29/05 05/26/05 12/03/02 155,15,16 278,696 278,696 JOD 0 0 106,741
Thomas Associates
Sutherland High School:
06-0414SC Visual Structural Inspection 0-003-SC1 11/03/06 DONE DONE DONE 10/16/06 10/16/06 / / / / 16 24,065 24,065 JOD 0 0 0
08-1690SC Visual Structural Inspection 0-003-SC2 06/18/09 DONE DONE DONE 03/17/09 03/17/09 / / / / 16 3,616 0 JOD 0 0 0
Pittsford(Barker Rd.)MS:
04-1487 Reconstruction 0-007-016 01/26/06 DONE DONE DONE 06/30/05 06/29/05 12/18/03 12/03/02 15 409,346 409,346 JOD 0 0 149,140
Thomas Associates
04-1225 Reconstruction 0-007-017 04/12/05 DONE DONE DONE 05/06/05 05/02/05 08/09/04 12/03/02 13,155,15,16 451,000 451,000 JOD 0 0 0
Thomas Associates
06-0412SC Visual Structural Inspection 0-007-SC1 11/03/06 DONE DONE DONE 10/16/06 10/16/06 / / / / 16 23,019 23,019 JOD 0 0 0
Pittsford High Sch. (Mendon):
04-1227 Reconstruction 0-009-018 04/25/06 DONE DONE DONE 05/06/05 05/02/05 08/09/04 12/03/02 155,16 310,000 310,000 JOD 0 0 0
Thomas Associates
- Reconstruction 0-009-019 / / / / 05/26/05 / / 15 0 18,007,110 JOD 0 0 0
- PR Additions and Alterations 0-009-020 / / / / 02/13/06 / / 02 - 16 0 0 JOD 0 0 0
07-1943 Reconstruction 0-009-021 04/17/08 DONE DONE DONE 04/14/08 04/03/08 03/17/08 05/16/06 2,7 1,744,040 1,744,040 JOD 0 0 0
Thomas Associates
08-0885 Reconstruction 0-009-022 12/09/08 DONE DONE DONE 12/08/08 12/05/08 10/06/08 10/24/08 16 60,000 60,000 JOD 0 0 43,337
TETRA TECH ARCHITECTS & ENGINEERS
- Reconstruction 0-009-023 / / / / 05/07/09 / / 16 0 0 JOD 0 0 0
06-0413SC Visual Structural Inspection 0-009-SC1 11/03/06 DONE DONE DONE 10/16/06 10/16/06 / / / / 16 24,065 24,065 JOD 0 0 0
New Middle School:
06-0411SC Visual Structural Inspection 0-025-SC1 11/03/06 DONE DONE DONE 10/16/06 10/16/06 / / / / 16 22,050 22,050 JOD 0 0 0
Bus Garage:
09-0269 Reconstruction 5-011-068 10/01/09 DONE DONE DONE 09/28/09 09/28/09 08/17/09 08/10/09 4,9,14,15,16 797,069 0 JOD 0 0 0
TETRA TECH ARCHITECTS & ENGINEERS
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Chestnut Ridge Elementary:
06-1447 Reconstruction 0-001-007 09/21/07 DONE DONE DONE 05/08/07 05/07/07 11/21/06 01/30/07 2,4,7,155,15,16 1,074,631 1,074,631 MGL 0 0 114,985
SEI Design Group
- Reconstruction 0-001-008 / / / / 09/28/09 / / 2,4,9,16 0 0 DDJ 0 0 0
Churchville Elementary:
06-1448 Reconstruction 0-002-007 09/21/07 DONE DONE DONE 05/08/07 05/07/07 11/21/06 01/30/07 2,4,7,155,15,16 2,459,525 2,459,525 MGL 0 0 263,169
SEI Design Group
06-0054SC Visual Structural Inspection 0-002-SC1 08/08/06 DONE DONE DONE 07/05/06 07/05/06 / / / / 16 3,694 3,694 JOD 0 0 0
06-0055SC Visual Structural Inspection 0-002-SC2 08/08/06 DONE DONE DONE 07/05/06 07/05/06 / / / / 16 3,106 3,106 JOD 0 0 0
07-2183SC Visual Structural Inspection 0-002-SC3 09/26/08 DONE DONE DONE 03/03/08 03/03/08 / / / / 16 9,204 0 JOD 0 0 0
Fairbank Rd Elem:
06-1449 Reconstruction 0-004-007 09/21/07 DONE DONE DONE 05/08/07 05/07/07 11/21/06 01/30/07 2,4,7,155,15,16 3,092,311 3,092,311 MGL 0 0 330,877
SEI Design Group
08-1175 Reconstruction 0-004-008 03/11/09 DONE DONE DONE 02/09/09 02/02/09 07/24/07 05/20/08 2,9 100,000 0 DDJ 0 0 0
SEI Design Group
- Reconstruction 0-004-009 / / / / / / / / 2,4,8,9,155,15,16 0 0 DDJ 0 0 0
08-1176 Reconstruction 0-004-010 03/11/09 DONE DONE DONE 02/09/09 02/02/09 01/29/09 05/20/08 2,9 422,074 422,074 DDJ 0 0 35,191
SEI Design Group
Senior High School:
06-1450 Reconstruction 0-005-007 09/21/07 DONE DONE DONE 05/08/07 05/07/07 11/21/06 01/30/07 2,4,7,155,15,16 731,885 731,885 MGL 0 0 78,312
SEI Design Group
07-0723 Reconstruction 0-005-008 11/13/07 DONE DONE DONE 11/06/07 11/02/07 08/09/07 05/15/07 2,9 100,000 100,000 MGL 0 0 0
Design Group Educ. Fac. Dept.
08-0196PR Additions and Alterations 0-005-009 UNREVIEWED 08/22/08 07/24/08 08/12/08 / / 02 - 16 38,226,194 33,616,819 DDJ 0 0 0
SEI Design Group
Middle School:
06-1451 Reconstruction 0-006-007 09/21/07 DONE DONE DONE 05/08/07 05/07/07 11/21/06 01/30/07 2,4,7,15,16 1,471,648 1,471,648 MGL 0 0 157,466
SEI Design Group
- Reconstruction 0-006-008 / / / / 08/09/07 / / 2 0 60,602,438 MGL 0 0 0
08-0198PR Additions and Alterations 0-006-009 UNREVIEWED 08/22/08 07/24/08 08/12/08 / / 02 - 16 3 9,915,950 DDJ 0 0 0
SEI Design Group
eus Storage Building:
03-1684 New Construction 4-012-001 04/26/05 DONE DONE DONE 06/29/04 06/22/04 01/27/04 01/18/00 02 - 16 29,000 29,000 RDR 0 0 0
Thomas Associates
New Transportation Facility:
- Reconstruction 5-009-003 / / / / 08/12/08 / / 2,8,9,15 0 0 DDJ 0 0 0
Transportation Facility:
08-1390SC Visual Structural Inspection 7-010-SC1 03/17/09 DONE DONE DONE 02/02/09 02/02/09 / / / / 16 6,358 4,000 JOD 0 0 0
Concession (metal bldg.):
03-1685 New Construction 7-011-001 04/26/05 DONE DONE DONE 06/29/04 06/22/04 09/02/03 01/18/00 02 - 16 29,000 0 RDR 0 0 0
Thomas Associates
Ticket Booth (Metal Bldg.):
03-1686 New Construction 7-013-001 04/26/05 DONE DONE DONE 06/29/04 06/22/04 09/02/03 01/18/00 02 - 16 6,250 0 RDR 0 0 0
Thomas Associates
Pressbox:
03-1687 New Construction 7-014-001 04/26/05 DONE DONE DONE 06/29/04 06/22/04 11/05/03 01/18/00 02 - 16 13,750 0 RDR 0 0 0
Thomas Associates
Operations/Security Bldg (House):
05-1410PR New Construction 7-015-001 06/21/06 DONE DONE DONE 06/22/06 06/21/06 06/14/06 / / 02 - 16 147,000 0 MGL 0 0 0
Thomas Associates
07-1572DB Discovered Building 7-015-002 04/30/08 DONE DONE DONE 02/08/08 02/06/08 06/26/06 / / 0 0 MGL 0 0 0
SEI Design Group
District-Wide:
08-1308 Reconstruction 7-999-002 05/07/09 DONE DONE DONE 03/02/09 02/26/09 01/21/09 12/09/08 10,13,15,16 1,741,600 1,741,600 DDJ 0 0 182,392
SEI Design Group
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
#1 M B Anderson K-6:
- Reconstruction 0-001-019 / / / / 07/15/09 / / 8,155,15,16 0 0 DDJ 0 0 0
#2 Clara Barton K-6:
05-0490 Reconstruction 0-002-014 03/16/06 DONE DONE DONE 12/23/05 12/23/05 07/27/05 07/01/05 2,4,9,16 541,770 541,770 RDR 0 0 10,835
Harison Bridges & Associates
08-0791 Reconstruction 0-002-015 01/30/09 DONE DONE DONE 11/25/08 11/24/08 05/01/08 07/01/08 2,8,155,16 453,552 453,552 DDJ 0 0 9,071
HBT Architects
#3 Nathaniel Rochester Cmmty K-8:
05-0603 Reconstruction 0-003-015 04/12/06 DONE DONE DONE 01/18/06 01/09/06 07/27/05 07/10/05 8,9,155,16 939,004 939,004 RDR 0 0 17,132
CMA Architecture,P.C
07-1045 Reconstruction 0-003-016 02/29/08 DONE DONE DONE 12/05/07 12/03/07 07/20/07 07/01/07 155,16 934,679 934,679 MGL 0 0 18,694
CMA Architecture,P.C
08-0832 Reconstruction 0-003-017 02/13/09 DONE DONE DONE 12/02/08 12/01/08 05/01/08 07/01/08 2,10,155,16 977,401 977,401 DDJ 0 0 19,548
CMA Architecture,P.C
- Reconstruction 0-003-018 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
#4 G.M.Forbes K-6:
04-0898 Reconstruction 0-004-017 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/09/04 07/01/04 16 47,938 47,938 RDR 0 0 0
TLC Engineering,P.C.
05-0489 Reconstruction 0-004-018 03/16/06 DONE DONE DONE 12/23/05 12/23/05 07/27/05 07/01/05 4,8,9,155,15,16 814,193 814,193 RDR 0 0 16,526
Hunt Engineers & Architects & Survey
08-0787 Reconstruction 0-004-019 02/13/09 DONE DONE DONE 11/24/08 11/24/08 05/01/08 07/01/08 155,15,16 513,216 513,216 DDJ 0 0 10,264
Clark Patterson Associates
#5 J.Williams K-5:
04-0899 Reconstruction 0-005-019 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 12,331,165 RDR 0 0 0
TLC Engineering,P.C.
05-0549 Reconstruction 0-005-020 04/03/06 DONE DONE DONE 01/11/06 / / 07/28/05 07/01/05 2,4,7,8,9,155,15,16 1,232,171 1,232,171 RDR 0 0 24,177
Design Group Educ. Fac. Dept.
07-1423 Reconstruction 0-005-021 04/11/08 DONE DONE DONE 01/18/08 01/17/08 07/20/07 07/01/07 4,7,13 836,649 836,649 MGL 0 0 16,733
Stantec Consulting Services Inc,.
08-0741 Reconstruction 0-005-022 12/17/08 DONE DONE DONE 11/10/08 11/07/08 05/01/08 07/01/08 2,9,155,15,16 1,851,123 1,851,123 DDJ 0 0 37,022
Hunt Engineers & Architects & Survey
09-0378 Reconstruction 0-005-023 11/10/09 DONE DONE DONE 11/03/09 10/30/09 07/15/09 07/01/09 8 800,000 0 DDJ 0 0 16,000
Design Group Educ. Fac. Dept.
#6 Dag Hammarskjold K-6:
05-0561 Reconstruction 0-006-016 04/05/06 DONE DONE DONE 01/17/06 01/09/06 07/28/05 07/01/05 4,8,9 360,027 360,027 RDR 0 0 0
M/E Engineering
- Reconstruction 0-006-017 / / / / 07/20/07 / / 2 0 0 MGL 0 0 0
08-0768 Reconstruction 0-006-018 12/31/08 DONE DONE DONE 11/19/08 11/18/08 05/01/08 07/01/08 2,7,8,155,16 734,976 734,976 DDJ 0 0 14,700
Miller- Anderson Architects
09-0379 Reconstruction 0-006-019 11/16/09 DONE DONE DONE 11/03/09 11/02/09 07/15/09 07/01/09 8 0 0 DDJ 0 0 0
Design Group Educ. Fac. Dept.
#7 Virgil Grissom K-6:
05-0441 Reconstruction 0-007-015 03/13/06 DONE DONE DONE 12/13/05 12/12/05 07/28/05 07/01/05 2,8,9,155,15,16 632,705 632,705 RDR 0 0 12,654
HBMA Architecture Engineering & Land
08-0888 Reconstruction 0-007-016 02/04/09 DONE DONE DONE 12/09/08 12/08/08 05/01/08 07/01/08 2,8,9,10,16 827,376 827,376 DDJ 0 0 16,548
SEI Design Group
#9 M.L.King K-6:
06-0662 Reconstruction 0-009-017 02/09/07 DONE DONE DONE 12/27/06 12/22/06 03/30/06 07/01/06 8,10,13,155,16 986,175 986,175 MGL 0 0 19,723
CMA Architecture,P.C
07-0852 Reconstruction 0-009-018 02/07/08 DONE DONE DONE 11/20/07 11/16/07 07/20/07 07/01/07 2,155 1,095,389 1,095,389 MGL 0 0 21,908
Design Group Educ. Fac. Dept.
- PR Additions and Alterations 0-009-019 / / / / 07/15/09 / / 02 - 16 0 0 DDJ 0 0 0
Roberto Clemente New ES8:
06-0553 Reconstruction 0-010-007 03/30/07 DONE DONE DONE 11/28/06 11/27/06 03/30/06 07/01/06 2,4,8,9,10,13,155,15 739,616 739,616 MGL 0 0 14,792
HBMA Architecture Engineering & Land
- Reconstruction 0-010-008 / / / / 07/15/09 / / 2,13,16 0 0 DDJ 0 0 0
M McLeod Bethune #45(fmlyNE.Elem):
06-1099 Reconstruction 0-011-008 04/11/07 DONE DONE DONE 03/14/07 03/08/07 03/30/06 07/01/06 2,10,13,155,15,16 400,000 400,000 MGL 0 0 0
IBC Engineering,P.C.
- Reconstruction 0-011-009 / / / / 09/21/09 / / 10,16 0 0 DDJ 0 0 0
#12 J.P.B.Duffy K-5:
04-0700 Reconstruction 0-012-016 03/28/05 DONE DONE DONE 01/21/05 01/20/05 05/05/04 07/01/04 16 305,879 305,879 RDR 0 0 0
Terrence J. Costich
07-0824 Reconstruction 0-012-017 02/11/08 DONE DONE DONE 11/16/07 11/15/07 07/19/07 07/01/07 2,4,9,10,15,16 731,350 0 MGL 0 0 0
Hunt Engineers & Architects & Survey
#14 C.Dewey/W of Inquiry K-5:
06-0710 Reconstruction 0-014-021 02/09/07 DONE DONE DONE 01/04/07 01/03/07 03/30/06 07/01/06 2,4,7,8,9,14,155,15, 540,705 540,705 MGL 0 0 10,814
CMA Architecture,P.C
- Reconstruction 0-014-022 / / / / 07/15/09 / / 7 0 0 DDJ 0 0 0
- Reconstruction 0-014-023 / / / / 07/15/09 / / 2,4,7,8,9,13,16 0 0 DDJ 0 0 0
#15 Freeman Clarke School:
04-0900 Reconstruction 0-015-007 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 39,191 39,191 RDR 0 0 0
TLC Engineering,P.C.
04-0549 Reconstruction 0-015-008 03/16/05 DONE DONE DONE 12/15/04 12/13/04 05/05/04 07/01/04 8,9,155,15,16 641,592 641,592 RDR 0 0 0
Plan Architectural Studio, P.C.
07-1335 Reconstruction 0-015-009 03/17/08 DONE DONE DONE 01/07/08 01/04/08 07/19/07 07/01/07 4,8,13,15,16 244,015 244,015 MGL 0 0 4,880
CMA Architecture,P.C
#16 J.W.Spencer K-6:
06-0638 Reconstruction 0-016-016 01/29/07 DONE DONE DONE 12/21/06 12/18/06 03/30/06 07/01/06 9,16 39,270 39,270 MGL 0 0 785
Terrence J. Costich
09-0450 Reconstruction 0-016-017 UNREVIEWED 11/19/09 11/16/09 07/15/09 07/01/09 2,4,8,9,13,155,15,16 0 0 DDJ 0 0 0
Design Group Educ. Fac. Dept.
#17 Enrico Fermi K-5:
04-0901 Reconstruction 0-017-018 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 44,734 44,734 RDR 0 0 0
TLC Engineering,P.C.
04-0420 Reconstruction 0-017-019 01/19/05 DONE DONE DONE 11/22/04 11/18/04 05/05/04 07/01/04 2,7,9,155,15,16 1,930,914 1,930,914 RDR 0 0 0
RFL Architects,P>C.
07-0671 Reconstruction 0-017-020 02/13/08 DONE DONE DONE 10/30/07 10/29/07 07/19/07 07/01/07 2,8,9,16 1,023,207 1,023,207 MGL 0 0 20,464
IBC Engineering,P.C.
School of the Arts:
04-0902 Reconstruction 0-018-009 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 56,554 56,554 RDR 0 0 0
TLC Engineering,P.C.
04-0660 Reconstruction 0-018-010 02/24/05 DONE DONE DONE 01/11/05 01/10/05 05/06/04 07/01/04 2,4,9,16 633,533 633,533 RDR 0 0 0
FJF Architects, LLP
07-1421 Reconstruction 0-018-011 03/18/08 DONE DONE DONE 01/18/08 01/17/08 07/20/07 07/01/07 8,9,10,13,155,15,16 195,641 195,641 MGL 0 0 3,913
Miller- Anderson Architects
- Reconstruction 0-018-012 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
#19 Dr.C.T.Lunsford K-6:
04-0903 Reconstruction 0-019-016 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 8,815,748 RDR 0 0 0
TLC Engineering,P.C.
04-0581 Reconstruction 0-019-017 02/28/05 DONE DONE DONE 12/27/04 12/24/04 05/05/04 07/01/04 2,9,15,16 536,826 536,826 RDR 0 0 0
FJF Architects, LLP
07-0825 Reconstruction 0-019-018 02/11/08 DONE DONE DONE 11/16/07 11/15/07 07/19/07 07/01/07 8,9,155,16 350,764 350,764 MGL 0 0 7,015
Hunt Engineers & Architects & Survey
#20 Early Childhood School:
04-0904 Reconstruction 0-020-010 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 51,082 51,082 RDR 0 0 0
TLC Engineering,P.C.
04-1132 Reconstruction 0-020-011 05/19/05 DONE DONE DONE 04/11/05 04/11/05 05/05/04 07/01/04 4,10,16 275,350 275,350 RDR 0 0 0
Terrence J. Costich
07-1881 Reconstruction 0-020-012 05/27/08 DONE DONE DONE 03/31/08 03/24/08 07/19/07 07/01/07 2,4,155,16 142,428 142,428 MGL 0 0 948
IBC Engineering,P.C.
#22 Abe Lincoln K-6:
06-0711 Reconstruction 0-022-019 02/09/07 DONE DONE DONE 01/04/07 01/03/07 03/30/06 07/01/06 2,4,7,155,16 200,000 200,000 MGL 0 0 0
CMA Architecture,P.C
09-0451 Reconstruction 0-022-020 UNREVIEWED 11/19/09 11/16/09 07/15/09 07/01/09 2,8,9,155,15,16 0 0 DDJ 0 0 0
Design Group Educ. Fac. Dept.
Francis Parker School No.23:
04-0905 Reconstruction 0-023-014 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 45,757 45,757 RDR 0 0 0
TLC Engineering,P.C.
04-0567 Reconstruction 0-023-015 02/18/05 DONE DONE DONE 12/17/04 12/16/04 05/05/04 07/01/04 2,9,16 703,269 703,269 RDR 0 0 0
Terrence J. Costich
07-1882 Reconstruction 0-023-016 05/27/08 DONE DONE DONE 03/31/08 03/24/08 07/19/07 07/01/07 9,10,155,15,16 73,656 73,656 MGL 0 0 1,473
IBC Engineering,P.C.
#25 N.Hawthorne K-6:
04-0570 Reconstruction 0-025-015 01/07/05 DONE DONE DONE 12/22/04 12/17/04 05/05/04 07/01/04 2,4,8,16 0 5,777,965 RDR 0 0 0
Terrence J. Costich
07-1883 Reconstruction 0-025-016 05/27/08 DONE DONE DONE 03/31/08 03/24/08 07/19/07 07/01/07 9,15,16 18,480 18,480 MGL 0 0 370
IBC Engineering,P.C.
#28 Henry Hudson K-6:
04-0906 Reconstruction 0-028-019 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 7,868,872 RDR 0 0 0
TLC Engineering,P.C.
05-0538 Reconstruction 0-028-020 03/16/06 DONE DONE DONE 01/04/06 01/03/06 07/28/05 07/01/05 4,9,155,15,16 540,079 540,079 RDR 0 0 10,802
Miller- Anderson Architects
08-0734 Reconstruction 0-028-021 12/26/08 DONE DONE DONE 11/10/08 11/07/08 05/01/08 07/01/08 2,155,15,16 329,919 329,919 DDJ 0 0 0
Architectura
#29 Adlai Stevenson K-6:
04-0907 Reconstruction 0-029-018 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 44,541 44,541 RDR 0 0 0
TLC Engineering,P.C.
05-0550 Reconstruction 0-029-019 04/13/06 DONE DONE DONE 01/11/06 / / 07/28/05 07/01/05 2,8,9 478,500 478,500 RDR 0 0 0
Design Group Educ. Fac. Dept.
08-0997 Reconstruction 0-029-020 02/27/09 DONE DONE DONE 01/02/09 12/22/08 05/01/08 07/01/08 2,8,9,10,155,16 454,901 454,901 DDJ 0 0 9,098
Stantec Consulting Services Inc,.
- Reconstruction 0-029-021 / / / / 09/25/08 / / 2,4,7,8,9,155,15,16 0 0 DDJ 0 0 0
#30 Gen E.S.Otis K-6:
04-0908 Reconstruction 0-030-018 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 7,052,599 RDR 0 0 0
TLC Engineering,P.C.
05-0491 Reconstruction 0-030-019 03/16/06 DONE DONE DONE 12/23/05 12/23/05 07/28/05 07/01/05 2,8,9,16 495,000 495,000 RDR 0 0 0
Harison Bridges & Associates
08-0895 Reconstruction 0-030-020 01/12/09 DONE DONE DONE 12/09/08 12/08/08 05/01/08 07/01/08 2,8,9 217,470 217,470 DDJ 0 0 4,349
Razak Associates,LLC,Architects
Dr. Freddie Thomas Lrng. Ctr.:
04-0909 Reconstruction 0-031-007 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 11,956 11,956 RDR 0 0 0
TLC Engineering,P.C.
05-0562 Reconstruction 0-031-008 04/05/06 DONE DONE DONE 01/17/06 01/09/06 07/28/05 07/01/05 2,4,7,8,9,155,16 400,000 400,000 RDR 0 0 0
M/E Engineering
08-0835 Reconstruction 0-031-009 03/04/09 DONE DONE DONE 12/02/08 12/01/08 05/01/08 07/01/08 10,13,16 688,182 688,182 DDJ 0 0 13,764
FRA engineering & Architecture
- Reconstruction 0-031-010 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Wilson Foundation Academy:
06-0683 Reconstruction 0-032-005 03/19/07 DONE DONE DONE 12/28/06 12/27/06 03/30/06 07/01/06 9,10,13,155 100,000 100,000 MGL 0 0 0
CMA Architecture,P.C
- Reconstruction 0-032-006 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Audubon K-6:
04-0910 Reconstruction 0-033-017 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 64,535 64,535 RDR 0 0 0
TLC Engineering,P.C.
07-0117 Reconstruction 0-033-019 01/25/08 DONE DONE DONE 08/01/07 07/31/07 07/28/05 11/16/06 2,4,7,8,9,155,15,16 36,500,000 21,904,023 MGL 0 0 9,333,051
Stantec Architecture
#34 Dr. L.A.Cerulli K-6:
06-0604 Reconstruction 0-034-018 02/07/07 DONE DONE DONE 12/11/06 12/11/06 03/30/06 07/01/06 8,9,10,13,155,15,16 383,980 383,980 MGL 0 0 7,680
Miller- Anderson Architects
- Reconstruction 0-034-019 / / / / 07/15/09 / / 2,8,9,10,13,155,15,1 0 0 DDJ 0 0 0
#35 Pinnacle K-6:
04-0911 Reconstruction 0-035-014 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 57,237 57,237 RDR 0 0 0
TLC Engineering,P.C.
04-0583 Reconstruction 0-035-015 02/09/05 DONE DONE DONE 12/27/04 12/24/04 05/05/04 07/01/04 2,9,155 669,011 669,011 RDR 0 0 0
Heininger Bataille Marquest Alatmura
07-1474 Reconstruction 0-035-016 04/14/08 DONE DONE DONE 01/29/08 01/28/08 07/19/07 07/01/07 8,155,16 59,136 59,136 MGL 0 0 1,183
FRA engineering & Architecture
#36 H.W.Longfellow K-5:
04-0912 Reconstruction 0-036-013 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 29,429 29,429 RDR 0 0 0
TLC Engineering,P.C.
04-1066 Reconstruction 0-036-014 04/12/05 DONE DONE DONE 04/01/05 03/31/05 05/05/04 07/01/04 2,8,9,16 115,360 115,360 RDR 0 0 0
FJF Architects, LLP
07-1475 Reconstruction 0-036-015 04/14/08 DONE DONE DONE 01/29/08 01/28/08 07/19/07 07/01/07 9,14 27,720 27,720 MGL 0 0 554
FRA engineering & Architecture
#37 L.E.Morgan K-6:
- Reconstruction 0-037-016 / / / / 11/01/06 / / 2,4,7,8,9,10,13,155, 0 4,629,371 MGL 0 0 0
- Reconstruction 0-037-017 / / / / 07/20/07 / / 2,7,8,9,155,16 0 0 MGL 0 0 0
#39 A.J.Townson K-6:
04-0913 Reconstruction 0-039-014 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 47,933 47,933 RDR 0 0 0
TLC Engineering,P.C.
05-0505 Reconstruction 0-039-015 03/13/06 DONE DONE DONE 12/27/05 12/23/05 07/28/05 07/01/05 2,8,155,16 1,071,917 1,071,917 RDR 0 0 0
CMA Architecture,P.C
08-0836 Reconstruction 0-039-016 03/04/09 DONE DONE DONE 12/02/08 12/01/08 05/01/08 07/01/08 2,4 397,000 0 DDJ 0 0 0
FRA engineering & Architecture
#41 Kodak Park K-6:
04-0914 Reconstruction 0-041-018 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 32,786 32,786 RDR 0 0 0
TLC Engineering,P.C.
04-1133 Reconstruction 0-041-019 06/10/05 DONE DONE DONE 04/11/05 04/11/05 05/05/04 07/01/04 2,9,15,16 343,098 343,098 RDR 0 0 0
Terrence J. Costich
07-1884 Reconstruction 0-041-020 05/27/08 DONE DONE DONE 03/31/08 03/24/08 07/19/07 07/01/07 8,9,13,155,16 42,240 42,240 MGL 0 0 845
IBC Engineering,P.C.
- Reconstruction 0-041-021 / / / / 07/19/07 / / 9,15,16 0 0 MGL 0 0 0
#42 Abelard Reynolds K-6:
- XX Reconstruction 0-042-013 CANCELLED / / / / 01/14/05 / / 155,15,16 0 7,207,211 MGL 0 0 0
06-1047 Reconstruction 0-042-014 04/30/07 DONE DONE DONE 03/06/07 03/01/07 03/30/06 07/01/06 9,13,155,15,16 385,167 385,167 MGL 0 0 7,703
Terrence J. Costich
09-0385 Additions and Alterations 0-042-015 STARTED STARTED UNREVIEWED11/03/09 11/02/09 07/15/09 07/01/09 02 - 16 0 0 DDJ 0 0 0
Design Group Educ. Fac. Dept.
#43 T.Roosevelt K-6:
04-0915 Reconstruction 0-043-013 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 65,802 65,802 RDR 0 0 0
TLC Engineering,P.C.
04-0421 Reconstruction 0-043-014 01/03/05 DONE DONE DONE 11/22/04 11/18/04 05/05/04 07/01/04 8,9,155,15,16 365,462 365,462 RDR 0 0 0
Fraser-Willey&Associaes,P.C
07-1476 Additions and Alterations 0-043-015 04/14/08 DONE DONE DONE 01/29/08 01/28/08 07/19/07 07/01/07 02 - 16 148,896 148,896 MGL 0 0 2,978
FRA engineering & Architecture
#44 Lincoln Park K-6:
06-0712 Reconstruction 0-044-021 02/09/07 DONE DONE DONE 01/04/07 01/03/07 03/30/06 07/01/06 8,9,10,15 454,356 454,356 MGL 0 0 9,087
CMA Architecture,P.C
07-1885 Reconstruction 0-044-022 05/27/08 DONE DONE DONE 03/31/08 03/24/08 07/20/07 07/01/07 155,15 240,636 240,636 MGL 0 0 4,813
IBC Engineering,P.C.
09-0418 Reconstruction 0-044-023 STARTED STARTED UNREVIEWED11/18/09 11/09/09 07/15/09 07/01/09 4 0 0 DDJ 0 0 0
Design Group Educ. Fac. Dept.
Sch W/out Walls 9-12:
04-0550 Reconstruction 0-045-011 03/16/05 DONE DONE DONE 12/15/04 12/13/04 05/07/04 07/01/04 2,8,9,155,15,16 495,704 495,704 RDR 0 0 0
Plan Architectural Studio, P.C.
07-1336 Reconstruction 0-045-012 03/17/08 DONE DONE DONE 01/07/08 01/04/08 07/24/07 07/01/07 8,16 532,963 532,963 MGL 0 0 10,659
CMA Architecture,P.C
- Reconstruction 0-045-013 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
- Reconstruction 0-045-014 / / / / 07/15/09 / / 16 0 0 DDJ 0 0 0
- Reconstruction 0-045-015 / / / / 07/15/09 / / 13,16 0 0 DDJ 0 0 0
- Reconstruction 0-045-016 / / / / / / / / 16 0 0 DDJ 0 0 0
#46 C.Carroll K-6:
05-0537 Reconstruction 0-046-018 03/15/06 DONE DONE DONE 01/04/06 01/03/06 07/28/05 07/01/05 7,10 76,263 76,263 RDR 0 0 1,525
Miller- Anderson Architects
08-0837 Reconstruction 0-046-019 03/04/09 DONE DONE DONE 12/02/08 12/01/08 05/01/08 07/01/08 2,9 229,271 229,271 DDJ 0 0 0
FRA engineering & Architecture
#50 H.B.Montgomery K-5:
04-0649 Reconstruction 0-050-013 02/09/05 DONE DONE DONE 01/10/05 01/07/05 05/25/01 07/01/04 8 889,861 889,861 RDR 0 0 0
Harrison Bridges & Associates
06-0666 Reconstruction 0-050-018 04/02/07 DONE DONE DONE 12/27/06 12/22/06 03/30/06 07/01/06 8,10,13,15,16 227,761 227,761 MGL 0 0 4,555
HBMA Architecture Engineering & Land
- Reconstruction 0-050-019 / / / / 07/15/09 / / 7 0 0 DDJ 0 0 0
#52 F.F.Dow K-5:
04-0916 Reconstruction 0-052-015 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 75,010 75,010 RDR 0 0 0
TLC Engineering,P.C.
04-0453 Reconstruction 0-052-016 12/24/04 DONE DONE DONE 11/24/04 11/24/04 05/05/04 07/01/04 2,8,9,15,16 625,078 625,078 RDR 0 0 0
La Bella Associates
07-1477 Reconstruction 0-052-017 04/14/08 DONE DONE DONE 01/29/08 01/28/08 01/29/08 07/01/07 65,472 65,472 MGL 0 0 1,309
FRA engineering & Architecture
#57 Early Childhood Ctr.:
06-0639 Reconstruction 0-087-010 01/29/07 DONE DONE DONE 12/21/06 12/18/06 03/30/06 07/01/06 2,8,9,13,155,16 150,000 150,000 MGL 0 0 0
Terrence J. Costich
- Reconstruction 0-087-011 / / / / 09/21/09 / / 2,8 0 0 DDJ 0 0 0
Franklin HS 9-12:
04-0917 Reconstruction 0-101-024 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 95,599 95,599 RDR 0 0 0
TLC Engineering,P.C.
04-0838 Reconstruction 0-101-025 04/13/05 DONE DONE DONE 02/23/05 02/11/05 05/05/04 07/01/04 7,8,9,155,15,16 3,463,485 3,463,485 RDR 0 0 0
Miller- Anderson Architects
- Reconstruction 0-101-026 / / / / 08/01/05 / / 4,8,9,155,15,16 0 30,073,344 MGL 0 0 0
07-1525 Reconstruction 0-101-027 05/08/08 DONE DONE DONE 02/01/08 01/31/08 07/19/07 07/01/07 2,8,9,13,16 1,533,416 1,533,416 MGL 0 0 30,668
Miller- Anderson Architects
- Reconstruction 0-101-028 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Charlotte M.S. 6-8:
04-0918 Reconstruction 0-102-024 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 21,266,705 RDR 0 0 0
TLC Engineering,P.C.
05-0421 Reconstruction 0-102-025 04/06/06 DONE DONE DONE 12/07/05 12/05/05 07/28/05 07/01/05 9,10,155,15,16 707,256 707,256 RDR 0 0 14,145
Plan Architectural Studio, P.C.
07-1933 Reconstruction 0-102-026 05/13/08 DONE DONE DONE 04/08/08 03/31/08 07/20/07 07/01/07 7 300,000 0 DDJ 0 0 6,000
Design Group Educ. Fac. Dept.
08-0833 Reconstruction 0-102-027 02/02/09 DONE DONE DONE 12/02/08 12/01/08 05/01/08 07/01/08 8,9,10,13,155,16 583,608 583,608 DDJ 0 0 11,672
Smith+Associates Architects
- Reconstruction 0-102-028 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
- Reconstruction 0-102-029 / / / / 07/15/09 / / 7 0 0 DDJ 0 0 0
East High School 9-12:
04-1261 Reconstruction 0-103-024 05/19/05 DONE DONE DONE 05/11/05 05/04/05 04/08/05 07/01/04 2,9 280,983 280,983 RDR 0 0 0
Terrence J. Costich
05-0528 Reconstruction 0-103-025 03/31/06 DONE DONE DONE 01/03/06 12/30/05 07/28/05 07/01/05 2,4,9,155,15,16 1,561,758 1,561,758 RDR 0 0 29,836
CMA Architecture,P.C
07-1105 Reconstruction 0-103-026 02/14/08 DONE DONE DONE 12/12/07 12/11/07 07/20/07 07/01/07 155 550,633 550,633 MGL 0 0 11,013
Miller- Anderson Architects
08-0788 Reconstruction 0-103-027 01/07/09 DONE DONE DONE 11/24/08 11/24/08 05/01/08 07/01/08 2,9,10,155,16 1,708,476 1,708,476 DDJ 0 0 34,170
Clark Patterson Associates
- Reconstruction 0-103-028 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Jefferson M.S. 6-8:
05-0560 Reconstruction 0-105-022 04/07/06 DONE DONE DONE 01/17/06 01/09/06 08/01/05 07/01/05 2,4,8,9,155,15,16 1,664,257 1,664,257 RDR 0 0 33,285
M/E Engineering
07-1043 Reconstruction 0-105-023 01/08/08 DONE DONE DONE 12/05/07 12/03/07 10/23/07 07/01/07 16 98,683 98,683 MGL 0 0 1,974
IBC Engineering,P.C.
08-1000 Reconstruction 0-105-024 03/17/09 DONE DONE DONE 01/02/09 12/22/08 05/01/08 07/01/08 8,9,10,13,155,16 1,019,238 1,019,238 DDJ 0 0 20,385
Miller- Anderson Architects
- Reconstruction 0-105-025 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Monroe M.S. 6-8:
04-0919 Reconstruction 0-107-020 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 0 34,129,111 RDR 0 0 0
TLC Engineering,P.C.
04-0551 Reconstruction 0-107-021 03/16/05 DONE DONE DONE 12/15/04 12/13/04 05/05/04 07/01/04 2,4,9,15,16 3,766,304 3,766,304 RDR 0 0 0
Plan Architectural Studio, P.C.
06-1567 Reconstruction 0-107-022 06/25/07 DONE DONE DONE 06/04/07 06/04/07 04/04/07 07/01/06 9 125,374 125,374 MGL 0 0 0
Terrence J. Costich
07-1337 Reconstruction 0-107-023 03/17/08 DONE DONE DONE 01/07/08 01/04/08 07/20/07 07/01/07 2,4,8,9,10,13,16 169,240 169,240 MGL 0 0 3,385
CMA Architecture,P.C
- Reconstruction 0-107-024 / / / / 08/10/07 / / 13,16 0 0 MGL 0 0 0
Wilson HS 9-12:
06-0684 Reconstruction 0-108-019 03/19/07 DONE DONE DONE 12/28/06 12/27/06 03/30/06 07/01/06 2,9,13,155,15,16 744,504 744,504 MGL 0 0 14,890
CMA Architecture,P.C
- Reconstruction 0-108-020 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
- Reconstruction 0-108-021 / / / / 07/15/09 / / 2,8,9,10,13,155,15,1 0 0 DDJ 0 0 0
F. Douglass M.S. 6-8:
06-0797 Reconstruction 0-109-021 03/22/07 DONE DONE DONE 01/23/07 01/22/07 03/30/06 07/01/06 4,8,9,10,13,15,16 1,175,139 1,175,139 MGL 0 0 23,503
Hunt Engineers & Architects & Survey
07-0920 Reconstruction 0-109-022 02/13/08 DONE DONE DONE 11/23/07 11/21/07 07/20/07 07/01/07 2,8,9,155,15,16 2,436,126 2,436,126 MGL 0 0 48,723
EDGE Architecture
- Reconstruction 0-109-023 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
- Reconstruction 0-109-024 / / / / 07/15/09 / / 8,9,13,155,16 0 0 DDJ 0 0 0
Marshall HS 9-12:
04-0920 Reconstruction 0-110-027 03/28/05 DONE DONE DONE 03/09/05 03/07/05 04/22/04 07/01/04 16 63,247 63,247 RDR 0 0 0
TLC Engineering,P.C.
04-0547 Reconstruction 0-110-028 02/01/05 DONE DONE DONE 12/14/04 12/13/04 05/05/04 07/01/04 4,7,8,9,155,15,16 2,379,510 2,379,510 RDR 0 0 0
Plan Architectural Studio, P.C.
07-0944 Reconstruction 0-110-029 03/24/08 DONE DONE DONE 11/23/07 11/23/07 / / 07/01/07 4,7,8,9,155,15,16 468,304 468,304 MGL 0 0 9,366
Miller- Anderson Architects
- Reconstruction 0-110-030 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Edison Tech/Occ H.S. 9-12:
04-0821 Reconstruction 0-111-021 04/12/05 DONE DONE DONE 02/14/05 02/11/05 05/05/04 07/01/04 4,8,9,155,15,16 3,685,423 3,685,423 RDR 0 0 0
Miller- Anderson Architects
05-0785 Reconstruction 0-111-022 04/12/06 DONE DONE DONE 02/16/06 02/13/06 07/28/05 07/01/05 9,155,15,16 2,492,747 2,492,747 RDR 0 0 49,855
Miller- Anderson Architects
06-0655 Reconstruction 0-111-023 01/31/07 DONE DONE DONE 12/21/06 12/20/06 03/30/06 07/01/06 2,13,155,16 1,418,868 1,418,868 MGL 0 0 0
Miller- Anderson Architects
07-1044 Reconstruction 0-111-024 02/14/08 DONE DONE DONE 12/05/07 12/03/07 07/20/07 07/01/07 2,13,155,16 525,587 525,587 MGL 0 0 10,512
Miller- Anderson Architects
- Reconstruction 0-111-025 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
- Reconstruction 0-111-026 / / / / 07/15/09 / / 8,9,13,155,15,16 0 0 DDJ 0 0 0
1ofton SHS 9-12:
- Reconstruction 0-112-015 / / / / 07/20/07 / / 8,9,10,155,15,16 0 0 MGL 0 0 0
Service Station:
- XX Reconstruction 0-117-002 CANCELLED / / / / 12/29/04 / / 4,8,9,16 0 0 MGL 0 0 0
Modular Classroom:
- PR New Construction 0-178-001 / / / / 04/11/07 / / 02 - 16 0 0 MGL 0 0 0
Central Office:
- Reconstruction 1-053-010 / / / / 08/01/05 / / 4,7 0 0 MGL 0 0 0
- Reconstruction 1-053-011 / / / / 03/30/06 / / 7,8 0 0 MGL 0 0 0
- Reconstruction 1-053-012 / / / / 05/10/07 / / 15,16 0 0 MGL 0 0 0
Guard Station @ Transp.Dept.(Demolis:
- XX Reconstruction 1-171-002 CANCELLED / / / / 06/30/06 / / 2,10,155,16 0 0 MGL 0 0 0
Grounds Bldg-Quonset Hut:
06-0726 Reconstruction 2-080-002 04/19/07 DONE DONE DONE 01/10/07 01/08/07 09/21/06 07/01/05 2,10 44,608 0 MGL 0 0 0
Wendel Duchscherer
Maintenance Shed @ Carrol School:
08-1132 New Construction 3-180-001 03/04/09 DONE DONE DONE 01/27/09 01/16/09 12/02/08 07/01/08 02 - 16 70,000 0 DDJ 0 0 0
FRA engineering & Architecture
Adlai E. Stevenson-Maintenance Shed:
08-1301 New Construction 3-181-001 02/27/09 DONE DONE DONE 02/27/09 02/27/09 01/09/09 07/01/08 02 - 16 54,000 0 DDJ 0 0 0
Stantec Consulting Services Inc,.
Trans. Bldg. @ Service Center:
04-0648 Reconstruction 5-078-104 04/18/05 DONE DONE DONE 01/10/05 01/07/05 05/07/04 07/01/04 7 1,039,490 1,039,490 RDR 0 0 0
Terrence J. Costich
- XX Reconstruction 5-078-105 CANCELLED / / / / 08/01/05 / / 2 0 0 MGL 0 0 0
- XX Additions and Alterations 5-078-106 CANCELLED / / / / 03/30/06 / / 02 - 16 0 0 MGL 0 0 0
06-0727 Reconstruction 5-078-107 04/19/07 DONE DONE DONE 01/10/07 01/08/07 06/30/06 07/01/05 2,10,16 2,006,287 2,006,287 MGL 0 0 0
Wendel Duchscherer
Recreation Bldg:
05-0604 Reconstruction 7-058-001 04/10/06 DONE DONE DONE 01/18/06 01/09/06 07/27/05 07/10/05 2,4,8,9,15,16 504,438 504,438 RDR 0 0 0
CMA Architecture,P.C
06-0663 Reconstruction 7-059-001 02/09/07 DONE DONE DONE 12/27/06 12/22/06 09/22/06 07/01/06 2,8,10,13,155,15,16 359,600 0 MGL 0 0 0
CMA Architecture,P.C
- Reconstruction 7-059-002 / / / / 10/02/09 / / 4,7,8,9,155,15,16 0 0 DDJ 0 0 0
04-0701 Reconstruction 7-060-001 03/28/05 DONE DONE DONE 01/21/05 01/20/05 08/10/04 07/01/04 2,8,9,155,15,16 176,725 0 RDR 0 0 0
Terrence J. Costich
04-0582 Reconstruction 7-062-001 02/28/05 DONE DONE DONE 12/27/04 12/24/04 08/10/04 07/01/04 2,9,155,15,16 215,292 0 RDR 0 0 0
FJF Architects, LLP
R.I.S.E. Bldg.-Service Center:
06-0728XX Additions and Alterations 7-079-002 04/19/07 CANCELLED 01/10/07 01/08/07 06/30/06 07/01/05 02 - 16 1,151,000 0 MGL 0 0 0
Wendel Duchscherer
Svce. Ctr. Storehouse, Kitchen, Offi:
06-0729 Additions and Alterations 7-081-002 04/19/07 DONE DONE DONE 01/10/07 01/08/07 06/30/06 07/01/05 02 - 16 705,626 0 MGL 0 0 0
Wendel Duchscherer
Press Box@Marshall Ctr for Learning:
04-0548 Reconstruction 7-134-002 02/01/05 DONE DONE DONE 12/14/04 12/13/04 11/23/04 07/01/04 2,4,8,15,16 250,000 0 RDR 0 0 0
Plan Architectural Studio, P.C.
Baseball Press Box @ East HS:
- New Construction 7-172-001 / / / / 01/09/06 / / 02 - 16 0 0 MGL 0 0 0
Grounds Department Building:
06-0730 New Construction 7-174-001 04/19/07 DONE DONE DONE 01/10/07 01/08/07 07/10/06 07/01/05 02 - 16 3,182,932 0 MGL 0 0 0
Wendel Duchscherer
Field House @ Charlotte High School:
08-0834 New Construction 7-179-001 02/02/09 DONE DONE DONE 12/02/08 12/01/08 09/26/08 07/01/08 02 - 16 681,309 0 DDJ 0 0 0
Smith+Associates Architects
St. Simon's Terr. (Marritta):
- Reconstruction 8-057-002 / / / / 07/15/09 / / 2,8 0 0 DDJ 0 0 0
Rochester Bus. Institute-RBI Tutoria:
07-1544 Reconstruction 8-121-004 04/18/08 DONE DONE DONE 02/06/08 01/30/08 10/14/05 07/01/07 2,8,9,155,15,16 1,267,180 1,267,180 MGL 0 0 25,344
Design Group Educ. Fac. Dept.
- Reconstruction 8-121-005 / / / / 09/25/08 / / 2,16 0 0 DDJ 0 0 0
Sacred Heart School:
- TQ Temporary Quarters 8-173-001 / / / / 06/29/06 / / 0 0 MGL 0 0 0
Lease @ 690 St. Paul Street:
07-1440 Reconstruction 8-176-L01 01/29/08 DONE DONE DONE 01/25/08 01/25/08 02/27/07 03/27/08 13,875,000 12,129,779 MGL 0 0 0
Design Group Educ. Fac. Dept.
Purchase Former Rochester Charter Sc:
07-0916 New Construction 8-177-001 03/17/08 DONE DONE DONE 11/23/07 11/20/07 02/27/07 07/19/07 02 - 16 5,000,000 1,699,494 MGL 0 0 3,176,670
Design Group Educ. Fac. Dept.
I'm ready community learning center:
09-0375 Reconstruction 8-182-L01 11/13/09 DONE DONE DONE 10/30/09 10/29/09 05/27/09 06/24/09 657,587 657,587 DDJ 0 0 0
Design Group Educ. Fac. Dept.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Winslow Elementary School:
07-0757 Reconstruction 0-002-013 03/31/08 DONE DONE DONE 11/07/07 11/06/07 06/19/07 05/07/07 2,4,7,8,9,155,15,16 2,084,000 0 HCM 0 0 0
La Bella Associates
- Reconstruction 0-002-014 / / / / 08/14/09 / / 2,9,155,15,16 0 0 HCM 0 0 0
Roth Middle School:
06-0790 Reconstruction 0-003-021 04/20/07 DONE DONE DONE 01/19/07 01/10/07 09/02/05 12/13/05 2,4,7,8,9,155,15,16 4,200,000 2,256,267 HCM 0 0 0
La Bella Associates
- Reconstruction 0-003-022 / / / / 08/14/09 / / 2,4,8,9,10,155,15,16 0 0 HCM 0 0 0
07-2175SC Visual Structural Inspection 0-003-SC1 06/04/08 DONE DONE DONE 01/25/08 01/25/08 / / / / 16 3,931 0 JOD 0 0 0
Leary Elementary School:
08-0857 Additions and Alterations 0-005-016 05/14/09 DONE DONE DONE 12/04/08 12/02/08 06/11/08 05/07/08 02 - 16 3,000,000 610,000 HCM 0 0 0
La Bella Associates
Carlton Webster-Ninth Grade Academy:
07-0758 Reconstruction 0-006-013 03/31/08 DONE DONE DONE 11/07/07 11/06/07 06/19/07 05/07/07 2,4,8,9,155,15,16 464,000 464,000 HCM 0 0 0
La Bella Associates
- Reconstruction 0-006-014 / / / / 08/14/09 / / 2,7,8,155,15,16 0 0 HCM 0 0 0
07-2173SC Visual Structural Inspection 0-006-SC1 06/04/08 DONE DONE DONE 01/25/08 01/25/08 / / / / 16 2,500 0 JOD 0 0 0
Ethel K Fyle Elementary:
08-0858 Reconstruction 0-007-017 05/14/09 DONE DONE DONE 12/04/08 12/02/08 06/11/08 05/07/08 2,4,7,8,9,155,15,16 890,000 0 HCM 0 0 0
La Bella Associates
Emma Sherman Elementary:
07-0759 Reconstruction 0-008-014 03/31/08 DONE DONE DONE 11/07/07 11/06/07 11/20/06 05/07/07 2,4,7,8,9,155,15,16 1,174,000 1,174,000 HCM 0 0 0
La Bella Associates
David Crane Elementary:
04-1194 Reconstruction 0-009-016 04/26/05 DONE DONE DONE 04/25/05 04/19/05 03/03/05 05/31/02 7 855,012 855,012 HCM 0 0 0
La Bella Associates
07-0760 Reconstruction 0-009-017 03/31/08 DONE DONE DONE 11/07/07 11/06/07 11/20/06 05/07/07 2,4,7,8,9,155,15,16 324,000 324,000 HCM 0 0 0
La Bella Associates
Burger Middle School:
- PR Additions and Alterations 0-010-012 / / / / 09/02/05 / / 02 - 16 0 0 HCM 0 0 0
06-0791 Additions and Alterations 0-010-012 04/20/07 DONE DONE DONE 01/19/07 01/10/07 09/02/05 12/13/05 02 - 16 16,039,542 5,368,846 HCM 0 0 1,828,544
La Bella Associates
- Reconstruction 0-010-013 / / / / 10/05/09 / / 10 0 0 HCM 0 0 0
Rush Henrietta Sperry School:
- PR Additions and Alterations 0-011-024 / / / / 09/02/05 / / 02 - 16 0 0 HCM 0 0 0
05-1385 Reconstruction 0-011-025 05/10/06 DONE DONE DONE 06/19/06 06/19/06 04/06/06 05/17/05 155,15 121,454 121,454 HCM 0 0 0
M/E Engineering
06-1272 Reconstruction 0-011-026 02/22/08 DONE DONE DONE 04/04/07 04/04/07 11/20/06 12/13/05 2,4,8,9,155,15,16 2,997,000 2,997,000 HCM 0 0 0
La Bella Associates
06-1392SC Visual Structural Inspection 0-011-SC1 05/02/07 DONE DONE DONE 03/01/07 03/01/07 / / / / 16 4,000 0 JOD 0 0 0
07-2174SC Visual Structural Inspection 0-011-SC2 06/04/08 DONE DONE DONE 01/25/08 01/25/08 / / / / 16 13,666 0 JOD 0 0 0
New Administration Building:
07-0856 New Construction 1-023-001 05/05/08 DONE DONE DONE 11/20/07 11/19/07 04/10/07 / / 02 - 16 2,906,895 0 HCM 0 0 0
La Bella Associates
Erie Station Storage:
- New Construction 2-025-001 / / / / 08/25/09 / / 02 - 16 0 0 HCM 0 0 0
Guard House East @ Sperry HS:
06-1273 New Construction 7-021-001 02/22/08 DONE DONE DONE 04/04/07 04/04/07 01/24/07 12/13/05 02 - 16 30,500 0 HCM 0 0 0
La Bella Associates
Guard House West @ Sperry HS:
06-1274 New Construction 7-022-001 02/22/08 DONE DONE DONE 04/04/07 04/04/07 01/24/07 12/13/05 02 - 16 30,500 0 HCM 0 0 0
La Bella Associates
Church of the Good Shepard Elem.:
07-2264TQ Temporary Quarters 8-024-001 07/07/08 DONE DONE DONE 06/16/08 06/03/08 06/13/08 / / 0 0 HCM 0 0 0
La Bella Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
05-0267 Reconstruction 0-001-012 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,4,7,8,9,15,16 1,238,591 1,238,591 JOD 0 0 0
Konopka Architecture
06-0529 Reconstruction 0-001-013 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,7,8,9,155,16 408,003 127,300 JOD 0 0 51,000
Konopka Architecture
07-0264 Reconstruction 0-001-014 01/16/08 DONE DONE DONE 09/04/07 08/30/07 01/04/07 02/13/07 2,4,7,16 853,762 747,888 JOD 0 0 79,400
Konopka Architecture
E. Barclay Elementary School:
05-0268 Reconstruction 0-002-011 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,4,7,8,9,10,13,14,1 1,918,568 1,918,568 JOD 0 0 0
Konopka Architecture
06-0530 Reconstruction 0-002-012 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,8,9,16 134,749 172,455 JOD 0 0 16,844
Konopka Architecture
07-0265 Reconstruction 0-002-013 01/16/08 DONE DONE DONE 09/04/07 08/30/07 01/04/07 02/13/07 2,9,155,15,16 905,296 1,077,206 JOD 0 0 84,193
Konopka Architecture
J. Ginther Elementary:
05-0269 Reconstruction 0-004-010 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,8,155,15,16 448,443 448,443 JOD 0 0 0
Konopka Architecture
06-0531 Reconstruction 0-004-011 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,8,9,16 156,301 233,000 JOD 0 0 19,538
Konopka Architecture
07-0266 Reconstruction 0-004-012 01/16/08 DONE DONE DONE 09/04/07 08/30/07 01/04/07 02/13/07 2,4,8,9,10,155,15,16 397,644 367,154 JOD 0 0 36,981
Konopka Architecture
Senior High School:
05-0270 Reconstruction 0-007-019 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,4,9,10,155,15,16 2,596,362 2,596,362 JOD 0 0 0
Konopka Architecture
06-0532 Reconstruction 0-007-020 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,8,9,16 1,173,827 1,348,230 JOD 0 0 146,728
Konopka Architecture
07-0267 Reconstruction 0-007-021 01/16/08 DONE DONE DONE 09/04/07 08/30/07 01/04/07 02/13/07 2,4,7,8,9,10,155,15, 2,208,916 2,508,165 JOD 0 0 205,429
Konopka Architecture
Fred Hill Intermediate School:
05-0271 Reconstruction 0-010-012 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,7,8,9,155,15,16 969,320 969,320 JOD 0 0 0
Konopka Architecture
06-0533 Reconstruction 0-010-013 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,7,8,9,155,16 153,188 153,188 JOD 0 0 19,149
Konopka Architecture
07-0268 Reconstruction 0-010-014 01/16/08 DONE DONE DONE 09/04/07 08/30/07 01/04/07 02/13/07 7,8,9,16 499,479 742,987 JOD 0 0 46,451
Konopka Architecture
District Office Facility:
06-0534 Reconstruction 1-014-002 02/13/07 DONE DONE DONE 11/21/06 11/20/06 09/13/06 05/16/06 2,9,16 23,932 0 JOD 0 0 0
Konopka Architecture
New Storage Bldg.:
05-0272 Reconstruction 2-012-002 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2 79,641 0 JOD 0 0 0
Konopka Architecture
Buildings & Grounds Facility:
05-0273 Reconstruction 3-011-003 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2 79,641 0 JOD 0 0 0
Konopka Architecture
Bus Garage(see 1-003):
05-0274 Reconstruction 5-003-009 03/06/06 DONE DONE DONE 10/19/05 10/18/05 04/06/05 05/17/05 2,16 48,173 48,173 JOD 0 0 0
Konopka Architecture
09-0347 Reconstruction 5-003-010 DONE STARTED UNREVIEWED10/27/09 10/22/09 09/17/08 03/05/09 0 0 JOD 0 0 0
Konopka Architecture
Transporation Facility:
08-1674 New Construction 5-016-001 09/17/09 DONE DONE DONE 06/09/09 06/04/09 06/20/08 03/05/09 02 - 16 9,623,249 0 JOD 0 0 0
Konopka Architecture
Stadium Concession:
05-0829 New Construction 7-015-001 02/02/07 DONE DONE DONE 02/28/06 02/27/06 02/28/06 05/16/06 02 - 16 390,000 0 JOD 0 0 0
Konopka Architecture
New Press Box @ High School:
- PR New Construction 7-017-001 / / / / 05/14/09 / / 02 - 16 0 0 JOD 0 0 0
Districtwide:
09-0253 Reconstruction 7-999-001 10/01/09 DONE DONE DONE 09/22/09 09/21/09 05/14/09 05/19/09 16 140,000 0 JOD 0 0 0
Konopka Architecture
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Spry MS 7-9:
- PR Additions and Alterations 0-001-009 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0757 Additions and Alterations 0-001-009 05/23/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 3,263,861 3,263,861 JOD 0 0 0
Thomas Associates
07-0235 Reconstruction 0-001-010 04/17/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,9,10,155,15,16 1,952,399 0 JOD 0 0 0
Thomas Associates
Klem Road North Elementary:
- PR Additions and Alterations 0-003-007 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0758 Additions and Alterations 0-003-007 05/23/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 515,053 515,053 JOD 0 0 0
Thomas Associates
07-0230 Reconstruction 0-003-008 02/29/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,9,10,155,15,16 2,704,030 0 JOD 0 0 0
Thomas Associates
04-0234 Reconstruction 0-003-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 3,600 3,600 JOD 0 0 0
Plank Road North Elementary:
- PR Additions and Alterations 0-009-009 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0752 Additions and Alterations 0-009-009 05/17/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 802,800 802,800 JOD 0 0 0
Thomas Associates
07-0236 Reconstruction 0-009-010 04/17/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,9,10,155,15,16 4,931,488 0 JOD 0 0 0
Thomas Associates
04-0237 Reconstruction 0-009-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 3,600 3,600 JOD 0 0 0
Dewitt Road Elementary:
- PR Additions and Alterations 0-010-006 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0753 Additions and Alterations 0-010-006 05/17/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 635,653 635,653 JOD 0 0 0
Thomas Associates
07-0237 Reconstruction 0-010-007 04/17/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,7,8,9,155,15,16 608,690 0 JOD 0 0 0
Thomas Associates
04-0238 Reconstruction 0-010-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 3,600 3,600 JOD 0 0 0
Thomas MS 7-9:
- PR Additions and Alterations 0-011-019 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0754 Additions and Alterations 0-011-019 05/17/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 3,367,510 3,367,510 JOD 0 0 0
Thomas Associates
07-0238 Reconstruction 0-011-020 04/17/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,9,10,155,15,16 4,445,864 4,445,864 JOD 0 0 0
Thomas Associates
04-0611 Visual Structural Inspection 0-011-SC1 12/31/04 DONE DONE DONE 12/30/04 12/30/04 / / / / 16 23,932 23,932 JOD 0 0 0
State Road Elementary:
- PR Additions and Alterations 0-012-008 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0759 Additions and Alterations 0-012-008 05/23/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 466,578 466,578 JOD 0 0 0
Thomas Associates
07-0231 Reconstruction 0-012-009 02/29/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,10,155,15,16 2,643,945 0 JOD 0 0 0
Thomas Associates
04-0236 Reconstruction 0-012-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 3,600 3,600 JOD 0 0 0
Schroeder HS 10-12:
06-0755 Reconstruction 0-013-018 05/17/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 2,8,9,10,155,15,16 1,845,036 1,845,036 JOD 0 0 0
Thomas Associates
07-0219 Reconstruction 0-013-019 03/31/08 DONE DONE DONE 08/22/07 08/22/07 06/20/07 05/16/06 2,4,7,8,9,10,155,15, 13,530,261 13,530,261 JOD 0 0 2,802,422
Thomas Associates
04-0612SC Visual Structural Inspection 0-013-SC1 12/31/04 DONE DONE DONE 12/30/04 12/30/04 / / / / 16 23,932 23,932 JOD 0 0 0
Plank Road South Elementary:
- PR Additions and Alterations 0-016-005 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0756 Additions and Alterations 0-016-005 05/17/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 641,550 641,550 JOD 0 0 0
Thomas Associates
07-0232 Reconstruction 0-016-006 02/29/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,8,9,10,155,15,16 1,245,362 0 JOD 0 0 0
Thomas Associates
04-0233FP Reconstruction 0-016-FP2 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 3,600 3,600 JOD 0 0 0
Klem Road South Elementary:
- PR Additions and Alterations 0-017-005 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0760 Additions and Alterations 0-017-005 05/23/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 727,792 727,792 JOD 0 0 0
Thomas Associates
07-0233 Reconstruction 0-017-006 02/29/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,9,10,155,15,16 889,520 0 JOD 0 0 0
Thomas Associates
04-0232 Reconstruction 0-017-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 7,932 7,932 JOD 0 0 0
Schlegel Road Elementary:
- PR Additions and Alterations 0-018-005 / / / / 07/26/05 / / 02 - 16 0 0 JOD 0 0 0
06-0761 Additions and Alterations 0-018-005 05/23/07 DONE DONE DONE 01/12/07 01/11/07 07/26/05 05/16/06 02 - 16 715,175 715,175 JOD 0 0 0
Thomas Associates
07-0234 Reconstruction 0-018-006 02/29/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 2,4,8,10,155,15,16 1,271,421 0 JOD 0 0 0
Thomas Associates
04-0235 Reconstruction 0-018-FP1 12/23/04 DONE DONE DONE 09/16/04 / / / / / / 16 7,932 7,932 JOD 0 0 0
Maintenance Storage Building:
- Additions and Alterations 2-015-002 / / / / 09/28/05 / / 02 - 16 0 0 JOD 0 0 0
Storage Building #3 @ Schroeder High:
- PR New Construction 2-034-001 / / / / 01/21/09 / / 02 - 16 0 0 JOD 0 0 0
Thomas High School Storage Building:
- New Construction 2-035-001 / / / / 01/21/09 / / 02 - 16 0 0 JOD 0 0 0
New Maintenance Facility:
07-0239 New Construction 3-032-001 04/17/08 DONE DONE DONE 08/23/07 08/23/07 06/20/07 05/16/06 02 - 16 651,290 0 JOD 0 0 0
Thomas Associates
Bus Garage Annex:
- Reconstruction 5-007-004 / / / / 09/28/05 / / 2,7,8,9,155,15,16 0 0 JOD 0 0 0
New Bus Garage:
- Reconstruction 5-028-002 / / / / 09/28/05 / / 2,9 0 0 JOD 0 0 0
Fueling Station:
- New Construction 7-033-001 / / / / 11/14/07 / / 02 - 16 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Thomas J. Connor Elementary:
05-0445 Reconstruction 0-002-010 04/27/06 DONE DONE DONE 12/14/05 12/14/05 03/22/05 06/16/05 2,7,8,9,15,16 1,773,957 1,773,957 RDR 0 0 0
Thomas Associates
07-0562 Reconstruction 0-002-011 03/06/08 DONE DONE DONE 10/17/07 10/15/07 11/30/06 03/27/07 2,4,8,9,155,16 773,790 773,790 MGL 0 0 112,589
La Bella Associates
07-2191SC Visual Structural Inspection 0-002-SC1 09/26/08 DONE DONE DONE 03/04/08 03/04/08 / / / / 16 7,246 0 JOD 0 0 0
Junior Senior High School:
05-0446 Reconstruction 0-003-010 04/27/06 DONE DONE DONE 12/14/05 12/14/05 03/22/05 06/16/05 2,7,8,9,10,155,15,16 5,132,416 5,132,416 RDR 0 0 0
Thomas Associates
07-0563 Reconstruction 0-003-011 03/06/08 DONE DONE DONE 10/18/07 10/15/07 11/30/06 03/27/07 4,8,9,155,15,16 1,226,210 1,226,210 MGL 0 0 151,790
La Bella Associates
Bus Garage:
05-0447 Reconstruction 5-004-005 04/27/06 DONE DONE DONE 12/14/05 12/14/05 03/22/05 06/16/05 2,4,7,8,9,155,15,16 2,090,627 2,090,627 RDR 0 0 0
Thomas Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Forman Center (fmlyPhase1,2,3):
04-1152 Reconstruction 0-002-007 06/24/05 DONE DONE DONE 04/13/05 04/11/05 08/31/04 / / 155 149,149 149,149 MAC 0 0 0
Turner Engineering
- Reconstruction 0-002-008 / / / / 03/07/06 / / 2,9,155,16 0 23,763,780 JOD 0 0 0
05-1334 Reconstruction 0-002-009 07/11/06 DONE DONE DONE 06/07/06 06/06/06 04/06/06 / / 7 796,786 796,786 JOD 0 0 0
HBMA Architecture Engineering & Land
05-1335 Reconstruction 0-002-010 07/11/06 DONE DONE DONE 06/07/06 06/06/06 06/05/06 / / 7 45,463 45,463 JOD 0 0 0
HBMA Architecture Engineering & Land
07-1189 Reconstruction 0-002-011 10/08/08 DONE DONE DONE 12/24/07 12/19/07 09/06/07 / / 4,8,9,155,15,16 750,000 0 JOD 0 0 0
habza architecture
07-1471 Reconstruction 0-002-012 05/06/08 DONE DONE DONE 01/26/08 01/24/08 11/23/07 12/13/07 2,7,15 1,200,000 1,200,000 JOD 0 0 0
SWBR Architects P.C.
- PR Additions and Alterations 0-002-013 / / / / 03/04/09 / / 02 - 16 0 0 JOD 0 0 0
Vocational Bldg-Foreman Center:
05-1336 Reconstruction 0-003-005 07/11/06 DONE DONE DONE 06/07/06 06/06/06 04/27/06 / / 7 25,000 25,000 JOD 0 0 0
HBMA Architecture Engineering & Land
- PR Additions and Alterations 0-003-006 / / / / 03/04/09 / / 02 - 16 0 0 JOD 0 0 0
08-1666 Reconstruction 0-003-007 07/17/09 DONE DONE DONE 06/09/09 06/01/09 05/20/09 06/25/09 7 465,000 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
Theraputic Swimming Pool Forman:
- Reconstruction 0-004-001 / / / / 03/07/06 / / 7 0 0 JOD 0 0 0
05-1337 Reconstruction 0-004-002 07/11/06 DONE DONE DONE 06/07/06 06/06/06 04/27/06 / / 7 6,334 0 JOD 0 0 0
HBMA Architecture Engineering & Land
- PR Additions and Alterations 0-004-003 / / / / 03/04/09 / / 02 - 16 0 0 JOD 0 0 0
World Of Work Cottage:
04-1153 Reconstruction 0-008-002 06/24/05 DONE DONE DONE 04/13/05 04/11/05 08/31/04 / / 2,155 69,850 69,850 MAC 0 0 0
Turner Engineering
Main Cottage Rush:
04-1154 Reconstruction 0-009-002 06/24/05 DONE DONE DONE 04/13/05 04/11/05 08/31/04 / / 2,155 70,390 70,390 MAC 0 0 0
Turner Engineering
Staff Development Services:
03-0062TQ Temporary Quarters 7-038-001 01/20/06 DONE DONE DONE 07/16/03 / / 08/23/00 / / 0 0 MAC 0 0 0
Alternative HS/OConnor Rd.:
- PR Additions and Alterations 8-033-002 / / / / 03/04/09 / / 02 - 16 0 0 JOD 0 0 0
Technology Services:
06-0652TQ Temporary Quarters 8-040-001 01/02/07 DONE DONE DONE 12/21/06 12/21/06 / / / / 0 0 JOD 0 0 0
08-1129 Reconstruction 8-040-002 05/20/09 DONE DONE DONE 01/27/09 01/23/09 / / 12/11/08 9,155,16 328,800 0 JOD 0 0 0
Hunt Engineers & Architects & Survey
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
We-mo-co Bldg North:
04-0293 Reconstruction 0-001-014 02/22/05 DONE DONE DONE 10/20/04 10/13/04 12/18/03 09/15/04 2,4,7,8,9,10,13,14,1 2,789,567 2,789,567 MAC 0 0 0
La Bella Associates
07-2331 Reconstruction 0-001-015 02/17/09 DONE DONE DONE 07/08/08 06/23/08 12/26/07 06/18/08 2,4,7,8,9,10,155,15, 1,206,037 0 JOD 0 0 0
La Bella Associates
We-mo-co Bldg South:
04-0294 Reconstruction 0-002-018 02/22/05 DONE DONE DONE 10/20/04 10/13/04 12/18/03 09/15/04 2,7,8,9,155,15,16 271,754 271,754 MAC 0 0 0
La Bella Associates
07-2332 Reconstruction 0-002-019 02/17/09 DONE DONE DONE 07/08/08 06/23/08 12/26/07 06/18/08 2,7,9,155,15,16 316,963 0 JOD 0 0 0
La Bella Associates
ADL House:
07-2333 Reconstruction 0-013-003 02/17/09 DONE DONE DONE 07/08/08 06/23/08 12/26/07 06/18/08 16 23,276 0 JOD 0 0 0
La Bella Associates
Admin. Bldg.(Educ. Service Cntr.):
04-0295 Reconstruction 1-005-012 02/22/05 DONE DONE DONE 10/20/04 10/13/04 12/18/03 09/15/04 2,8,155,15,16 167,601 0 MAC 0 0 0
La Bella Associates
07-2334 Reconstruction 1-005-013 02/17/09 DONE DONE DONE 07/08/08 06/23/08 12/26/07 06/18/08 2,7,8,155,15,16 214,211 0 JOD 0 0 0
La Bella Associates
Spencerport Plaza #3:
07-1998TQ Temporary Quarters 1-043-001 05/13/08 DONE DONE DONE 04/18/08 04/18/08 01/28/02 / / 0 0 MAC 0 0 0
La Bella Associates
Paul Road Transition Program:
- XX Reconstruction 8-047-001 10/30/06 CANCELLED / / / / 07/19/05 / / 0 0 JOD 0 0 0
Monroe2 Orleans Boces:
05-0283TQ Temporary Quarters 8-048-001 08/29/06 DONE DONE DONE 10/24/05 10/18/05 10/21/05 / / 0 0 JOD 0 0 0
Paul Rd. Transition Center:
06-0373TQ Temporary Quarters 8-049-001 10/30/06 DONE DONE DONE 10/27/06 10/27/06 08/15/06 / / 0 0 JOD 0 0 0
Generations Child Care Incorporated:
- TQ Temporary Quarters 8-050-001 / / / / 12/19/07 / / 0 0 JOD 0 0 0
Greenhouse:
07-2335 Reconstruction 9-006-001 02/17/09 DONE DONE DONE 07/08/08 06/23/08 12/26/07 06/18/08 2,16 19,619 0 JOD 0 0 0
La Bella Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED