Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/19/09 at 17:00:03




WEST CANADA VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-03-02-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr. Sr. High School And Additions:
04-0523   Reconstruction               0-003-006  02/04/05     DONE    DONE       DONE      12/10/04   12/07/04   08/06/04   05/18/04   16                        65,284        65,284  MAC             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P
06-0380   Additions and Alterations    0-003-007  02/21/07     DONE    DONE       DONE      10/30/06   10/24/06   08/06/04   07/07/05   02 - 16                3,619,200     3,619,200  MAC             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P
05-0179   Reconstruction               0-003-008  10/26/05     DONE    DONE       DONE      09/08/05   09/08/05   07/19/05   05/17/05   8,10,13,16                83,023        83,023  HCM             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P
  -    XX Reconstruction               0-003-009                         CANCELLED            /  /       /  /     07/25/05     /  /     8,10,13                        0    17,163,624  HCM             0           0            0
                                                                                                                                                                                                                                                                     
06-0713   Reconstruction               0-003-010  01/19/07     DONE    DONE       DONE      01/08/07   01/05/07   07/17/06   05/17/06   16                        99,966        99,966  HCM             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P
07-1473   Reconstruction               0-003-012  04/15/08     DONE    DONE       DONE      01/26/08   01/24/08   06/05/07   12/10/07   15                       100,000       100,000  HCM             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
08-0991   Reconstruction               0-003-013  08/14/09     DONE    DONE       DONE      01/02/09   12/18/08   12/11/07   06/12/07   2,4,7,8,9,14,155,15,   6,159,000     6,159,000  HCM             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
08-1682SC Visual Structural Inspection 0-003-SC1  06/18/09     DONE    DONE       DONE      06/17/09   06/17/09     /  /       /  /     16                         8,755             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          High School Bus Garage:
06-0381   Reconstruction               5-005-003  02/21/07     DONE    DONE       DONE      10/30/06   10/24/06   08/06/04   07/07/05   8,9,155,15,16            520,800       520,800  MAC             0           0            0
                                                                                                                                                                                                                                 Glynn Spillane Griffing Architests,P
08-0872   Reconstruction               5-005-004  05/06/09     DONE    DONE       DONE      12/05/08   12/04/08     /  /     05/20/08   2,7,8                     99,991       100,000  HCM             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRANKFORT-SCHUYLER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-04-02-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior-Senior High School:
07-1466   Reconstruction               0-001-011  10/30/08     DONE    DONE       DONE      01/26/08   01/24/08   03/05/07   06/14/07   4,8,10,155,15,16       1,768,699     1,446,685  DDJ             0           0      372,054
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    

          Reese Road Elementary School:
07-1467   Reconstruction               0-002-010  10/30/08     DONE    DONE       DONE      01/26/08   01/24/08   03/05/07   06/14/07   2,8,13,155,16          1,060,169     1,060,169  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    

          West Frankfort Elem. School:
07-1468   Reconstruction               0-006-009  10/30/08     DONE    DONE       DONE      01/26/08   01/24/08   03/05/07   06/14/07   2,4,8,13,155,15,16       807,470       807,470  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
06-1393SC Visual Structural Inspection 0-006-SC1  05/02/07     DONE    DONE       DONE      02/26/07   02/26/07     /  /       /  /     16                         2,995             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Equipment Storage @ Athletic Field:
07-1469   New Construction             2-012-001  10/30/08     DONE    DONE       DONE      01/26/08   01/24/08   11/16/07   06/14/07   02 - 16                   63,662             0  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ILION CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-05-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
08-1750   Reconstruction               0-001-005  10/21/09     DONE    DONE       DONE      06/29/09   06/23/09   10/03/07   05/20/08   2,4,7,8,9,10,13,14,1  14,465,900             0  HCM             0           0      289,318
                                                                                                                                                                                                                                 King & King, Architects             

          Barringer Rd. Elem.:
  -    XX Reconstruction               0-006-003                         CANCELLED            /  /       /  /     08/03/06     /  /     9                              0     6,572,135  MGL             0           0            0
                                                                                                                                                                                                                                                                     
08-1751   Reconstruction               0-006-004  10/21/09     DONE    DONE       DONE      06/29/09   06/23/09   10/03/07   05/20/08   2,4,7,8,9,10,155,15,   5,330,900             0  MGL             0           0      126,075
                                                                                                                                                                                                                                 King & King, Architects             

          Remington Elementary:
08-1752   Reconstruction               0-007-007  10/21/09     DONE    DONE       DONE      06/29/09   06/23/09   10/03/07   05/20/08   2,4,7,8,10,155,15,16   4,751,200             0  MGL             0           0       95,024
                                                                                                                                                                                                                                 King & King, Architects             

          Vehicle Garage:
  -       Reconstruction               7-002-001                                              /  /       /  /     10/03/07     /  /     4,7,8,155,15,16                0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Pressbox:
09-0367   New Construction             7-009-001  11/02/09     DONE    DONE       DONE      10/29/09   10/28/09   09/24/09   05/02/08   02 - 16                   71,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 King & King Architects              


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MOHAWK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-05-02-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School Building:
07-1300   Additions and Alterations    0-001-006  08/29/08     DONE    DONE       DONE      01/02/08   12/28/07   12/18/06   05/15/07   02 - 16                3,714,737     3,714,737  MGL             0           0       74,295
                                                                                                                                                                                                                                 King & King, Architects             
07-1301   Additions and Alterations    0-001-007  08/29/08     DONE    DONE       DONE      01/02/08   12/28/07   12/18/06   05/15/07   02 - 16                1,491,717     1,491,717  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          Fisher Elem School:
07-1302   Additions and Alterations    0-002-004  08/29/08     DONE    DONE       DONE      01/02/08   12/28/07   12/18/06   05/15/07   02 - 16                5,180,784     5,139,284  MGL             0           0      103,616
                                                                                                                                                                                                                                 King & King, Architects             
  -    PR Additions and Alterations    0-002-005                                              /  /       /  /     12/18/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage Bldg 1:
07-1303   Reconstruction               5-003-003  08/29/08     DONE    DONE       DONE      01/02/08   12/28/07   12/18/06   05/15/07   4,8,9                     57,262        57,262  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          New Bus Garage:
  -       Reconstruction               5-015-002                                              /  /       /  /     12/18/06     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Press Box:
07-1304   New Construction             7-016-001  08/29/08     DONE    DONE       DONE      01/02/08   12/28/07   10/16/07   05/15/07   02 - 16                   55,500             0  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HERKIMER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-06-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Senior High School:
07-1294   Reconstruction               0-001-005  08/20/08     DONE    DONE       DONE      01/02/08   12/28/07   11/21/06   05/15/07   2,4,7,8,9,10,155,15,   3,113,851     3,113,851  HCM             0           0      130,782
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-001-006                                              /  /       /  /     11/21/06     /  /     2,4,7,8,9,155,15,16            0    14,147,258  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-001-007                                              /  /       /  /     11/19/09     /  /     2,4,8,9,155,15,16              0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Herkimer Elementary:
07-1295   Reconstruction               0-006-003  08/20/08     DONE    DONE       DONE      01/02/08   12/28/07   11/21/06   05/15/07   2,4,7,8,9,10,155,15,   6,506,228     6,223,470  HCM             0           0      273,262
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-006-004                                              /  /       /  /     11/21/06     /  /     2,4,7,8,9,10,155,15,           0    12,389,691  HCM             0           0            0
                                                                                                                                                                                                                                                                     
08-1585   Reconstruction               0-006-005  07/02/09     DONE    DONE       DONE      05/05/09   04/27/09   01/26/09   05/15/07   2,8                      365,000             0  HCM             0           0       15,330
                                                                                                                                                                                                                                 King & King Architects              
  -       Reconstruction               0-006-006                                              /  /       /  /     11/19/09     /  /     2,9,155,15,16                  0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
07-1296   Reconstruction               5-009-002  08/20/08     DONE    DONE       DONE      01/02/08   12/28/07   11/28/06   05/15/07   2,4,7,8,9,155,15,16      379,921       379,921  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LITTLE FALLS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-08-00-05
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Benton Hall Elementary:
07-2026   Reconstruction               0-001-010  11/04/08     DONE    DONE       DONE      04/25/08   04/17/08   11/30/06   07/11/07   2,8,9,155,15,16        2,106,537     2,686,000  MGL             0           0      103,220
                                                                                                                                                                                                                                 SYTHESIS ARCHITECTS                 

          Middle School/High School:
07-2027   Reconstruction               0-008-012  11/04/08     DONE    DONE       DONE      04/25/08   04/17/08   11/30/06   07/11/07   2,8,9,155,15,16        4,393,463     3,814,000  MGL             0           0      215,280
                                                                                                                                                                                                                                 SYTHESIS ARCHITECTS                 

          School Bus Garage:
  -    PR Additions and Alterations    5-003-002                                              /  /       /  /     12/26/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          HS Athl. Storage/Restrooms:
  -       New Construction             7-010-002                                              /  /       /  /     12/26/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOLGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-10-03-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James A Green School:
07-0485   Reconstruction               0-001-013  04/10/08     DONE    DONE       DONE      10/03/07   10/02/07   09/20/05   04/17/07   2,4,7,8,9,10,13,155,   7,000,000     5,112,000  HCM             0           0      140,000
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




POLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-11-03-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
05-0200   Reconstruction               0-002-016  04/07/06     DONE    DONE       DONE      09/19/05   09/15/05   07/26/05   07/14/05   8,155,16                 409,988       409,988  RDR             0           0            0
                                                                                                                                                                                                                                                                     
06-1435   Reconstruction               0-002-017  05/14/07     DONE    DONE       DONE      05/07/07   05/07/07   04/20/07   01/17/07   7                        600,000       600,000  MGL             0           0      191,400
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-0798   Reconstruction               0-002-018  04/18/08     DONE    DONE       DONE      11/14/07   11/13/07     /  /     01/17/07   2,4,8,9,10,155,15,16   1,222,000     1,222,000  MGL             0           0      389,818
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Bus Storage Garage:
05-0201   Reconstruction               4-001-005  04/07/06     DONE    DONE       DONE      09/19/05   09/15/05   07/26/05   07/14/05   155,16                    52,446        52,446  RDR             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




VAN HORNESVILLE-OWEN D YOUNG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-17-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Main Building:
08-1661   Reconstruction               0-001-010                       ADDENDUM REQ'D       06/08/09   06/01/09   12/29/06   10/11/06   15                             0     4,253,325  HCM             0           0            0
                                                                                                                                                                                                                                 TDK Engineering Associates          
07-1151   Reconstruction               0-001-011  06/23/08     DONE    DONE       DONE      12/18/07   12/17/07   03/27/07   05/15/07   4,7,8,10,155,16        1,055,000     1,055,000  HCM             0           0       88,620
                                                                                                                                                                                                                                 McDonald & Monterose LLP            
  -       Reconstruction               0-001-012                                              /  /       /  /     06/01/09     /  /     15                             0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TOWN OF WEBB UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-19-01-02
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
06-0331   Reconstruction               0-001-012  01/17/07     DONE    DONE       DONE      10/18/06   10/17/06   07/25/06   05/16/06   2,4,8,9                  100,000       100,000  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
06-0332   Reconstruction               0-001-013  01/17/07     DONE    DONE       DONE      10/18/06   10/17/06   07/25/06   05/16/06   2,7                      295,000       295,000  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
07-0362   Reconstruction               0-001-014  01/07/08     DONE    DONE       DONE      09/14/07   09/14/07   02/12/07   02/06/07   16                        64,903        64,903  HCM             0           0       57,763
                                                                                                                                                                                                                                 March Associates                    
00-0000PR Reconstruction               0-001-015                                              /  /       /  /     02/20/07     /  /     8                              0     7,699,610  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-1439   Reconstruction               0-001-015  03/10/08     DONE    DONE       DONE      01/24/08   01/22/08   02/12/07   05/15/07   7,16                     300,000       300,000  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    
08-1096   Reconstruction               0-001-016  06/11/09     DONE    DONE       DONE      01/21/09   01/12/09   02/28/08   03/04/08   2,4,7,8,9,155,16          60,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Industrial Art Bld:
07-0363   Reconstruction               0-004-005  01/07/08     DONE    DONE       DONE      09/14/07   09/14/07   02/12/07   02/06/07   16                        56,000        56,000  HCM             0           0       56,000
                                                                                                                                                                                                                                 March Associates                    

          New Storage Building (Pole Barn):
08-1097   New Construction             2-010-001  06/11/09     DONE    DONE       DONE      01/21/09   01/12/09   02/28/08   03/04/08   02 - 16                  140,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    

          Bus Garage:
07-0364   Reconstruction               5-005-004  01/07/08     DONE    DONE       DONE      09/14/07   09/14/07   02/12/07   02/06/07   16                         5,500             0  HCM             0           0            0
                                                                                                                                                                                                                                 March Associates                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MT. MARKHAM CSD (FMLYBRIDGWTRWWINFIE STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-20-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          W. Winfield Middle School:
04-1318   Reconstruction               0-001-008  07/27/05     DONE    DONE       DONE      05/24/05   05/13/05   05/21/04   05/11/04   2,15,16                   40,449        40,449  MAC             0           0            0
                                                                                                                                                                                                                                 SMSA Architectural Services         
07-1086   Reconstruction               0-001-009  06/27/08     DONE    DONE       DONE      12/11/07   12/10/07   01/12/07   03/20/07   2,4,7,8,9,10,155,15,   5,345,644     5,241,325  MGL             0           0      106,900
                                                                                                                                                                                                                                 King & King, Architects             

          W. Winfield Elementary:
04-1319   Reconstruction               0-004-007  07/27/05     DONE    DONE       DONE      05/24/05   05/13/05   05/21/04   05/11/04   2,15,16                   41,554        41,554  MAC             0           0            0
                                                                                                                                                                                                                                 SMSA Architectural Services         
07-1087   Reconstruction               0-004-008  06/27/08     DONE    DONE       DONE      12/11/07   12/10/07   01/12/07   03/20/07   2,4,7,8,9,10,13,155,   4,283,059     4,283,059  MGL             0           0       85,660
                                                                                                                                                                                                                                 King & King, Architects             

          Leonardsville Elementary:
04-1320   Reconstruction               0-007-008  07/27/05     DONE    DONE       DONE      05/24/05   05/13/05   05/21/04   05/11/04   2,15,16                   11,450        11,450  MAC             0           0            0
                                                                                                                                                                                                                                 SMSA Architectural Services         
07-1088   Reconstruction               0-007-009  06/27/08     DONE    DONE       DONE      12/11/07   12/10/07   01/12/07   03/20/07   2,4,7,8,9,10,155,15,     558,554       586,787  MGL             0           0       11,140
                                                                                                                                                                                                                                 King & King, Architects             

          Mt. Markham Sr. High:
04-1321   Reconstruction               0-011-008  07/27/05     DONE    DONE       DONE      05/24/05   05/13/05   05/21/04   05/11/04   2,15,16                   39,899        39,899  MAC             0           0            0
                                                                                                                                                                                                                                 SMSA Architectural Services         
07-1089   Reconstruction               0-011-009  06/27/08     DONE    DONE       DONE      12/11/07   12/10/07   01/12/07   03/20/07   2,4,7,8,9,10,155,15,   9,315,931     9,303,921  MGL             0           0      186,300
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
04-1322   Reconstruction               5-009-008  07/27/05     DONE    DONE       DONE      05/24/05   05/13/05   05/21/04   05/11/04   2,15,16                   32,899        32,899  MAC             0           0            0
                                                                                                                                                                                                                                 SMSA Architectural Services         
07-1090   Reconstruction               5-009-009  06/27/08     DONE    DONE       DONE      12/11/07   12/10/07   01/12/07   03/20/07   2,4,7,8,9,10,155,15,   1,566,812     1,566,812  MGL             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             

          New Concession Stand:
02-0469DB Discovered Building          7-012-001  09/14/09     DONE    DONE       DONE      10/28/02     /  /     03/15/96     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES HERK-FULTON-HAMLT-OTSGO STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-90-00-00
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Busacker Educational Complex:
03-1542   Reconstruction               0-007-014  12/23/04     DONE    DONE       DONE      05/12/04   05/10/04   02/11/00   02/23/04   2,8,155,16             2,037,907     2,037,907  MAC             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
06-1607   Reconstruction               0-007-015  07/13/07     DONE    DONE       DONE      06/13/07   06/07/07   12/21/06   06/14/07   8,16                      83,850        83,850  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
  -       Reconstruction               0-007-016                                              /  /       /  /     05/01/08     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
08-1655   Reconstruction               0-007-017  06/25/09     DONE    DONE       DONE      06/01/09   05/21/09   04/08/09   04/23/09   155,16                   468,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 King & King Architects              

          Faxton- St. Lukes:
  -    TQ Temporary Quarters           8-018-001                                              /  /       /  /     08/02/07     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED