Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/25/08 at 08:59:58




WHEELERVILLE UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-03-01-02
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wheelerville School:
04-1348   Reconstruction               0-002-003  05/27/05     DONE    DONE       DONE      05/31/05   05/27/05   03/10/03   03/09/05   4,7,9,155,16             432,623       432,623  DDJ             0           0            0
                                                                                                                                                                                                                                 Sacco & McKinney Architects, PC     
  -       Reconstruction               0-002-004                                              /  /       /  /     11/15/06     /  /     2,8,9,10,155,16                0     3,439,809  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -    PR Additions and Alterations    5-003-003                                              /  /       /  /     11/15/06     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GLOVERSVILLE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-05-00-01
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Boulevard School:
05-0174   Reconstruction               0-004-007  02/07/06     DONE    DONE       DONE      09/06/05   09/06/05   10/02/03   02/03/04   2,4,7,8,9,14,155,15,   8,839,113     8,131,863  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
02-2091FP Reconstruction               0-004-FP1  10/02/03     DONE    DONE       DONE      05/05/03     /  /       /  /       /  /     16                         6,800         6,000  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          McNab School:
07-0464   Reconstruction               0-007-006  01/29/08     DONE    DONE       DONE      10/01/07   09/28/07   10/02/03   02/03/04   2,4,7,8,9,14,155,15,   5,949,100             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Park Terrace Elem.:
05-0175   Reconstruction               0-009-007  02/07/06     DONE    DONE       DONE      09/06/05   09/06/05   10/02/03   02/03/04   2,4,7,8,9,14,155,15,   8,666,393     5,469,170  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          High School:
04-1103   Additions and Alterations    0-010-013  05/24/05     DONE    DONE       DONE      04/06/05   04/05/05   10/02/03   02/03/04   02 - 16               23,699,228    21,077,462  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
04-0896   Reconstruction               0-010-014  03/24/05     DONE    DONE       DONE      03/07/05   03/04/05   01/28/05   02/03/04   2,10                     290,595       290,595  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1955   Additions and Alterations    0-010-015                         UNREVIEWED         04/14/08   04/03/08   08/09/07   02/08/07   02 - 16                        0    31,378,048  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
02-2090FP Reconstruction               0-010-FP1  10/02/03     DONE    DONE       DONE      05/05/03     /  /       /  /       /  /     16                        10,900        10,900  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Meco Elementary School:
07-0465   Reconstruction               0-014-006  01/29/08     DONE    DONE       DONE      10/01/07   09/28/07   10/02/03   02/03/04   2,4,7,8,9,14,155,15,   4,178,900             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
05-0672   Reconstruction               0-014-007  02/08/06     DONE    DONE       DONE      02/07/06   02/07/06   01/19/06   02/03/04   7                         24,500        24,500  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Kingsborough Elementary:
07-0466   Reconstruction               0-015-008  01/29/08     DONE    DONE       DONE      10/01/07   09/28/07   10/02/03   02/03/04   2,4,7,8,9,14,155,15,   6,204,700             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Middle School:
03-0925   Reconstruction               0-019-003  06/09/04     DONE    DONE       DONE      01/02/04   12/24/03   10/12/00   03/05/01   2,4,8,9,10,155,15,16   1,718,909     1,718,909  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
03-0926XX Reconstruction               0-019-004                         CANCELLED          01/02/04   12/24/03   10/02/03   03/05/01   2,4,7,8,9,14,155,15,           0    27,738,063  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
04-1104   Reconstruction               0-019-005  05/24/05     DONE    DONE       DONE      04/06/05   04/05/05   05/03/04   02/03/04   2,4,7,8,9,155,15,16    2,726,234     2,726,234  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1956   Alterations                  0-019-006                         UNREVIEWED         04/14/08   04/03/08   04/14/08   02/08/07                                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
02-2089FP Reconstruction               0-019-FP1  10/02/03     DONE    DONE       DONE      05/05/03     /  /       /  /       /  /     16                         4,800         4,800  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Storage/Utility Building:
03-1116   New Construction             2-026-001  06/09/04     DONE    DONE       DONE      02/13/04   02/13/04   11/13/03   03/05/01   02 - 16                   38,600             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Storage Bldg. @ Middle School:
04-1105XX New Construction             2-029-001  05/24/05               CANCELLED          04/06/05   04/05/05   03/30/05   02/03/04   02 - 16                   55,000             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Bus Garage (lease):
05-0045   Reconstruction               5-024-L02  07/01/02     DONE    DONE       DONE      07/15/05   07/14/05   07/11/05     /  /                               12,000        12,000  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0046   Reconstruction               5-024-L03  07/01/03     DONE    DONE       DONE      07/15/05   07/14/05   07/11/05     /  /                               30,000        30,000  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
05-0047   Reconstruction               5-024-L04  07/13/04     DONE    DONE       DONE      07/15/05   07/14/05   07/11/05   06/07/04                             30,000        30,000  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Maintenance Facility:
04-0197   New Construction             5-025-001  10/21/04     DONE    DONE       DONE      09/09/04   09/08/04   07/16/02   02/03/04   02 - 16                8,807,394     8,807,394  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Pumphouse-Middle School:
06-1124   Additions and Alterations    7-020-002  07/27/07     DONE    DONE       DONE      03/19/07   03/09/07   12/18/06   02/03/04   02 - 16                  314,200             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          New Press Box @ High School:
04-1106   New Construction             7-027-001  05/24/05     DONE    DONE       DONE      04/06/05   04/05/05   10/08/04   02/03/04   02 - 16                   52,775             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Press Box @ Park Terrace:
05-0176   New Construction             7-028-001  02/07/06     DONE    DONE       DONE      09/06/05   09/06/05   10/08/04   02/03/04   02 - 16                   64,500             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Districtwide:
  -       Reconstruction               7-999-001                                              /  /       /  /     05/03/04     /  /     16                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               7-999-002                                              /  /       /  /     04/06/05     /  /     16                             0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




JOHNSTOWN CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-06-00-01
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Warren Street School:
05-0837   Reconstruction               0-003-005  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   03/15/05   10/04/05   2,13                     283,173       462,545  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             

          Knox Junior High School:
05-0838   Reconstruction               0-006-004  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/17/05   10/04/05   2,155,16               2,501,889     3,220,416  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             

          Pleasant Ave. School:
05-0839   Reconstruction               0-007-009  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/17/05   10/04/05   7,155                     92,242       140,786  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             
  -       Reconstruction               0-007-010                                              /  /       /  /     09/12/05     /  /     13,15                          0     6,228,428  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Senior High School:
  -    PR Additions and Alterations    0-009-006                                              /  /       /  /     02/17/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
05-0840   Additions and Alterations    0-009-006  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/17/05   10/04/05   02 - 16                8,793,812     5,590,951  RDR             0           0    1,531,536
                                                                                                                                                                                                                                 Bonacci Architects pllc             
  -       Reconstruction               0-009-007                                              /  /       /  /     10/07/05     /  /     2,4,13,155                     0    12,284,424  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Glebe Street Elem.:
05-0841   Reconstruction               0-010-005  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/17/05   10/04/05   2,7,155,16               257,570       388,339  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             

          Jansen Avenue Elem. School:
05-0842   Reconstruction               0-011-003  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/17/05   10/04/05   2,7,155,16               262,837       429,070  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             

          Warehouse ABCD-Transportation Fac.:
06-1076   Reconstruction               5-033-L02  03/12/07     DONE    DONE       DONE      03/08/07   03/06/07   04/07/05     /  /                              255,000       270,000  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          GJSD Transportation/Maintenance:
05-1292   Reconstruction               5-038-L01  07/31/06     DONE    DONE       DONE      05/25/06   05/18/06   12/01/05   05/17/05                            289,336       281,835  RDR             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout #1 @ Baseball Field:
  -       New Construction             7-034-001                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout #2 @ Baseball Field:
  -       New Construction             7-035-001                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout #1 @ Softball Field:
  -       New Construction             7-036-001                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Dugout #2 @ Softball Field:
  -       New Construction             7-037-001                                              /  /       /  /     05/13/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Field House Toilets:
05-0843   New Construction             7-039-001  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   03/01/06   10/04/05   02 - 16                  188,170             0  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             

          Field House-Concessions:
  -    PR New Construction             7-040-001                                              /  /       /  /     02/13/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
05-0844   New Construction             7-040-001  11/02/06     DONE    DONE       DONE      03/01/06   02/28/06   02/13/06   10/04/05   02 - 16                  120,307             0  RDR             0           0            0
                                                                                                                                                                                                                                 Bonacci Architects pllc             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MAYFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-08-01-04
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
03-1565   Reconstruction               0-001-014  05/25/04     DONE    DONE       DONE      05/19/04   05/19/04   01/09/03   05/18/04   2,4,9,10,155,16           59,134        59,134  MAC             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
07-1601   Reconstruction               0-001-015               DONE    ADD. REQ'D STARTED   02/12/08   02/11/08   03/23/05   05/15/07   2,4,8,9,10,155,15,16           0     9,591,462  DDJ             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
07-1602   Reconstruction               0-001-016               DONE    ADD. REQ'D STARTED   02/12/08   02/11/08   09/13/07   05/15/07   2,4,8,9,155,15,16              0    12,290,120  DDJ             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
03-1363FP Reconstruction               0-001-FP1  06/02/04     DONE    DONE       DONE      04/07/04     /  /       /  /       /  /     16                         6,931         6,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-1378SC Visual Structural Inspection 0-001-SC1  01/16/08     DONE    DONE       DONE      12/31/07   12/31/07     /  /       /  /     16                        19,995             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
03-1564   Reconstruction               0-002-010  05/25/04     DONE    DONE       DONE      05/19/04   05/19/04   01/09/03   05/18/04   2,4,9,10,155,15,16       362,550       362,550  MAC             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
07-1603   Reconstruction               0-002-011               DONE    ADD. REQ'D STARTED   02/12/08   02/11/08   03/30/05   05/15/07   2,8,9,10,155,15,16             0    10,307,096  DDJ             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
03-1364FP Reconstruction               0-002-FP1  06/02/04     DONE    DONE       DONE      04/07/04     /  /       /  /       /  /     16                         6,000         6,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-0018SC Visual Structural Inspection 0-002-SC1  07/09/07     DONE    DONE       DONE      05/21/07   05/21/07     /  /       /  /     16                         1,793             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
07-1379SC Visual Structural Inspection 0-002-SC2  01/16/08     DONE    DONE       DONE      12/31/07   12/31/07     /  /       /  /     16                        19,043             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Shed @ Elementary School:
  -       Reconstruction               2-004-002                                              /  /       /  /     03/30/05     /  /     2,7,8,9,16                     0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Bldg.@ JR/SR High School:
  -       New Construction             2-009-001                                              /  /       /  /     03/30/05     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Building @ Elementary School:
  -       New Construction             2-010-001                                              /  /       /  /     03/30/05     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
07-1604   Reconstruction               5-003-006               DONE    ADD. REQ'D STARTED   02/12/08   02/11/08   04/05/05   05/15/07   2,15,16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-09-01-04
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Northville Central School:
04-0042   Reconstruction               0-001-009  09/29/06     DONE    DONE       DONE      07/07/04   06/23/04   06/28/04   06/14/04   155,16                   270,860       270,860  HCM             0           0            0
                                                                                                                                                                                                                                 Clough,Harbour&Associates LLP       
02-2398FP Reconstruction               0-001-FP1  08/25/03     DONE    DONE       DONE      06/17/03     /  /       /  /       /  /     16                         5,945         5,945  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1618SC Visual Structural Inspection 0-001-SC1  02/15/08     DONE    DONE       DONE      02/12/08   02/12/08     /  /       /  /     16                        12,004             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Shed/Mini Bus Garage:
05-1295DB Discovered Building          2-011-001  05/26/05     DONE    DONE       DONE      05/26/06   05/22/06   12/22/04     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
08-0003   Reconstruction               5-004-003                         UNREVIEWED         07/11/08   07/10/08   04/24/08   05/22/07   2,15                           0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OPPENHEIM EPHRATAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-10-01-04
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg:
07-0708   Additions and Alterations    0-001-006  04/22/08     DONE    DONE       DONE      11/05/07   11/02/07   09/06/06   04/25/07   02 - 16                4,530,000             0  HCM             0           0      312,844
                                                                                                                                                                                                                                 King & King, Architects             

          Bus Garage:
07-0709   Additions and Alterations    5-005-003  04/22/08     DONE    DONE       DONE      11/05/07   11/02/07   09/06/06   04/25/07   02 - 16                  950,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BROADALBIN-PERTH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-11-02-04
last updated on 07/25/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          ES/HS Broadalbin:
03-0406   Additions and Alterations    0-001-016  05/03/04     DONE    DONE       DONE      10/03/03   10/01/03   09/11/02   02/04/03   02 - 16               24,086,125    24,086,125  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0769   Reconstruction               0-001-017  06/24/08     DONE    DONE       DONE      11/13/07   11/07/07   07/18/07   02/06/07   2,4,7,8,9,155,15,16    3,739,025             0  JOD             0           0      186,951
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Grade School:
03-0407   Additions and Alterations    0-002-009  05/03/04     DONE    DONE       DONE      10/03/03   10/01/03   09/11/02   02/04/03   02 - 16                3,128,533     3,128,533  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Main Building Perth:
03-0408   Additions and Alterations    0-003-010  05/03/04     DONE    DONE       DONE      10/03/03   10/01/03   09/11/02   02/04/03   02 - 16                7,062,976     7,062,976  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0770   Reconstruction               0-003-011  06/24/08     DONE    DONE       DONE      11/13/07   11/07/07   07/18/07   02/06/07   2,4,7,8,9,155,15,16    2,174,575             0  JOD             0           0      108,729
                                                                                                                                                                                                                                 Ashley McGraw Architects            
07-0768   Reconstruction               0-003-012  06/13/08     DONE    DONE       DONE      11/13/07   11/07/07   07/18/07   02/06/07   13,15                    100,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Visual Structural Inspection 0-003-SC1                                              /  /       /  /       /  /       /  /     16                             0         2,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
03-0409   Reconstruction               5-004-002  05/03/04     DONE    DONE       DONE      10/03/03   10/01/03   07/15/03   02/04/03   2,4,7,8,9,155,15,16      287,945       287,945  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Bus Repair/Training Center:
03-0410   Additions and Alterations    5-014-003  05/03/04     DONE    DONE       DONE      10/03/03   10/01/03   09/11/02   02/04/03   02 - 16                  955,421       955,421  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED