Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/24/08 at 08:56:29




SOUTH JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-01-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wilson Elementary:
  -       Reconstruction               0-001-008                                              /  /       /  /     05/30/07     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Gen. B.C.Clarke Jr/Sr High:
  -       Reconstruction               0-005-005                                              /  /       /  /     05/30/07     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Mannsville Elementary:
  -       Reconstruction               0-006-005                                              /  /       /  /     05/30/07     /  /     2,4,7,8,9,10,155,15,           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Clarke Maint Stor Bl:
  -       Reconstruction               2-007-001                                              /  /       /  /     05/31/07     /  /     8,9,15,16                      0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Adams Center Bus Garage:
  -       Additions and Alterations    5-002-005                                              /  /       /  /     05/30/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Press Box / Concession Building:
  -    DB Discovered Building          7-009-001                                              /  /       /  /     06/12/07     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Clarke Storage and Concesstion Stand:
  -       New Construction             7-010-001                                              /  /       /  /     07/17/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ALEXANDRIA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-02-02-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Alexandria Central:
05-0341   Reconstruction               0-001-010  06/16/06     DONE    DONE       DONE      11/14/05   11/07/05   07/20/05   07/14/05   2,155,15,16              830,621       830,621  JOD             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-0973   Reconstruction               0-001-011  06/26/08     DONE    DONE       DONE      11/28/07   11/27/07   05/01/07   04/03/07   2,4,7,8,9,10,13,14,1   2,175,000             0  JOD             0           0      213,746
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
05-0342   Reconstruction               0-004-002  06/16/06     DONE    DONE       DONE      11/14/05   11/07/05   07/21/05   07/14/05   16                        10,969        10,969  JOD             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-0974   Additions and Alterations    0-004-003  06/26/08     DONE    DONE       DONE      11/28/07   11/27/07   05/01/07   04/03/07   02 - 16                  285,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          New Greenhouse:
07-0975   New Construction             0-005-001  06/26/08     DONE    DONE       DONE      11/28/07   11/27/07   10/16/07   04/03/07   02 - 16                   40,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




INDIAN RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-03-01-06
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Antwerp Primary School:
04-0804   Reconstruction               0-001-010  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   2,4                       46,200        46,200  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2047   Reconstruction               0-001-011                         UNREVIEWED         05/01/08   04/24/08   06/22/07   10/17/07   2,4,7,8,9,155,15,16            0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Evans Mills Primary School:
04-0805   Reconstruction               0-004-013  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   2,4                       49,800        49,800  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2048   Reconstruction               0-004-014                         UNREVIEWED         05/01/08   04/24/08   06/22/07   10/17/07   2,4,7,8,9,155,15,16            0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Philadelphia Primary School:
04-0806   Reconstruction               0-005-010  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   2,4                       43,166        43,166  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2049   Reconstruction               0-005-011                         UNREVIEWED         05/01/08   04/24/08   06/22/07   10/17/07   2,4,8,9,155,15,16              0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Indian River High School:
04-0807   Reconstruction               0-007-014  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   2,4,7                     48,000        48,000  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
08-0072   Additions and Alterations    0-007-015                         UNREVIEWED         07/22/08   07/16/08   06/22/07   10/17/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Theresa Primary School:
04-0808   Reconstruction               0-008-009  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   2,4                       78,600        78,600  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2050   Reconstruction               0-008-010                         UNREVIEWED         05/01/08   04/24/08   06/22/07   10/17/07   2,7,8,9,155,16                 0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Indian River Middle 5-8):
04-0809   Reconstruction               0-010-009  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   4                        117,500       117,500  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2280   Reconstruction               0-010-010                         UNREVIEWED         07/01/08   06/13/08   06/22/07   10/17/07   4,7,8,9,10,155,15,16           0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Calcium Primary School:
04-0810   Reconstruction               0-027-006  03/08/05     DONE    DONE       DONE      02/10/05   02/09/05   02/26/04   05/18/04   4                         41,400        41,400  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2281   Additions and Alterations    0-027-008                         UNREVIEWED         07/01/08   06/13/08   06/22/07   10/17/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          New Grade 4-5 Building:
07-2103   Additions and Alterations    0-032-002                         UNREVIEWED         05/08/08   05/06/08   06/22/07   10/17/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Flammable Storage Bldg. @ Antwerp:
05-1172DB Discovered Building          2-039-001  03/26/07     DONE    DONE       DONE      04/18/06   03/30/06   05/24/04     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          District & Athletic Storage Bldg.:
05-1173DB Discovered Building          2-042-001  03/26/07     DONE    DONE       DONE      04/18/06   03/30/06   05/24/04     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Maintenance Storage Building:
05-1174DB Discovered Building          3-041-001  03/26/07     DONE    DONE       DONE      04/18/06   03/30/06   05/24/04     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               3-041-002                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Calcium Bus Garage:
07-2282   Reconstruction               4-009-005                         UNREVIEWED         07/01/08   06/13/08   06/22/07   10/17/07   2,14,155,16                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Bus Garage:
07-2051   Additions and Alterations    5-002-005                         UNREVIEWED         05/01/08   04/24/08   06/22/07   10/17/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          New Transportation Facility:
07-2104   Reconstruction               5-031-002                         UNREVIEWED         05/08/08   05/06/08   06/22/07   10/17/07   2,4,9,155,16                   0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-1899   Reconstruction               5-031-003  04/03/08     DONE    DONE       DONE      03/31/08   03/24/08   02/21/08   10/17/07   14,16                    125,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Well Pump House:
05-1175DB Discovered Building          7-040-001  03/26/07     DONE    DONE       DONE      04/18/06   03/30/06   05/24/04     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New Concession Stand:
08-0073   New Construction             7-043-001                         UNREVIEWED         07/22/08   07/16/08   04/10/08   10/17/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENERAL BROWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-04-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Brownville Glen Elementary:
  -       Reconstruction               0-001-003                                              /  /       /  /     01/22/07     /  /     2,4,7,8,9,155,15,16            0     4,296,400  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Dexter Elementary:
  -       Reconstruction               0-002-003                                              /  /       /  /     03/01/07     /  /     2,4,7,8,9,155,15,16            0     4,296,400  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          General Brown High:
  -       Reconstruction               0-003-003                                              /  /       /  /     01/22/07     /  /     2,4,7,8,9,155,15,16            0    15,355,530  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
  -       Reconstruction               0-010-003                                              /  /       /  /     01/22/07     /  /     2,4,7,8,9,155,15,16            0     8,990,217  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               5-004-003                                              /  /       /  /     01/22/07     /  /     2,4,7,8,9,155,15,16            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




THOUSAND ISLANDS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-07-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Guardino Elem. (fmly Clayton):
07-0108   Reconstruction               0-003-002  11/21/07     DONE    DONE       DONE      07/30/07   07/27/07   03/17/06   12/19/06   2,4,7,8,9,10,13,14,1   1,477,818             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0044   Reconstruction               0-003-003  04/09/08     DONE    DONE       DONE      07/12/07   07/11/07   01/10/07     /  /     7,155,16               1,271,228     1,271,228  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Cape Vincent Elem:
07-0109   Reconstruction               0-005-002  11/21/07     DONE    DONE       DONE      07/30/07   07/27/07   03/17/06   12/19/06   2,4,8,9,155,15,16        372,391             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0045   Reconstruction               0-005-003  04/09/08     DONE    DONE       DONE      07/12/07   07/11/07   01/10/07     /  /     7,8,155,16                39,556             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Junior Senior High:
03-1647   Reconstruction               0-011-005  07/06/04     DONE    DONE       DONE      06/24/04   06/22/04   03/17/04   03/16/04   2,15                     137,454       137,454  RDR             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
04-1378   Reconstruction               0-011-006  07/27/05     DONE    DONE       DONE      06/08/05   05/31/05   04/19/05   05/19/05   9,16                      53,308        53,308  RDR             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0110   Additions and Alterations    0-011-007  11/21/07     DONE    DONE       DONE      07/30/07   07/27/07   03/17/06   12/19/06   02 - 16                5,595,042             0  MGL             0           0      105,092
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0799   Reconstruction               0-011-008  02/01/07     DONE    DONE       DONE      01/23/07   01/22/07   03/17/06   12/19/06   2,7                    1,068,014     1,068,014  MGL             0           0      183,698
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0046   Reconstruction               0-011-009  04/09/08     DONE    DONE       DONE      07/12/07   07/11/07   01/10/07     /  /     7,155,16               1,271,228             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Bus Garage/Clayton:
07-0111   Reconstruction               5-001-005  11/21/07     DONE    DONE       DONE      07/30/07   07/27/07   03/17/06   12/19/06   2,4,7,8,9                103,988             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               5-001-006                                              /  /       /  /     01/10/07     /  /     7,8,155,16                     0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-0004   Reconstruction               5-001-007  07/24/07     DONE    DONE       DONE      07/03/07   07/02/07   05/25/07   12/19/06   15,16                     85,200             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Bus Garage @ Cape Vincent:
07-0112   Reconstruction               5-004-003  11/21/07     DONE    DONE       DONE      07/30/07   07/27/07   03/17/06   12/19/06   2,4,7,8,9                 32,500             0  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
06-0800   Reconstruction               5-004-004  02/01/07     DONE    DONE       DONE      01/23/07   01/22/07   03/17/06   12/19/06   2,4                       51,074        51,074  MGL             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               5-004-005                                              /  /       /  /     01/10/07     /  /     7,8,155,16                     0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELLEVILLE HENDERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-09-09-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 School:
  -       Reconstruction               0-010-003                                              /  /       /  /     03/02/04     /  /     15                             0    11,770,407  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-010-004                                              /  /       /  /     12/01/05     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage (Union):
  -       Reconstruction               5-003-002                                              /  /       /  /     03/02/04     /  /     15                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SACKETS HARBOR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-10-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Sackets Harbor Central:
07-0119   Reconstruction               0-001-007  02/29/08     DONE    DONE       DONE      08/01/07   08/01/07   10/07/05   12/06/06   2,4,7,8,9,10,155,15,   2,439,967     2,439,967  MGL             0           0      153,820
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-0326   Reconstruction               0-001-008  01/18/08     DONE    DONE       DONE      09/07/07   09/07/07   08/14/07   12/06/06   2,8,9,10,155,15,16     1,336,990             0  MGL             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LYME CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-13-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-0360   Reconstruction               0-002-004               DONE    DONE       ADD. REQ'D09/14/07   09/13/07   11/30/06   07/26/07   8,155,16                       0     9,814,284  MGL             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -    PR Additions and Alterations    0-002-005                                              /  /       /  /     01/16/08     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-002-006                                              /  /       /  /     03/14/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0892SC Visual Structural Inspection 0-002-SC1  02/07/07     DONE    DONE       DONE      01/26/07   01/26/07     /  /       /  /     16                         8,160         8,160  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
07-0361   Reconstruction               5-006-002               DONE    DONE       ADD. REQ'D09/14/07   09/13/07   11/30/06   07/26/07   8,155,16                       0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAFARGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-14-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
04-0023   Reconstruction               0-001-007  08/25/04     DONE    DONE       DONE      07/02/04   06/29/04   06/18/04   05/18/04   8,10                     112,979       112,979  JOD             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Additions and Alterations    0-001-008                                              /  /       /  /     01/22/07     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERTOWN CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-20-00-01
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Elementary:
03-1692   Reconstruction               0-010-004  07/26/04     DONE    DONE       DONE      07/01/04   06/30/04   06/18/04   05/18/04   9,14                      23,332        23,332  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
05-0863   Reconstruction               0-010-005  03/16/06     DONE    DONE       DONE      03/06/06   03/03/06   05/13/05   06/21/05   4,8,9,10,14,155,15,1   1,586,503     1,586,503  HCM             0           0       79,325
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Reconstruction               0-010-006                                              /  /       /  /     03/07/08     /  /     2,4,155,16                     0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Knickerbocker Elementary:
  -    PR Additions and Alterations    0-011-003                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0864   Additions and Alterations    0-011-003  03/16/06     DONE    DONE       DONE      03/06/06   03/03/06   05/13/05   06/21/05   02 - 16                1,244,592     1,239,490  HCM             0           0       62,230
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -    PR Additions and Alterations    0-011-004                                              /  /       /  /     03/07/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Sherman Elementary School:
  -    PR Additions and Alterations    0-012-003                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0865   Additions and Alterations    0-012-003  03/16/06     DONE    DONE       DONE      03/06/06   03/03/06   05/13/05   06/21/05   02 - 16                3,173,506     3,173,506  HCM             0           0      158,675
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Reconstruction               0-012-004                                              /  /       /  /     03/07/08     /  /     2,8,9,155,15,16                0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Watertown High School:
  -    PR Additions and Alterations    0-015-005                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0866   Additions and Alterations    0-015-005  03/16/06     DONE    DONE       DONE      03/06/06   03/03/06   05/13/05   06/21/05   02 - 16                1,990,909     1,990,909  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Reconstruction               0-015-006                                              /  /       /  /     02/05/07     /  /     16                             0    26,045,664  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-015-007                                              /  /       /  /     03/07/08     /  /     2,4,7,8,9,155,15,16            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0881SC Visual Structural Inspection 0-015-SC1  11/21/07     DONE    DONE       DONE      09/13/07   09/13/07     /  /       /  /     16                        48,025         7,121  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Ohio Street Elementary:
  -       Reconstruction               0-016-003                                              /  /       /  /     05/13/05     /  /     9,155,15,16                    0     5,800,140  HCM             0           0            0
                                                                                                                                                                                                                                                                     
06-1250   Reconstruction               0-016-004  06/29/07     DONE    DONE       DONE      04/02/07   04/02/07   02/05/07   06/21/05   2,9,155,15,16            376,187       376,187  HCM             0           0       18,809
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-2125PR Additions and Alterations    0-016-005                         UNREVIEWED         05/19/08   05/14/08   03/07/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Starbuck School:
07-0970   Reconstruction               0-017-003  05/20/08     DONE    DONE       DONE      11/28/07   11/27/07   11/21/07   11/19/07   2,4,7,8,9,10,155,15,   4,119,550             0  HCM             0           0      205,977
                                                                                                                                                                                                                                 Bernier Carr Associates             

          H.T.Wiley Elementary:
05-0867   Reconstruction               0-021-008  03/16/06     DONE    DONE       DONE      03/06/06   03/03/06   05/13/05   06/21/05   2,4,7,8,9,10,14,155,   7,962,692     7,962,692  HCM             0           0      398,135
                                                                                                                                                                                                                                 Bernier Carr Associates             
06-1462   Reconstruction               0-021-009  09/12/07     DONE    DONE       DONE      05/09/07   05/09/07   02/05/07   06/21/05   2,7,8,9,155,15,16        188,870             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
  -       Reconstruction               0-021-010                                              /  /       /  /     03/07/08     /  /     2,9,16                         0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New Middle School:
  -       Reconstruction               0-023-002                                              /  /       /  /     02/05/07     /  /     2                              0    22,139,888  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Field House:
03-0512   Reconstruction               7-004-001  06/02/04     DONE    DONE       DONE      10/28/03   10/14/03   09/24/03   10/27/98   4,7,9                     78,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CARTHAGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 22-22-01-06
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
03-1375   Reconstruction               0-001-009  05/02/04     DONE    DONE       DONE      04/09/04   04/08/04   02/04/04   03/16/04   2,7                    1,013,000     1,013,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
04-0378   Reconstruction               0-001-010  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/04/04   03/16/04   2,4,8,9,10,155,15,16   1,979,704     1,979,704  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
  -    PR Additions and Alterations    0-001-011                                              /  /       /  /     02/17/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0571   Additions and Alterations    0-001-011  03/09/07     DONE    DONE       DONE      11/30/06   11/29/06   02/17/06   05/16/06   02 - 16               18,083,000     6,872,000  JOD             0           0      360,000
                                                                                                                                                                                                                                 March Associates                    
  -       Reconstruction               0-001-012                                              /  /       /  /     11/15/06     /  /     8,16                           0    27,054,706  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Middle School:
04-0379   Reconstruction               0-002-004  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/04/04   03/16/04   2,8,9,10,155,15,16     1,407,460     1,407,460  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
  -    PR Additions and Alterations    0-002-005                                              /  /       /  /     02/21/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0572   Additions and Alterations    0-002-005  03/09/07     DONE    DONE       DONE      11/30/06   11/29/06   02/21/06   05/16/06   02 - 16               11,211,000    11,211,000  JOD             0           0      180,000
                                                                                                                                                                                                                                 March Associates                    

          Black River Elementary:
03-1376   Reconstruction               0-003-005  05/02/04     DONE    DONE       DONE      04/09/04   04/08/04   02/04/04   03/16/04   2,7                      499,946       499,946  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
04-0380   Reconstruction               0-003-006  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/04/04   03/16/04   2,4,8,9,10,155,15,16     355,330       355,330  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Great Bend Grade School:
04-0381   Reconstruction               0-008-004  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/05/04   03/16/04   155,15,16                105,830       105,830  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
05-0702   Reconstruction               0-008-005  05/23/06     DONE    DONE       DONE      02/10/06   02/01/06   10/19/05   05/17/05   7                        113,500       113,500  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-2338   Reconstruction               0-008-006                         UNREVIEWED         07/08/08   06/24/08   05/03/07   03/16/04   2,16                           0             0  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Carthage Elementary:
03-1377   Reconstruction               0-012-005  05/02/04     DONE    DONE       DONE      04/09/04   04/08/04   02/04/04   03/16/04   7                        140,000       140,000  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    
04-0382   Reconstruction               0-012-006  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/04/04   03/16/04   2,4,8,9,10,155,15,16     230,840       230,840  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Pole Barn:
06-0573   Reconstruction               3-006-002  03/09/07     DONE    DONE       DONE      11/30/06   11/29/06   11/15/06   05/16/06   2,7,8,9,10,155,15,16     230,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Bus Garage:
04-0383   Reconstruction               5-005-003  01/14/05     DONE    DONE       DONE      11/09/04   11/08/04   02/05/04   03/16/04   2                        392,816       392,816  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Districtwide:
04-0384   Reconstruction               7-999-001  12/28/04     DONE    DONE       DONE      11/09/04   11/08/04   02/05/04   03/16/04   16                       179,020       179,020  JOD             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED