REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior/Senior High School:
06-1642 Reconstruction 0-001-005 06/25/07 DONE DONE DONE 06/22/07 06/21/07 11/01/06 / / 4,7,155,15,16 265,000 334,146 HCM 0 0 57,240
SEI Design Group
- Reconstruction 0-001-006 / / / / 05/10/07 / / 2,8,155,15,16 0 0 HCM 0 0 0
L.P. Quinn Elementary School:
- Reconstruction 0-006-006 / / / / 11/01/06 / / 155,15,16 0 8,173,901 HCM 0 0 0
Bus Garage:
- Reconstruction 5-002-004 / / / / 11/01/06 / / 15,16 0 0 HCM 0 0 0
Goff Nelson Memorial Library:
07-1532 Reconstruction 6-004-002 03/27/08 DONE DONE DONE 02/01/08 02/01/08 11/01/06 / / 155,15,16 36,000 0 HCM 0 0 0
Design Group Educ. Fac. Dept.
Gym @ Civic Center:
- Reconstruction 8-007-002 / / / / 11/01/06 / / 16 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
03-1290 Reconstruction 0-001-007 04/23/04 DONE DONE DONE 03/18/04 03/17/04 09/05/03 11/24/03 2,9,155,16 747,950 747,950 RDR 0 0 0
03-1012 Reconstruction 0-001-008 02/13/04 DONE DONE DONE 01/22/04 01/12/04 12/18/03 11/24/03 2,155,16 720,861 720,861 RDR 0 0 0
Bernier Carr Associates
03-0913FP Reconstruction 0-001-FP1 02/24/04 DONE DONE DONE 12/30/03 / / / / / / 16 5,938 5,938 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Bldg. Campus:
02-1016 Additions and Alterations 0-001-013 12/22/03 DONE DONE DONE 01/02/03 12/24/02 06/28/02 05/21/02 02 - 16 5,737,100 0 MGL 0 0 0
Collins & Scoville Architects
03-1637 Reconstruction 0-001-014 06/28/04 DONE DONE DONE 06/21/04 06/18/04 06/08/04 05/21/02 2,155,15,16 485,000 485,000 DDJ 0 0 0
Collins & Scoville Architects
04-1262 Reconstruction 0-001-015 05/13/05 DONE DONE DONE 05/12/05 / / 01/03/05 05/21/02 2,8,9,155,15 700,000 700,000 DDJ 0 0 0
Collins & Scoville Architects
07-1202PR Additions and Alterations 0-001-016 UNREVIEWED 12/24/07 12/24/07 12/14/07 / / 02 - 16 0 47,994,749 DDJ 0 0 0
Collins & Scoville Architects,P.C.
07-1808 Reconstruction 0-001-017 04/01/08 DONE DONE DONE 03/15/08 03/07/08 12/14/07 02/28/08 4,10,15,16 1,136,520 0 DDJ 0 0 0
Collins & Scoville Architects
Bus Garage:
02-1017 Reconstruction 5-008-005 12/22/03 DONE DONE DONE 01/02/03 12/24/02 06/28/02 05/21/02 2,4,7,155,15,16 806,800 806,800 MGL 0 0 0
Collins & Scoville Architects
- PR Additions and Alterations 5-008-006 / / / / 12/14/07 / / 02 - 16 0 0 DDJ 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Petrova Avenue School:
04-1044 Reconstruction 0-002-013 06/28/05 DONE DONE DONE 03/28/05 03/28/05 10/13/04 06/03/03 2,4,8,9 387,840 387,840 HCM 0 0 0
Bernier Carr Associates
06-0821 Reconstruction 0-002-014 04/12/07 DONE DONE DONE 01/29/07 01/26/07 02/23/06 03/15/05 2,4,8,9,155,15,16 1,598,650 1,598,650 JOD 0 0 98,719
Bernier Carr Associates
Bloomingdale Elementary:
- PR Additions and Alterations 0-013-007 / / / / 02/23/06 / / 02 - 16 0 2,900,070 JOD 0 0 0
05-1258 Additions and Alterations 0-013-007 05/17/06 DONE DONE DONE 05/18/06 05/17/06 02/23/06 03/15/06 02 - 16 1,012,021 1,012,021 JOD 0 0 417,862
Bernier Carr Associates
Middle/High School:
03-1021 Reconstruction 0-014-007 04/19/04 DONE DONE DONE 01/23/04 01/16/04 08/11/03 06/03/03 7 415,257 415,257 HCM 0 0 0
Bernier Carr Associates
04-1045 Reconstruction 0-014-008 06/28/05 DONE DONE DONE 03/28/05 03/28/05 10/13/04 06/03/03 2,4,8 181,813 181,813 HCM 0 0 0
Bernier Carr Associates
07-1640 Reconstruction 0-014-009 02/26/08 DONE DONE DONE 02/19/08 02/14/08 02/23/06 03/15/05 2,4,8,9,155,15,16 2,025,000 0 JOD 0 0 0
Bernier Carr Associates
MODULAR #1 @ BLOOMINGDALE ES:
05-1141TQ Temporary Quarters 0-017-001 04/17/06 DONE DONE DONE 04/17/06 04/11/06 03/24/06 / / 02 - 16 14,289 0 JOD 0 0 0
Bernier Carr Associates
Modular #2 @ Bloomingdale ES:
- TQ Temporary Quarters 0-018-001 / / / / 04/07/06 / / 02 - 16 0 0 JOD 0 0 0
MODULAR #1 @ PERTOVA ES:
- PR New Construction 0-019-001 / / / / 04/14/06 / / 02 - 16 0 0 JOD 0 0 0
MODULAR #2 @ PETROVA ES:
- PR New Construction 0-020-001 / / / / 04/14/06 / / 02 - 16 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Malone Junior High School:
03-0236 Reconstruction 0-001-007 UNREVIEWED
DONE ADD. REQ'D08/27/03 07/30/03 07/12/02 04/16/01 155,15,16 680,487 680,487 JOD 0 0 0
Wendel Duchscherer Arch/Eng
04-1404 Reconstruction 0-001-008 08/19/05 DONE DONE DONE 06/09/05 06/09/05 03/17/05 05/17/05 8 90,167 55,000 JOD 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
07-0710 Reconstruction 0-001-009 11/08/07 DONE DONE DONE 11/05/07 11/02/07 10/11/07 10/09/07 13 125,000 125,000 JOD 0 0 0
King & King, Architects
- PR Additions and Alterations 0-001-010 / / / / 02/28/08 / / 02 - 16 0 0 JOD 0 0 0
St.Joseph's Elem. School:
03-0237 Reconstruction 0-011-003 UNREVIEWED
DONE ADD. REQ'D08/27/03 07/30/03 07/12/02 04/16/01 155,15,16 221,200 221,200 JOD 0 0 0
Wendel Duchscherer Arch/Eng
04-1405 Reconstruction 0-011-004 08/19/05 DONE DONE DONE 06/09/05 06/09/05 03/17/05 05/17/05 2,7 254,225 254,225 JOD 0 0 0
Dodge Chamberlin Luzine Weber, Arch.
Flanders Elementary School:
03-0238 Reconstruction 0-017-005 UNREVIEWED
DONE ADD. REQ'D08/27/03 07/30/03 07/12/02 04/16/01 155,15,16 449,287 449,287 JOD 0 0 0
Wendel Duchscherer Arch/Eng
Davis Elementary School Pre - K - 2:
03-0239 Reconstruction 0-018-002 UNREVIEWED
DONE ADD. REQ'D08/27/03 07/30/03 07/12/02 04/16/01 155,15,16 82,351 82,351 JOD 0 0 0
Wendel Duchscherer Arch/Eng
- Reconstruction 0-018-003 / / / / 02/28/08 / / 2,4,7,8,9,10,14,155, 0 0 JOD 0 0 0
Franklin Acad:HS 9-12:
03-0240 Reconstruction 0-019-008 UNREVIEWED
DONE ADD. REQ'D08/27/03 07/30/03 08/06/02 04/16/01 155,15,16 56,958 56,958 JOD 0 0 0
Wendel Duchscherer Arch/Eng
04-0578 Additions and Alterations 0-019-009 02/22/05 DONE DONE DONE 12/27/04 12/24/04 03/16/04 03/14/00 02 - 16 278,670 278,670 JOD 0 0 0
Beardsley Design Associates
- XX Reconstruction 0-019-010 CANCELLED / / / / 05/24/04 / / 16 0 36,031,040 JOD 0 0 0
06-0085 Reconstruction 0-019-011 07/19/06 DONE DONE DONE 07/19/06 07/19/06 06/01/06 05/23/06 155 578,000 578,000 JOD 0 0 0
King & King, Architects
- Reconstruction 0-019-012 / / / / 05/21/07 / / 4,155,15,16 0 0 JOD 0 0 0
- Reconstruction 0-019-013 / / / / 02/28/08 / / 2,155,15,16 0 0 JOD 0 0 0
Pre-Kindergarden - 5 Elementary Scho:
- PR New Construction 0-029-001 / / / / 02/28/08 / / 02 - 16 0 0 JOD 0 0 0
Bus Garage:
- Reconstruction 5-006-005 / / / / 05/18/06 / / 15,16 0 0 JOD 0 0 0
New Bus Garage / Maintencance Buildi:
- PR New Construction 5-028-001 / / / / 02/28/08 / / 02 - 16 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central School Building:
05-1233 Reconstruction 0-001-008 09/01/06 DONE DONE DONE 05/08/06 05/01/06 11/21/05 05/01/05 8,155 83,500 83,500 DDJ 0 0 0
William Taylor Architects, PLLC.
Bus Garage:
05-1234 Reconstruction 5-003-008 09/01/06 DONE DONE DONE 05/08/06 05/01/06 11/21/05 05/01/05 8,10,15 47,000 47,000 DDJ 0 0 0
William Taylor Architects, PLLC.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bus Garage (lease):
04-1038 Reconstruction 5-004-L02 03/28/05 DONE DONE DONE / / / / 02/22/05 / / 37,400 37,400 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
North Franklin Educ. Ctr.:
02-0304 Reconstruction 0-002-006 08/15/03 DONE DONE DONE 09/24/02 09/24/02 02/21/02 11/15/01 7 550,000 550,000 MAC 0 0 0
348 Lake Street
07-1932 Reconstruction 0-002-007 04/24/08 DONE DONE DONE 04/08/08 03/31/08 11/14/07 11/17/05 155,16 306,000 0 JOD 0 0 0
348 Lake Street
Adirondack Educ. Ctr.:
02-0305 Reconstruction 0-004-007 08/15/03 DONE DONE DONE 09/24/02 09/24/02 02/21/02 11/15/01 7 238,500 238,500 MAC 0 0 0
348 Lake Street
04-0098 Reconstruction 0-004-008 11/09/04 DONE DONE DONE 08/06/04 08/05/04 05/23/03 02/20/03 155 325,372 325,372 MAC 0 0 0
Saranac Engineering
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED