Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/19/09 at 17:00:03




TUPPER LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-01-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior/Senior High School:
06-1642   Reconstruction               0-001-005  06/25/07     DONE    DONE       DONE      06/22/07   06/21/07   11/01/06     /  /     4,7,155,15,16            265,000       265,000  HCM             0           0       57,240
                                                                                                                                                                                                                                 SEI Design Group                    
08-1090   Reconstruction               0-001-006  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   05/10/07   03/04/08   2,8,155,15,16          1,057,880             0  HCM             0           0      173,186
                                                                                                                                                                                                                                 SEI Design Group                    

          L.P. Quinn Elementary School:
08-1091   Reconstruction               0-006-006  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   155,15,16                589,333             0  HCM             0           0       98,365
                                                                                                                                                                                                                                 SEI Design Group                    

          Bus Garage:
08-1092   Reconstruction               5-002-004  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   15,16                    127,217             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    

          Goff Nelson Memorial Library:
07-1532   Reconstruction               6-004-002  03/27/08     DONE    DONE       DONE      02/01/08   02/01/08   11/01/06     /  /     155,15,16                 36,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Design Group Educ. Fac. Dept.       
08-1095   Reconstruction               6-004-003  06/08/09     DONE    DONE       DONE      01/21/09   01/09/09   12/16/08   03/04/08   4,7,155,16               265,970             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    

          Gym @ Civic Center:
08-1093   Reconstruction               8-007-002  06/10/09     DONE    DONE       DONE      01/20/09   01/09/09   11/01/06   03/04/08   16                       159,600             0  HCM             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CHATEAUGAY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-08-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -    PR Additions and Alterations    0-001-009                                              /  /       /  /     09/01/09     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Steel Storage @ HS Concession:
  -    DB Discovered Building          2-012-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Building #1 @ HS Athl. Fld.:
  -    DB Discovered Building          2-013-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Bldg #2 @ HS Athl. Fld.:
  -    DB Discovered Building          2-014-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Salt Storage @ HS Athl Fld:
  -    DB Discovered Building          2-015-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Bldg @ HS Baseball Fld:
  -    DB Discovered Building          2-016-001                                              /  /       /  /       /  /       /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SALMON RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-12-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg. Campus:
04-1262   Reconstruction               0-001-015  05/13/05     DONE    DONE       DONE      05/12/05     /  /     01/03/05   05/21/02   2,8,9,155,15             828,877       828,877  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       
07-1202PR Additions and Alterations    0-001-016                         UNREVIEWED         12/24/07   12/24/07   12/14/07     /  /     02 - 16                        0    47,994,749  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
08-0560   Additions and Alterations    0-001-016  08/03/09     DONE    DONE       DONE      10/20/08   10/16/08   12/14/07   02/28/08   02 - 16               43,767,838    31,271,852  DDJ             0           0    1,204,684
                                                                                                                                                                                                                                 Collins & Scoville Architects,P.C.  
07-1808   Reconstruction               0-001-017  04/01/08     DONE    DONE       DONE      03/15/08   03/07/08   12/14/07   02/28/08   4,10,15,16             1,440,000     1,440,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Collins & Scoville Architects       

          Maintenance Building:
  -    DB Discovered Building          3-012-001                                              /  /       /  /     07/15/08     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -    PR Additions and Alterations    5-008-006                                              /  /       /  /     12/14/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SARANAC LAKE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-14-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Petrova Avenue School:
04-1044   Reconstruction               0-002-013  06/28/05     DONE    DONE       DONE      03/28/05   03/28/05   10/13/04   06/03/03   2,4,8,9                  387,840       387,840  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
06-0821   Reconstruction               0-002-014  04/12/07     DONE    DONE       DONE      01/29/07   01/26/07   02/23/06   03/15/05   2,4,8,9,155,15,16      1,435,619     1,435,619  JOD             0           0       98,719
                                                                                                                                                                                                                                 Bernier Carr Associates             
09-0397   Reconstruction               0-002-015               DONE    STARTED    UNREVIEWED11/06/09   11/04/09     /  /     05/20/08   8,10                           0             0  JOD             0           0            0
                                                                                                                                                                                                                                 348 Lake Street                     

          Bloomingdale Elementary:
  -    PR Additions and Alterations    0-013-007                                              /  /       /  /     02/23/06     /  /     02 - 16                        0     2,900,070  JOD             0           0            0
                                                                                                                                                                                                                                                                     
05-1258   Additions and Alterations    0-013-007  05/17/06     DONE    DONE       DONE      05/18/06   05/17/06   02/23/06   03/15/06   02 - 16                1,012,021     1,012,021  JOD             0           0      417,862
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Middle/High School:
04-1045   Reconstruction               0-014-008  06/28/05     DONE    DONE       DONE      03/28/05   03/28/05   10/13/04   06/03/03   2,4,8                    181,813       181,813  HCM             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             
07-1640   Reconstruction               0-014-009  02/26/08     DONE    DONE       DONE      02/19/08   02/14/08   02/23/06   03/15/05   2,4,8,9,155,15,16      2,025,000     2,025,000  JOD             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             

          MODULAR #1 @ BLOOMINGDALE ES:
05-1141TQ Temporary Quarters           0-017-001  04/17/06     DONE    DONE       DONE      04/17/06   04/11/06   03/24/06     /  /     02 - 16                   14,289             0  JOD             0           0            0
                                                                                                                                                                                                                                 Bernier Carr Associates             

          Modular #2 @ Bloomingdale ES:
  -    TQ Temporary Quarters           0-018-001                                              /  /       /  /     04/07/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          MODULAR #1 @ PERTOVA ES:
  -    PR New Construction             0-019-001                                              /  /       /  /     04/14/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          MODULAR #2 @ PETROVA ES:
  -    PR New Construction             0-020-001                                              /  /       /  /     04/14/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MALONE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-15-01-06
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Malone Junior High School:
04-1404   Reconstruction               0-001-008  08/19/05     DONE    DONE       DONE      06/09/05   06/09/05   03/17/05   05/17/05   8                         90,167        90,167  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0710   Reconstruction               0-001-009  11/08/07     DONE    DONE       DONE      11/05/07   11/02/07   10/11/07   10/09/07   13                        60,370        60,370  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
  -    PR Additions and Alterations    0-001-010                                              /  /       /  /     02/28/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          St.Joseph's Elem. School:
04-1405   Reconstruction               0-011-004  08/19/05     DONE    DONE       DONE      06/09/05   06/09/05   03/17/05   05/17/05   2,7                      254,225       254,225  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
  -       Reconstruction               0-011-005                                              /  /       /  /     09/30/09     /  /     2,4,7,8,9,10,155,15,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Flanders Elementary School:
  -       Reconstruction               0-017-006                                              /  /       /  /     07/28/09     /  /     2,7,8,9,155,15,16              0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Davis Elementary School Pre - K - 2:
  -       Reconstruction               0-018-003                                              /  /       /  /     02/28/08     /  /     2,4,7,8,9,10,14,155,           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Franklin Acad:HS 9-12:
04-0578   Additions and Alterations    0-019-009  02/22/05     DONE    DONE       DONE      12/27/04   12/24/04   03/16/04   03/14/00   02 - 16                  278,670       278,670  JOD             0           0            0
                                                                                                                                                                                                                                 Beardsley Design Associates         
06-0085   Reconstruction               0-019-011  07/19/06     DONE    DONE       DONE      07/19/06   07/19/06   06/01/06   05/23/06   155                      578,000       578,000  JOD             0           0            0
                                                                                                                                                                                                                                 King & King, Architects             
08-0098   Reconstruction               0-019-012  02/23/09     DONE    DONE       DONE      07/25/08   07/24/08   05/21/07   05/20/08   4,155,15,16              100,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Tisdel Associates consulting enginee
  -       Reconstruction               0-019-013                                              /  /       /  /     02/28/08     /  /     2,155,15,16                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Pre-Kindergarden - 5 Elementary Scho:
  -    XX New Construction             0-029-001                         CANCELLED            /  /       /  /     02/28/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
  -       Reconstruction               5-006-005                                              /  /       /  /     05/18/06     /  /     15,16                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage / Maintencance Buildi:
  -    XX New Construction             5-028-001                         CANCELLED            /  /       /  /     02/28/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BRUSHTON MOIRA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-16-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Central School Building:
05-1233   Reconstruction               0-001-008  09/01/06     DONE    DONE       DONE      05/08/06   05/01/06   11/21/05   05/01/05   8,155                     96,718        96,718  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
  -       Reconstruction               0-001-009                                              /  /       /  /     03/02/09     /  /     2,4,7,9,155,15,16              0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
05-1234   Reconstruction               5-003-008  09/01/06     DONE    DONE       DONE      05/08/06   05/01/06   11/21/05   05/01/05   8,10,15                   52,738        52,738  DDJ             0           0            0
                                                                                                                                                                                                                                 William Taylor Architects, PLLC.    
  -       Additions and Alterations    5-003-009                                              /  /       /  /     03/02/09     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
09-0396   Reconstruction               5-003-010               DONE    STARTED    STARTED   11/06/09   11/04/09   03/10/09     /  /     10,13                          0             0  DDJ             0           0            0
                                                                                                                                                                                                                                 SEI Design Group                    


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ST. REGIS FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-18-01-04
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bus Garage (lease):
04-1038   Reconstruction               5-004-L02  03/28/05     DONE    DONE       DONE        /  /       /  /     02/22/05     /  /                               37,400        37,400  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES FRANKLIN-ESSEX-HAMILTON STATUS REPORT ON CAPITAL PROJECTS
District No.: 16-90-00-00
last updated on 11/19/09
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          North Franklin Educ. Ctr.:
07-1932   Reconstruction               0-002-007  04/24/08     DONE    DONE       DONE      04/08/08   03/31/08   11/14/07   11/17/05   155,16                   306,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 348 Lake Street                     

          Adirondack Educ. Ctr.:
08-1168   Reconstruction               0-004-009  03/18/09     DONE    DONE       DONE      02/06/09   01/30/09   12/15/08   08/28/08   9,10,155,15,16           478,500             0  JOD             0           0            0
                                                                                                                                                                                                                                 348 Lake Street                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED