Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 10/10/08 at 08:41:43




BEACON CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-02-00-01
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          James Forrestal School:
05-0495   Alterations                  0-002-012  05/08/06     DONE    DONE       DONE      12/23/05   12/23/05   03/09/04   05/18/04   02 - 16                  175,000       175,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0761   Reconstruction               0-002-013  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   2,4,7,9,10,14,155,16   1,201,711             0  JOD             0           0       97,339
                                                                                                                                                                                                                                 Fellenzer Engineering               

          South Ave. School:
05-0496   Alterations                  0-003-008  05/08/06     DONE    DONE       DONE      12/23/05   12/23/05   03/09/04   05/18/04   02 - 16                  250,000       250,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0762   Reconstruction               0-003-009  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   2,4,7,8,9,10,14,155,   2,814,140             0  JOD             0           0      227,945
                                                                                                                                                                                                                                 Fellenzer Engineering               

          Rombout Junior High School:
04-1035   Additions and Alterations    0-004-010  05/17/05     DONE    DONE       DONE      03/25/05   03/22/05   03/09/04   05/18/04   02 - 16                8,400,000     8,400,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0763   Reconstruction               0-004-011  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   7,9,10,155,15,16       1,140,896             0  JOD             0           0       92,413
                                                                                                                                                                                                                                 Fellenzer Engineering               

          Glenham Elementary School:
05-0497   Alterations                  0-006-013  05/08/06     DONE    DONE       DONE      12/23/05   12/23/05   03/09/04   05/18/04   02 - 16                  130,000       130,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0764   Reconstruction               0-006-014  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   2,7,9,10,16            1,073,140             0  JOD             0           0       86,924
                                                                                                                                                                                                                                 Fellenzer Engineering               

          Sargent Elementary School:
05-0498   Additions and Alterations    0-008-011  05/08/06     DONE    DONE       DONE      12/23/05   12/23/05   03/09/04   05/18/04   02 - 16                  320,000       320,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0765   Reconstruction               0-008-012  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   2,4,9,14,16              614,542             0  JOD             0           0       49,778
                                                                                                                                                                                                                                 Fellenzer Engineering               

          New High School:
05-0499   Alterations                  0-020-002  05/08/06     DONE    DONE       DONE      12/23/05   12/23/05   03/09/04   05/18/04   02 - 16                   50,000        50,000  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0766   Reconstruction               0-020-003  04/28/08     DONE    DONE       DONE      11/07/07   11/06/07   03/08/07   03/21/07   10,155,16                955,571       955,571  JOD             0           0       77,401
                                                                                                                                                                                                                                 Fellenzer Engineering               

          Administration Building:
  -    PR Additions and Alterations    1-005-005                                              /  /       /  /     03/09/04     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Maintenance Garage:
  -       Reconstruction               3-011-004                                              /  /       /  /     03/08/07     /  /     4,7,8                          0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Maintenance/Storage:
  -       Additions and Alterations    5-018-002                                              /  /       /  /     03/09/04     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Howland Public Library:
  -    PR New Construction             6-022-001                                              /  /       /  /     02/04/05     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Fieldhouse:
  -       Reconstruction               7-016-002                                              /  /       /  /     03/08/07     /  /     7,15                           0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Press Box:
04-1459   New Construction             7-023-001  09/02/05     DONE    DONE       DONE      06/23/05   06/22/05   04/25/05   05/18/04   02 - 16                   35,585             0  JOD             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-05-02-02
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Dover Middle/High School:
05-0181   Reconstruction               0-001-009  01/30/06     DONE    DONE       DONE      09/13/05   09/12/05   04/11/05   05/17/05   2,8,9,15                  99,691        99,691  RDR             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
05-1277   Reconstruction               0-001-010  02/15/07     DONE    DONE       DONE      05/22/06   05/19/06   10/27/05   12/15/05   2,10,155,15,16         2,070,450     2,070,450  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
06-1084   Reconstruction               0-001-011  03/09/07     DONE    DONE       DONE      03/09/07   03/02/07   02/16/07   05/16/06   10,13,15,16               91,500        91,500  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
07-1529   Reconstruction               0-001-012  04/18/08     DONE    DONE       DONE      02/01/08   01/31/08   10/11/07   05/15/07   15                        56,100        56,100  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
  -       Reconstruction               0-001-013                                              /  /       /  /     09/23/08     /  /     4,7                            0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Wingdale Elementary:
07-1530   Reconstruction               0-003-004  04/18/08     DONE    DONE       DONE      02/01/08   01/31/08   10/11/07   05/15/07   16                        43,400        43,400  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
  -       Reconstruction               0-003-005                                              /  /       /  /     05/14/08     /  /     15                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Dover Elem. School:
03-1575   Reconstruction               0-004-007  07/15/04     DONE    DONE       DONE      05/21/04   05/20/04   12/19/03   05/18/04   2,10                      90,803        90,803  RDR             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   
06-0543   Reconstruction               0-004-008                       ADDENDUM REQ'D       11/22/06   11/21/06   10/27/05     /  /     2,7,9,15,16                    0     6,448,770  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   

          Athletic Storage Building:
  -       New Construction             2-011-001                                              /  /       /  /     09/23/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Athletic Bldg. / Bleachers:
05-1278   New Construction             7-009-001  02/15/07     DONE    DONE       DONE      05/22/06   05/19/06   11/10/05   12/15/05   02 - 16                  359,950             0  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   

          Concession Stand @ MS/HS:
05-1279   New Construction             7-010-001  02/15/07     DONE    DONE       DONE      05/22/06   05/19/06   11/10/05   12/15/05   02 - 16                   69,600             0  JOD             0           0            0
                                                                                                                                                                                                                                 Morris Associates                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HYDE PARK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-08-01-06
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Haviland Middle School(JrHigh):
04-0446XX Reconstruction               0-001-015  03/10/05               CANCELLED          11/24/04   11/19/04     /  /     05/21/02   7,9,10,15,16             625,000       625,000  MAC             0           0            0
                                                                                                                                                                                                                                 Liscum-McCormack-Vanvoorhis         
  -       Reconstruction               0-001-016                                              /  /       /  /     01/14/05     /  /     2,4,7,8,9,14,155,15,           0    15,961,616  HCM             0           0            0
                                                                                                                                                                                                                                                                     
04-1244   Reconstruction               0-001-016  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05     /  /     03/15/05                            443,892       412,191                  0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0017   Reconstruction               0-001-017  08/23/05     DONE    DONE       DONE      07/06/05   07/01/05   05/31/05   03/15/05   7                        233,417       128,000  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0468   Reconstruction               0-001-018  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,8,9,14,155,15,16   2,449,646     2,110,261  HCM             0           0      335,816
                                                                                                                                                                                                                                 Thomas Associates                   
07-2297   Reconstruction               0-001-019               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0    17,563,484  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-001-020                                              /  /       /  /     09/10/08     /  /     2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Roosevelt High School:
04-1245   Reconstruction               0-002-015  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,8,9,14,155,15,16     400,121       314,100  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0469   Reconstruction               0-002-016  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,8,9,155,15,16      1,548,970     1,783,284  HCM             0           0      276,137
                                                                                                                                                                                                                                 Thomas Associates                   
05-0254   Reconstruction               0-002-017  10/11/05     DONE    DONE       DONE      10/11/05   10/11/05   09/28/05   03/15/05   16                       434,630       186,500  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
07-2298   Reconstruction               0-002-018               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   7,8                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
07-2316   Reconstruction               0-002-019  08/26/08     DONE    DONE       DONE      07/18/08   07/18/08   07/16/08     /  /     2,8,13                 1,085,835             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                

          Ralph R. Smith Elementary:
04-0443XX Reconstruction               0-003-013  03/10/05               CANCELLED          11/24/04   11/19/04   09/12/02   05/21/02   8                         25,000        25,000  MAC             0           0            0
                                                                                                                                                                                                                                 Liscum-McCormack-Vanvoorhis         
04-1246   Reconstruction               0-003-014  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,7,8,9,14,155,15,     345,662       355,116  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0470   Reconstruction               0-003-015  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,7,8,9,14,155,15,   2,348,837     2,131,437  HCM             0           0      499,415
                                                                                                                                                                                                                                 Thomas Associates                   
07-2299   Reconstruction               0-003-016               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-003-017                                              /  /       /  /     09/10/08     /  /     7,8                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Violet Avenue Elementary:
04-0444   Reconstruction               0-004-012  03/10/05     DONE    DONE       DONE      11/24/04   11/19/04   09/12/02   05/21/02   7,9,15                   300,000       300,000  MAC             0           0            0
                                                                                                                                                                                                                                 Liscum-McCormack-Vanvoorhis         
04-1247   Reconstruction               0-004-013  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,7,8,9,14,155,15,     252,572       191,268  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0471   Reconstruction               0-004-014  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,7,8,9,14,155,15,   1,289,034     1,443,027  HCM             0           0      132,002
                                                                                                                                                                                                                                 Thomas Associates                   
07-2300   Reconstruction               0-004-015               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-004-016                                              /  /       /  /     09/10/08     /  /     2,4,7,8                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Hyde Park Elementary:
04-0445   Reconstruction               0-005-016  03/10/05     DONE    DONE       DONE      11/24/04   11/19/04   09/12/02   05/21/02   7,8,9,13,15              395,000       395,000  MAC             0           0            0
                                                                                                                                                                                                                                 Liscum-McCormack-Vanvoorhis         
04-0737   Reconstruction               0-005-017  02/03/05     DONE    DONE       DONE      01/28/05   01/27/05   12/13/04   05/15/01   14,16                     52,800        52,800  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
04-1248   Reconstruction               0-005-018  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,7,8,9,14,155,15,      55,304        31,020  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0472   Reconstruction               0-005-019  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,7,8,9,14,155,15,     731,044       862,607  HCM             0           0       68,108
                                                                                                                                                                                                                                 Thomas Associates                   
07-2301   Reconstruction               0-005-020               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-005-021                                              /  /       /  /     09/10/08     /  /     2,4,7,8                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Netherwood Elementary School:
04-1249   Reconstruction               0-007-014  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,7,8,9,14,155,15,      33,755        15,180  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0473   Reconstruction               0-007-015  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,7,8,9,14,155,15,   2,098,122     2,098,122  HCM             0           0       92,823
                                                                                                                                                                                                                                 Thomas Associates                   
07-2302   Reconstruction               0-007-016               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-007-017                                              /  /       /  /     09/10/08     /  /     7,8                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          North Park Elementary School:
04-0479XX Reconstruction               0-013-014  02/24/05               CANCELLED          11/24/04   11/18/04   09/12/02   05/21/02   2,155                     60,000        60,000  MAC             0           0            0
                                                                                                                                                                                                                                 Liscum-McCormack-Vanvoorhis         
04-1250   Reconstruction               0-013-015  06/24/05     DONE    DONE       DONE      05/10/05   05/09/05   01/14/05   03/15/05   2,4,7,8,9,14,155,15,      82,647        19,140  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0474   Reconstruction               0-013-016  04/06/06     DONE    DONE       DONE      12/20/05   12/20/05   05/31/05   03/15/05   2,4,7,8,9,155,15,16      572,346       572,346  HCM             0           0       74,942
                                                                                                                                                                                                                                 Thomas Associates                   
07-2303   Reconstruction               0-013-017               DONE    STARTED    UNREVIEWED07/03/08   06/12/08   10/23/07   12/13/07   2,7,8                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 ThomasAssociates, PC                
  -       Reconstruction               0-013-018                                              /  /       /  /     09/10/08     /  /     7,8                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Leased Administration:
07-2317   Reconstruction               1-016-002  08/26/08     DONE    DONE       DONE      07/07/08   06/18/08   01/31/08   12/13/07                            524,955             0  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Bus Garage:
07-2318   Reconstruction               4-006-008  08/26/08     DONE    DONE       DONE      07/07/08   06/18/08   10/23/07   12/13/07   7                        384,210             0  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          District Wide:
  -       Reconstruction               7-999-001                                              /  /       /  /     10/23/07     /  /     10,13,16                       0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTHEAST (WEBUTUCK) CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-11-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Millerton Elementary School:
05-0131   Reconstruction               0-001-007  08/30/05     DONE    DONE       DONE      08/16/05   08/09/05   04/06/05   04/18/05   13                       320,000       320,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-001-008                                              /  /       /  /     05/01/08     /  /     2,7,15                         0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Webutuck Jr/Sr High School:
03-1197   Reconstruction               0-002-012  07/01/04     DONE    DONE       DONE      03/02/04   03/01/04   11/05/03   04/27/00   4,9,10,155,15,16       1,397,584     1,397,584  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               0-002-013                                              /  /       /  /     05/01/08     /  /     8,9,15,16                      0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Amenia Elementary School:
03-1198   Reconstruction               0-003-012  07/01/04     DONE    DONE       DONE      03/02/04   03/01/04   11/05/03   04/27/00   8,9,10,155,15,16         580,559       580,559  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            

          Webutuck Elementary School:
03-1196   Reconstruction               0-004-011  07/01/04     DONE    DONE       DONE      03/02/04   03/01/04   11/05/03   04/27/00   8,9                      432,842       432,842  JOD             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               0-004-012                                              /  /       /  /     10/07/08     /  /     8,9,15,16                      0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Stand:
  -       New Construction             7-009-001                                              /  /       /  /     11/16/07     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PAWLING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-12-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Pawling Elementary School:
04-0689   Reconstruction               0-001-014  02/04/05     DONE    DONE       DONE      01/19/05   01/18/05   08/12/04   11/22/04   7                        115,000       115,000  JOD             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
05-0063   Reconstruction               0-001-015  03/29/06     DONE    DONE       DONE      07/22/05   07/20/05   08/12/04   05/18/04   16                       150,000       150,000  JOD             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          
06-0778   Reconstruction               0-001-017  03/09/07     DONE    DONE       DONE      01/17/07   01/17/07   11/20/06   05/16/06   7                      2,600,000     2,600,000  JOD             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          Junior Senior High School:
07-1616   Reconstruction               0-002-013  04/23/08     DONE    DONE       DONE      02/14/08   02/12/08   12/17/07   05/15/07   2,4,7,16               1,910,000             0  JOD             0           0      465,307
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          New Middle School:
07-0550   Reconstruction               0-006-003  10/19/07     DONE    DONE       DONE      10/16/07   10/12/07   10/15/07   10/02/07   15                        35,000        35,000  JOD             0           0            0
                                                                                                                                                                                                                                 Damiano Barile Engineers, P.C.      
  -       Reconstruction               0-006-004                                              /  /       /  /     10/11/07     /  /     15                             0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Admin @ Donaldson Center:
05-0039TQ Temporary Quarters           1-010-001                       ADDENDUM REQ'D       07/13/05   07/12/05   06/13/05     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Administration Building:
05-0196TQ Temporary Quarters           1-011-001                       ADDENDUM REQ'D       09/16/05   09/16/05   07/19/05     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage:
07-1617   Reconstruction               3-003-003  04/23/08     DONE    DONE       DONE      02/14/08   02/12/08   12/17/07   05/15/07   7                         30,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Kaeyer, Garment & Davidson          

          Leased Bus Garage:
05-0040   Reconstruction               5-009-L01  01/26/06     DONE    DONE       DONE      07/13/05   07/12/05   06/08/05     /  /                              848,500       848,500  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




PINE PLAINS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-13-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Seymour Smith School:
03-1193   Reconstruction               0-001-008  05/18/04     DONE    DONE       DONE      03/03/04   03/01/04   02/03/04   05/18/04   4,7                      438,120       438,120  MAC             0           0            0
                                                                                                                                                                                                                                 Walter Priede,Architect             
  -       Reconstruction               0-001-009                                              /  /       /  /     02/03/04     /  /     10                             0     8,055,750  MAC             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-001-010                                              /  /       /  /     02/03/04     /  /     155                            0     8,055,750  MAC             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-001-011                                              /  /       /  /     08/11/05     /  /     155                            0     8,055,750  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0346   Reconstruction               0-001-012  09/12/07     DONE    DONE       DONE      09/10/07   09/10/07   08/10/07   06/20/07   2,4,155,15,16            175,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
  -       Reconstruction               0-001-013                                              /  /       /  /     08/22/08     /  /     2,4,7,8,10,16                  0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Cold Springs Elementary:
04-1007   Reconstruction               0-002-005  06/03/05     DONE    DONE       DONE      03/17/05   03/16/05   01/20/05   05/17/05   7                        740,187       740,187  HCM             0           0            0
                                                                                                                                                                                                                                 Quality Environmental Solutions & Te

          Stissing Mt Jr/Sr High School:
06-1355   Reconstruction               0-009-009  09/05/07     DONE    DONE       DONE      04/24/07   04/19/07   06/05/06   05/15/07   2,4,8,9,155,15,16        824,000       824,000  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
08-0097   Reconstruction               0-009-010  10/08/08     DONE    DONE       DONE      07/25/08   07/23/08   03/17/08   03/05/08   16                       235,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Storage Shed:
06-1356   New Construction             2-011-001  09/05/07     DONE    DONE       DONE      04/24/07   04/19/07   04/10/07     /  /     02 - 16                   95,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Press Box:
06-1357   New Construction             7-010-001  09/05/07     DONE    DONE       DONE      04/24/07   04/19/07   04/10/07     /  /     02 - 16                   56,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




POUGHKEEPSIE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-15-00-01
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Columbus School #3:
03-0301   Reconstruction               0-001-009  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/12/03   04/24/02   2,4,8,9,13,155,15,16     310,000       310,000  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          SFB Morse School #5:
03-0302   Reconstruction               0-002-009  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/11/01   04/24/02   2,4,7,8,9,10,14,155,   5,708,830     3,738,100  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Gov. Clinton School #8:
03-0303   Reconstruction               0-004-009  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/09/03   04/24/02   2,4,8,9,13,155,15,16     515,000       515,000  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          C.B. Warring School #10:
03-0304   Reconstruction               0-005-009  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/09/03   04/24/02   2,4,8,9,13,155,15,16     364,499       364,499  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Krieger School No. 11:
03-0305   Reconstruction               0-006-009  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/11/01   04/24/02   2,4,7,8,9,10,14,155,   7,409,333     6,720,316  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Junior/Senior High School:
03-0306   Reconstruction               0-007-012  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/11/01   04/24/02   2,4,7,8,9,10,14,155,   7,380,000     7,048,000  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              
04-1394SC Visual Structural Inspection 0-007-SC1  06/10/05     DONE    DONE       DONE      04/13/05   04/13/05     /  /       /  /     16                        32,208        32,208  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          W.W. Smith Elementary:
03-0307   Reconstruction               0-008-014  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/09/03   04/24/02   2,4,8,9,13,155,15,16     622,791       622,791  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Middle School:
03-0308   Reconstruction               0-015-014  03/04/04     DONE    DONE       DONE      09/16/03   06/16/03   05/09/03   04/24/02   2,4,8,9,13,155,15,16     676,000       676,000  RDR             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              
04-1395SC Visual Structural Inspection 0-015-SC1  06/10/05     DONE    DONE       DONE      04/13/05   04/13/05     /  /       /  /     16                        27,122        27,122  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          BOATHOUSE STORAGE BUILDING:
  -    TQ Temporary Quarters           7-020-001                                              /  /       /  /     06/14/06     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ARLINGTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-01-06
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Arlington Middle School:
06-0390   Reconstruction               0-002-012  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,4,7,8,9,10,155,15,   1,562,099     1,407,392  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Raymond Ave. Grade School:
06-0391   Reconstruction               0-003-011  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,8,9,155,16             479,357       224,869  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Overlook Elementary School:
06-0392   Reconstruction               0-004-010  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,7,155,15,16          1,437,093     1,703,242  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          LaGrange Elementary School:
06-0393   Reconstruction               0-005-013  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,7,13,15,16           1,360,874     1,261,608  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Beekman Elementary School:
06-0394   Reconstruction               0-006-009  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,8,155,15,16          1,029,305     1,042,099  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Traver Road Primary:
06-0395   Reconstruction               0-007-010  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,7,8,155,15,16        1,337,411     1,075,599  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          North Campus HS:
04-1349   Reconstruction               0-008-008  07/27/05     DONE    DONE       DONE      06/01/05   05/27/05   03/24/05   05/11/05   16                       365,000       365,000  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-008-009                                              /  /       /  /     08/10/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
06-0839   Additions and Alterations    0-008-009  06/21/07     DONE    DONE       DONE      01/30/07   01/25/07   08/10/05   12/13/05   02 - 16                2,164,280     2,164,280  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
07-0426   Reconstruction               0-008-010  12/26/07     DONE    DONE       DONE      09/27/07   09/14/07     /  /       /  /     2,4,7,8,9,14,155,15,  44,678,959    44,678,959  HCM             0           0    3,307,788
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-008-011                                              /  /       /  /     07/27/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-008-012                                              /  /       /  /     09/03/08     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          LaGrange MS(fmlySouth Campus):
06-0396   Reconstruction               0-009-006  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,9,155,15,16          1,888,325     1,326,677  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Titusville Elementary School:
06-0397   Reconstruction               0-010-008  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,4,7,8,9,14,155,15,   2,239,675     1,977,608  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          West Road Elem. School:
06-0398   Reconstruction               0-012-006  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,7,14,155,15,16         946,507       946,507  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Noxon Road Elem. School:
06-0399   Reconstruction               0-013-003  02/27/07     DONE    DONE       DONE      10/31/06   10/30/06   02/13/06   12/13/05   2,4,7,9,14,155,15,16   1,057,115       925,378  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Grounds Garage:
06-0840   Reconstruction               2-023-001  12/26/07     DONE    DONE       DONE      01/30/07   01/25/07   12/05/06   12/13/05   15,16                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SPACKENKILL UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-16-02-02
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Martha W. Lawrence Elementary:
04-0322   Reconstruction               0-001-003  01/03/05     DONE    DONE       DONE      10/25/04   10/22/04   09/17/04   05/18/04   7,9                      204,800       204,800  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1002   Reconstruction               0-001-004  03/02/07     DONE    DONE       DONE      02/26/07   02/22/07   11/20/06   10/10/06   155                      135,000       135,000  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
06-1643   Reconstruction               0-001-005  07/06/07     DONE    DONE       DONE      06/26/07   06/22/07   05/22/07   05/07/07   2,155                    105,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Todd Junior High School:
04-0323   Reconstruction               0-002-011  01/03/05     DONE    DONE       DONE      10/25/04   10/22/04   03/25/04   05/18/04   7,16                     860,500       860,500  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Nassau Road Elementary:
04-0324   Reconstruction               0-003-009  01/03/05     DONE    DONE       DONE      10/25/04   10/22/04   03/25/04   05/18/04   2,7,16                   702,300       702,300  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Hagan Elementary School:
04-0325   Reconstruction               0-004-010  01/03/05     DONE    DONE       DONE      10/25/04   10/22/04   03/25/04   05/18/04   7,15,16                1,182,400     1,182,400  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-004-011                                              /  /       /  /     09/24/08     /  /     2,4,9,155                      0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Spackenkill High School:
05-0647   Reconstruction               0-005-015  10/19/06     DONE    DONE       DONE      01/24/06   01/24/06   03/16/05   03/16/05   2,7,8,9,155,15,16      2,150,000     2,150,000  JOD             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -    PR Additions and Alterations    0-005-016                                              /  /       /  /     09/24/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Districtwide:
02-1552   Reconstruction               7-999-001  01/28/04     DONE    DONE       DONE      02/24/03   02/18/03   10/23/02   04/10/02   16                       520,450       520,450  MGL             0           0            0
                                                                                                                                                                                                                                 Salamon, Julia                      


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RED HOOK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-17-01-06
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Linden Ave Middle School:
07-1053   Reconstruction               0-003-005  04/24/08     DONE    DONE       DONE      12/06/07   12/05/07   06/28/06   01/23/07   2,7                    1,770,320     1,770,320  DDJ             0           0       89,708
                                                                                                                                                                                                                                 Gerard Associates                   
07-1382SC Visual Structural Inspection 0-003-SC1  01/17/08     DONE    DONE       DONE      01/07/08   01/07/08     /  /       /  /     16                        10,000             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Senior High School:
05-0343   Reconstruction               0-005-006  03/03/06     DONE    DONE       DONE      11/14/05   11/03/05   02/17/05   03/10/05   16                       178,887       178,887  DDJ             0           0            0
                                                                                                                                                                                                                                 J.Paul Vosburgh, Architct           
07-1054   Reconstruction               0-005-007  04/24/08     DONE    DONE       DONE      12/06/07   12/05/07   06/28/06   01/23/07   2,7                    3,648,227     3,648,227  DDJ             0           0      184,868
                                                                                                                                                                                                                                 Gerard Associates                   
06-0746SC Visual Structural Inspection 0-005-SC1  06/07/07     DONE    DONE       DONE      01/05/07   01/05/07     /  /       /  /     16                        12,667             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Mill Rd. Elementary:
05-0049   Reconstruction               0-006-005  07/15/05     DONE    DONE       DONE      07/15/05   07/14/05   04/19/05   05/18/05   2,15                      99,761        99,761  DDJ             0           0            0
                                                                                                                                                                                                                                 J.Paul Vosburgh, Architct           
06-0616   Reconstruction               0-006-006  12/28/06     DONE    DONE       DONE      12/12/06   12/11/06   06/20/06   08/17/06   15                        85,991        85,991  DDJ             0           0            0
                                                                                                                                                                                                                                 J.Paul Vosburgh, Architct           
07-1055   Reconstruction               0-006-007  04/24/08     DONE    DONE       DONE      12/06/07   12/05/07   06/28/06   01/23/07   2,7                    9,531,453     9,531,453  DDJ             0           0      482,991
                                                                                                                                                                                                                                 Gerard Associates                   
07-1380SC Visual Structural Inspection 0-006-SC1  01/17/08     DONE    DONE       DONE      01/07/08   01/07/08     /  /       /  /     16                        11,852             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          High School Track Storage Barn:
07-1029DB Discovered Building          2-019-001  07/18/08     DONE    DONE       DONE      12/04/07   11/30/07   09/23/03     /  /     02 - 16                        0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Linden Ave. Bus Garage:
07-0273   Reconstruction               5-007-005  10/05/07     DONE    DONE       DONE      09/04/07   08/31/07   05/21/07   06/14/07   10                       150,000       150,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Gerard Associates                   
07-1381SC Visual Structural Inspection 5-007-SC1  01/17/08     DONE    DONE       DONE      01/07/08   01/07/08     /  /       /  /     16                         5,960             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          :
05-0226   Reconstruction               7-020-001  10/03/05     DONE    DONE       DONE      09/27/05   09/20/05   08/22/05     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Red Hook VFW:
  -    XX Reconstruction               8-021-001                         CANCELLED            /  /       /  /     05/25/05     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          RED HOOK FIRE HOUSE:
06-0212TQ Temporary Quarters           8-022-001  04/26/07     DONE    DONE       DONE      09/07/06   09/01/06   03/31/06     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




RHINEBECK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-18-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
04-0886   Additions and Alterations    0-002-014  04/22/05     DONE    DONE       DONE      03/04/05   03/03/05   10/25/00   01/27/04   02 - 16               17,454,364    15,980,651  DDJ             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
05-1123   Reconstruction               0-002-015  10/12/06     DONE    DONE       DONE      04/13/06   04/10/06   07/22/05   08/16/05   8,155,16                 755,412       755,412  DDJ             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
07-1367   Reconstruction               0-002-016  01/28/08     DONE    DONE       DONE      01/15/08   01/14/08   03/07/07   03/13/07   2,8,16                   477,600             0  DDJ             0           0      301,842
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Livingston Elem. School:
04-0887   Additions and Alterations    0-004-011  04/22/05     DONE    DONE       DONE      03/04/05   03/03/05   11/17/00   01/27/04   02 - 16                6,205,636     5,377,993  DDJ             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
05-1124   Reconstruction               0-004-012  10/12/06     DONE    DONE       DONE      04/13/06   04/10/06   07/22/05   08/16/05   8,155,16                  58,030        58,030  DDJ             0           0            0
                                                                                                                                                                                                                                 Einhorn Yaffee Prescott P.C.        
07-1368   Reconstruction               0-004-013  01/28/08     DONE    DONE       DONE      01/15/08   01/14/08   03/07/07   03/13/07   2,8,16                   148,103             0  DDJ             0           0       93,601
                                                                                                                                                                                                                                 Clark Patterson Associates          

          Administrative Building:
04-1351TQ Temporary Quarters           1-009-001  08/02/05     DONE    DONE       DONE      06/01/05   06/01/05   05/02/05     /  /                                    0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WAPPINGERS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-21-01-06
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Kinry Road Elementary:
07-0817   Reconstruction               0-002-013  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   155                      108,970             0  HCM             0           0       45,730
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Evans Elementary School:
04-1480   Reconstruction               0-003-016  08/09/05     DONE    DONE       DONE      06/29/05   06/27/05   04/15/05   05/17/05   155,15,16                215,680       215,680  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0130   Reconstruction               0-003-017  09/12/07     DONE    DONE       DONE      08/06/07   08/03/07   04/18/07   05/15/07   8,155                     88,450        88,450  HCM             0           0       37,150
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Junior High School:
  -       Reconstruction               0-004-025                                              /  /       /  /     07/31/06     /  /     2,4,7,8,9,10,13,14,1           0    15,540,132  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Vassar Road Elementary:
06-0300   Reconstruction               0-008-017  10/25/06     DONE    DONE       DONE      10/05/06   10/04/06   07/31/06   05/16/06   7                      1,059,796     1,059,796  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0818   Reconstruction               0-008-018  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,155,15,16               23,229             0  HCM             0           0        9,756
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Ketcham Senior High School:
03-0435   Reconstruction               0-012-020  04/09/04     DONE    DONE       DONE      10/09/03   10/07/03   08/29/03   06/03/03   2,4,7,8,9,155,15,16      771,996       771,996  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0129   Reconstruction               0-012-021  11/13/07     DONE    DONE       DONE      08/06/07   08/03/07   04/18/07   05/15/07   4,8,9,10,155,15,16       275,622             0  HCM             0           0      115,762
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0145   Reconstruction               0-012-022  10/25/07     DONE    DONE       DONE      08/08/07   08/03/07   08/08/07   05/15/07                            163,310       163,310  HCM             0           0       68,591
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1771   Reconstruction               0-012-023  09/22/08     DONE    DONE       DONE      03/08/08   03/05/08   08/08/07   05/15/07   10                     1,408,290             0  HCM             0           0      301,551
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
02-1898FP Reconstruction               0-012-FP1  10/21/03     DONE    DONE       DONE      04/16/03     /  /       /  /       /  /     16                        17,100        17,100  MGL             0           0            0
                                                                                                                                                                                                                                                                     
04-0099SC Visual Structural Inspection 0-012-SC1  08/06/04     DONE    DONE       DONE      08/02/04   08/02/04     /  /       /  /     16                        25,806        16,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
04-0335SC Visual Structural Inspection 0-012-SC2  12/01/04     DONE    DONE       DONE      10/27/04   10/27/04     /  /       /  /     16                        47,360        47,360  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Brinckerhoff Elementary:
06-0301   Reconstruction               0-013-016  10/25/06     DONE    DONE       DONE      10/05/06   10/04/06   07/31/06   05/16/06   7,15                   1,401,063     1,401,063  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0819   Reconstruction               0-013-017  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,155,15,16              424,560             0  HCM             0           0      178,315
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Oak Grove Elementary:
07-0820   Reconstruction               0-014-015  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,7,155,15,16            403,322             0  HCM             0           0      169,395
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0808   Reconstruction               0-014-016  11/21/07     DONE    DONE       DONE      11/15/07   11/14/07   08/30/07   05/15/07   7                      1,132,160     1,132,160  HCM             0           0      475,500
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Gayhead Elementary:
04-0575   Reconstruction               0-016-014  01/10/05     DONE    DONE       DONE      12/22/04   12/17/04   09/08/04   05/18/04   7                        816,551       816,551  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0150   Reconstruction               0-016-015  08/09/06     DONE    DONE       DONE      08/07/06   08/04/06   07/31/06   06/26/06   15,16                    265,000       265,000  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-0821   Reconstruction               0-016-016  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,155,15,16              475,507             0  HCM             0           0      199,727
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
02-1902FP Reconstruction               0-016-FP1  10/20/03     DONE    DONE       DONE      04/16/03     /  /       /  /       /  /     16                         4,275         4,275  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Van Wyck Junior High School:
04-1338   Reconstruction               0-017-016  08/10/05     DONE    DONE       DONE      05/27/05   05/26/05   04/12/05   05/18/04   2,15                      39,000        39,000  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
06-0525   Reconstruction               0-017-017  12/01/06     DONE    DONE       DONE      11/20/06   11/17/06   07/31/06   05/16/06   15                       642,183       642,183  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
  -       Additions and Alterations    0-017-018                                              /  /       /  /     07/31/06     /  /     02 - 16                        0    26,049,232  HCM             0           0            0
                                                                                                                                                                                                                                                                     
03-0191FP Reconstruction               0-017-FP1  10/14/03     DONE    DONE       DONE      08/15/03     /  /       /  /       /  /     16                         4,275         4,275  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Sheafe Road Elementary:
07-0822   Reconstruction               0-018-012  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,155,15,16              239,876             0  HCM             0           0      100,748
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Myers Corners Elementary:
07-0823   Reconstruction               0-019-016  02/04/08     DONE    DONE       DONE      11/16/07   11/15/07   04/18/07   05/15/07   2,155,15,16              806,664             0  HCM             0           0      338,799
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          John Jay High School:
04-1339   Reconstruction               0-020-024  08/10/05     DONE    DONE       DONE      05/27/05   05/26/05   04/12/05   05/18/04   2,15                      75,000        75,000  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
05-1416   Reconstruction               0-020-025  07/15/02     DONE    DONE       DONE      06/27/06   06/23/06     /  /     04/26/06   2                        774,255       774,255  HCM             0           0            0
                                                                                                                                                                                                                                 Jack Eisenbach - Engineer           
07-1772   Additions and Alterations    0-020-026  09/22/08     DONE    DONE       DONE      03/08/08   03/05/08   04/18/07   05/15/07   02 - 16                4,602,396             0  HCM             0           0    1,933,000
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
07-1747   Reconstruction               0-020-027  05/14/08     DONE    DONE       DONE      03/04/08   02/29/08   02/01/08   12/18/07   15                       250,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.
02-1899FP Reconstruction               0-020-FP1  03/22/04     DONE    DONE       DONE      04/16/03     /  /       /  /       /  /     16                        21,375        21,375  MGL             0           0            0
                                                                                                                                                                                                                                                                     
06-0046SC Visual Structural Inspection 0-020-SC1  08/09/06     DONE    DONE       DONE      05/17/06   05/17/06     /  /       /  /     16                        73,036        64,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Modulars 1 & 2 @ Van Wyck Jr. HS:
03-1517   New Construction             0-040-001  06/15/04     DONE    DONE       DONE      05/05/04   05/04/04   03/25/04   05/18/04   02 - 16                  370,025             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Mods. 1 & 2 @ Gayhead Elem.:
03-1518   New Construction             0-041-001  06/15/04     DONE    DONE       DONE      05/05/04   05/04/04   03/25/04   05/18/04   02 - 16                  285,490             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Land Acquisition/New School Facility:
  -    XX New Construction             0-042-001                         CANCELLED            /  /       /  /     11/05/04     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          :
  -    PR New Construction             0-045-001                                              /  /       /  /     12/01/05     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Portable #1 @ Fishkill ES:
07-1624   New Construction             0-046-001  04/02/08     DONE    DONE       DONE      02/14/08   02/12/08   12/26/07   12/18/07   02 - 16                  625,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Athletic Storage @ Ketcham HS:
04-1102   New Construction             2-043-001  06/15/05     DONE    DONE       DONE      04/06/05   04/05/05   11/05/04   11/08/04   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Dodge Chamberlin Luzine Weber, Arch.

          Bus Garage (lease):
04-0483   Reconstruction               5-038-L02  11/23/04     DONE    DONE       DONE      12/08/04   11/15/04   12/08/04   01/27/04                            435,000       435,000  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Orchard View School & Administration:
05-0225TQ Temporary Quarters           8-044-001                       ADDENDUM REQ'D       09/28/05   09/21/05   05/26/05     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




MILLBROOK CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-22-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior/Senior High School:
04-0043   Reconstruction               0-008-006  07/26/04     DONE    DONE       DONE      07/07/04   07/02/04   08/09/01   06/21/04   9,10                     165,900       165,900  MAC             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-008-007                                              /  /       /  /     09/13/07     /  /     2,10,15                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-1996   Reconstruction               0-008-008  05/22/08     DONE    DONE       DONE      04/18/08   04/10/08   02/21/08   10/29/07   2,155                    504,827             0  HCM             0           0      388,717
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-008-009                                              /  /       /  /     08/11/08     /  /     2,8,155,15,16                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0609SC Visual Structural Inspection 0-008-SC1  06/25/07     DONE    DONE       DONE      08/17/06   08/17/06     /  /       /  /     16                         9,744             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Elm Drive Elementary School:
04-0044   Reconstruction               0-010-010  07/26/04     DONE    DONE       DONE      07/07/04   07/02/04     /  /     06/21/04   2,9                       21,848        21,848  MAC             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-010-011                                              /  /       /  /     08/11/08     /  /     2,8,155,15,16                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0611SC Visual Structural Inspection 0-010-SC1  06/25/07     DONE    DONE       DONE      08/17/06   08/17/06     /  /       /  /     16                         4,331             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Alden Place Elementary:
07-1725   Reconstruction               0-011-009  05/13/08     DONE    DONE       DONE      03/03/08   02/26/08   01/31/08     /  /     2,13,15                   58,145             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          
  -       Reconstruction               0-011-010                                              /  /       /  /     08/11/08     /  /     2,8,155,15,16                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
06-0610SC Visual Structural Inspection 0-011-SC1  06/25/07     DONE    DONE       DONE      08/17/06   08/17/06     /  /       /  /     16                         4,331             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New High School:
04-0602   New Construction             0-031-001  03/07/05     DONE    DONE       DONE      12/28/04   12/20/04   01/09/02   03/09/04   02 - 16               20,795,000    11,895,781  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Associates          


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES DUTCHESS STATUS REPORT ON CAPITAL PROJECTS
District No.: 13-90-00-00
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Special Education Center:
  -       Reconstruction               0-001-019                                              /  /       /  /     12/18/03     /  /     2,4,15                         0       335,640  MAC             0           0            0
                                                                                                                                                                                                                                                                     
05-0781   Reconstruction               0-001-020  04/20/06     DONE    DONE       DONE      02/16/06   02/15/06   04/06/05   04/30/05   2,9,10,155,15,16         371,056       371,056  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              
  -       Reconstruction               0-001-021                                              /  /       /  /     08/09/05     /  /     2,155,15,16                    0       335,640  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0078   Reconstruction               0-001-022  11/07/06     DONE    DONE       DONE      07/19/06   07/05/06   03/24/06   04/30/06   4,9,155,16               325,000       325,000  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              
06-0076   Reconstruction               0-001-023  10/26/06     DONE    DONE       DONE      07/19/06   07/05/06   07/17/06   04/30/06   15,16                    260,000       260,000  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Area Occupational Center:
06-0079XX Reconstruction               0-003-021  11/07/06               CANCELLED          07/19/06   07/05/06   11/15/00   04/30/06   155,16                         0    17,383,742  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              
06-0077   Reconstruction               0-003-022  10/26/06     DONE    DONE       DONE      07/19/06   07/05/06   07/17/06   04/30/06   15,16                    750,000       750,000  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Alt. Ed. Bldg. @ Salt Point Campus:
  -    PR New Construction             0-042-001                                              /  /       /  /     11/26/07     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Administration Bldg.:
  -    PR Alterations                  1-002-011                                              /  /       /  /     04/21/06     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0080XX Alterations                  1-002-011  11/07/06               CANCELLED          07/19/06   07/05/06   04/21/06   04/30/06   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Rhinebeck Architecture              

          Special Ed. @ South Hills Mall:
03-0097TQ Temporary Quarters           8-038-001  02/26/04     DONE    DONE       DONE      07/30/03     /  /     07/30/03     /  /                                    0             0  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          :
  -       Reconstruction               8-039-L01                                              /  /       /  /     08/01/05     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          OBSERVATORY @ VASSAR COLLEGE:
  -    TQ Temporary Quarters           8-040-001