Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 07/24/08 at 08:56:28




AFTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-01-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
03-0071FP Reconstruction               0-001-FP1  09/30/03     DONE    DONE       DONE      07/23/03     /  /       /  /       /  /     16                        11,548        11,548  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage & Ag. Shop:
03-0256   Reconstruction               0-003-004  01/14/04     DONE    DONE       DONE      09/08/03   08/29/03   05/19/03   09/29/03   7                        172,546       172,546  JOD             0           0            0
                                                                                                                                                                                                                                 William F. Taylor, P.C.             

          Storage Bldg. @ Athletic Fields:
  -    DB Discovered Building          2-007-001                                              /  /       /  /     05/27/08     /  /                                    0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BAINBRIDGE-GUILFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-02-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          High School:
  -    PR Additions and Alterations    0-001-017                                              /  /       /  /     02/13/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Greenlawn Elementary:
03-0855   Reconstruction               0-002-011  08/21/03     DONE    DONE       DONE      12/22/03   12/12/03   08/21/03   08/19/03   2                         54,800        54,800  HCM             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -       Reconstruction               0-002-012                                              /  /       /  /     02/13/07     /  /     2,4,7,8,9,155,15,16            0     8,120,196  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Elementary School:
  -       Reconstruction               0-003-010                                              /  /       /  /     02/13/07     /  /     2,4,7,8,9,155,15,16            0     2,781,919  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Technology/Storage Building:
  -       Reconstruction               0-004-003                                              /  /       /  /     02/13/07     /  /     7                              0     3,356,412  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GREENE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-06-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          MS/HS 6-12:
04-0787   Reconstruction               0-002-014  03/17/05     DONE    DONE       DONE      02/08/05   02/07/05   03/23/04   11/16/04   2,7,9,10,16            1,213,001     1,213,001  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0947   Reconstruction               0-002-015  09/18/06     DONE    DONE       DONE      03/14/06   03/13/06   01/18/06   11/16/04   2,7,16                   673,343       673,343  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-002-016                                              /  /       /  /     10/25/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Intermediate School:
04-0788   Reconstruction               0-003-012  03/17/05     DONE    DONE       DONE      02/08/05   02/07/05   03/23/04   11/16/04   2,16                     697,962       697,962  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0948   Reconstruction               0-003-013  09/18/06     DONE    DONE       DONE      03/14/06   03/13/06   02/22/06   11/16/04   8,16                     246,000       246,000  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-003-014                                              /  /       /  /     10/25/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Primary School:
04-0789   Reconstruction               0-004-011  03/17/05     DONE    DONE       DONE      02/08/05   02/07/05   03/23/04   11/16/04   2,16                     978,653       978,653  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0949   Reconstruction               0-004-012  09/18/06     DONE    DONE       DONE      03/14/06   03/13/06   02/22/06   11/16/04   8                        479,970       479,970  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    0-004-013                                              /  /       /  /     10/23/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-004-014                                              /  /       /  /     10/24/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Canal St. Pole Barn:
04-0790   Additions and Alterations    2-006-002  03/17/05     DONE    DONE       DONE      02/08/05   02/07/05   08/19/04   11/16/04   02 - 16                   37,489             0  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Ball Flats - Storage Facility:
07-0163   New Construction             2-015-001  09/12/07     DONE    DONE       DONE      08/16/07   08/15/07   07/23/07   08/08/07   02 - 16                   58,000             0  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Bus Garage:
04-0791   Additions and Alterations    5-005-008  03/17/05     DONE    DONE       DONE      02/08/05   02/07/05   03/23/04   11/16/04   02 - 16                  617,233       617,233  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
05-0950   Reconstruction               5-005-009  09/18/06     DONE    DONE       DONE      03/14/06   03/13/06   01/18/06   11/16/04   15                        33,825        33,825  HCM             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
  -    PR Additions and Alterations    5-005-010                                              /  /       /  /     10/25/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Additions and Alterations    5-005-011                                              /  /       /  /     10/29/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Districtwide:
  -       Reconstruction               7-999-003                                              /  /       /  /     10/23/07     /  /     155                            0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               7-999-004                                              /  /       /  /     10/25/07     /  /     10,13,14,155,16                0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




UNADILLA VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-10-03-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Pre K-12 Building:
04-0085   Additions and Alterations    0-014-002  09/03/04     DONE    DONE       DONE      07/26/04   07/23/04   03/23/04   05/18/04   02 - 16                   86,276        86,276  RDR             0           0            0
                                                                                                                                                                                                                                 Ashley McGraw Architects            
  -       Reconstruction               0-014-003                                              /  /       /  /     07/25/05     /  /     4,7                            0    40,773,053  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-014-004                                              /  /       /  /     02/27/08     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Transportation Facility:
  -    PR Additions and Alterations    5-015-002                                              /  /       /  /     02/27/08     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          CONCESSION STAND:
  -    PR New Construction             7-016-001                                              /  /       /  /     02/15/06     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               7-016-002                                              /  /       /  /     02/27/08     /  /     2,4,7,8,9,155,15,16            0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORWICH CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-12-00-05
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Stanford J. Gibson School:
06-0668   Reconstruction               0-002-007  03/22/07     DONE    DONE       DONE      12/27/06   12/22/06   01/09/06   03/14/06   155,15,16              2,087,625     1,741,673  JOD             0           0       85,593
                                                                                                                                                                                                                                 Thomas Associates                   
02-2233FP Reconstruction               0-002-FP1  08/19/03     DONE    DONE       DONE      05/21/03     /  /       /  /       /  /     16                         5,100         5,100  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Browne School:
06-0669   Reconstruction               0-004-008  03/22/07     DONE    DONE       DONE      12/27/06   12/22/06   01/09/06   03/14/06   155,15,16              2,137,960     2,366,030  JOD             0           0       87,656
                                                                                                                                                                                                                                 Thomas Associates                   
02-2232FP Reconstruction               0-004-FP1  08/19/03     DONE    DONE       DONE      05/27/04   05/27/04     /  /       /  /     16                         5,100         5,100  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Norwich Senior High School:
  -    XX Additions and Alterations    0-008-007                         CANCELLED            /  /       /  /     06/03/04     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-008-008                                              /  /       /  /     09/08/05     /  /     155,16                         0    13,576,638  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-008-009                                              /  /       /  /     09/20/05     /  /     155                            0    13,576,638  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0670   Reconstruction               0-008-010  03/22/07     DONE    DONE       DONE      12/27/06   12/22/06   01/09/06   03/14/06   155,15,16             30,725,259    30,927,912  JOD             0           0    1,259,736
                                                                                                                                                                                                                                 Thomas Associates                   
06-0002   Reconstruction               0-008-011  07/12/06     DONE    DONE       DONE      07/06/06   07/03/06   06/22/06   03/14/06   15                        97,400        35,000  JOD             0           0       97,400
                                                                                                                                                                                                                                 Thomas Associates                   
02-2230FP Reconstruction               0-008-FP1  08/19/03     DONE    DONE       DONE      05/21/03     /  /       /  /       /  /     16                        10,400        10,400  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Norwich Middle School:
  -       Reconstruction               0-009-004                                              /  /       /  /       /  /       /  /     2,4,8,9,10,13,155,15           0    12,303,798  JOD             0           0            0
                                                                                                                                                                                                                                                                     
  -    PR Additions and Alterations    0-009-005                                              /  /       /  /     01/09/06     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     
06-0671XX Additions and Alterations    0-009-005  03/22/07               CANCELLED          12/27/06   12/22/06   01/09/06   03/14/06   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
02-2231FP Reconstruction               0-009-FP1  08/19/03     DONE    DONE       DONE      05/21/03     /  /       /  /       /  /     16                         4,900         4,900  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Storage Building  @ High School:
  -    PR New Construction             2-034-001                                              /  /       /  /     04/24/08     /  /     02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Storage Bldg. #2:
06-0672   Reconstruction               4-012-002  03/22/07     DONE    DONE       DONE      12/27/06   12/22/06   01/13/06   03/14/06   16                       211,256       223,887  JOD             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          Guernsey Mem. Library:
03-0685   Reconstruction               6-022-002  04/08/04     DONE    DONE       DONE      11/13/03   11/07/03   04/10/00   10/07/03   155                      390,027             0  MGL             0           0            0
                                                                                                                                                                                                                                 St. John Associates                 
05-1287   Reconstruction               6-022-003  09/21/06     DONE    DONE       DONE      05/24/06   05/22/06   10/27/05   02/16/06   2,8,155,16               760,000             0  JOD             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   

          High School Press Box:
06-1259   New Construction             7-033-001  04/03/07     DONE    DONE       DONE      04/03/07   03/21/07   03/22/07   03/14/06   02 - 16                   40,500             0  JOD             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GEORGETOWN-SOUTH OTSELIC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-14-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior Senior High School:
  -    PR Additions and Alterations    0-001-006                                              /  /       /  /     06/10/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




OXFORD ACADEMY & CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-15-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Oxford Middle School:
03-1058   Reconstruction               0-002-012  04/20/04     DONE    DONE       DONE      01/30/04   01/28/04   08/10/00   02/15/00   2,9                       69,320        69,320  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
04-1353   Reconstruction               0-002-013  08/09/05     DONE    DONE       DONE      06/02/05   05/31/05   11/29/04   05/09/05   2,16                      38,060        38,060  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
06-1400   Reconstruction               0-002-014  05/10/07     DONE    DONE       DONE      05/03/07   04/24/07   07/05/06   07/20/06   8,9,155,15,16          1,018,303     1,018,303  MGL             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
03-0355FP Reconstruction               0-002-FP1  10/20/03     DONE    DONE       DONE      10/02/03     /  /       /  /       /  /     16                         9,640         9,640  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Primary School:
03-1059   Reconstruction               0-010-011  04/20/04     DONE    DONE       DONE      01/30/04   01/28/04   09/04/02   02/15/00   2,7,9,155,16             536,189       536,189  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
04-1354   Reconstruction               0-010-012  08/09/05     DONE    DONE       DONE      06/02/05   05/31/05   08/25/04   05/09/05   2,4,8,9,10,155,15,16     186,940       186,940  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
03-0356FP Reconstruction               0-010-FP1  10/20/03     DONE    DONE       DONE      10/02/03     /  /       /  /       /  /     16                         4,820         4,820  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          District Office Adm. Building:
  -    XX Reconstruction               1-012-005                         CANCELLED            /  /       /  /     11/22/04     /  /     2,13,15,16                     0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Storage 2-Wood:
  -    DB Discovered Building          2-017-001                                              /  /       /  /     10/26/06     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Barn:
  -    DB Discovered Building          2-018-001                                              /  /       /  /     10/26/06     /  /                                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SHERBURNE EARLVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 08-20-01-04
last updated on 07/24/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
03-0412   Reconstruction               0-012-006  03/04/04     DONE    DONE       DONE      10/03/03   09/24/03   11/25/98   06/28/00   2,155,16               1,111,200     1,111,200  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
04-0682XX Reconstruction               0-012-008  03/09/05               CANCELLED          01/13/05   01/12/05   09/23/04   06/28/00   2,9,155,16               132,350       132,350  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
05-0939   Reconstruction               0-012-009  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/23/05   09/20/05   2,4,7,8,9,10,13,14,1   3,480,400     3,480,400  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -       Reconstruction               0-012-010                                              /  /       /  /     11/16/07     /  /     2,4,7,8,9,10,155,15,           0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          New Elementary School:
04-0683XX Reconstruction               0-018-003  03/09/05               CANCELLED          01/13/05   01/12/05   09/23/04   06/28/00   9,155,16                  56,150        56,150  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -    PR Additions and Alterations    0-018-004                                              /  /       /  /     08/23/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
05-0940   Additions and Alterations    0-018-004  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/23/05   09/20/05   02 - 16                1,319,400     1,319,400  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -    PR Additions and Alterations    0-018-005                                              /  /       /  /     11/16/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-018-006                                              /  /       /  /     04/25/08     /  /     2,9,155,15,16                  0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          :
  -       New Construction             2-023-001                                              /  /       /  /     08/22/05     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Storage:
05-0941   Additions and Alterations    4-020-002  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/23/05   09/20/05   02 - 16                  377,000       377,000  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -       Reconstruction               4-020-003                                              /  /       /  /     11/16/07     /  /     2,155,15,16                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Maintenance:
05-0942   Reconstruction               5-019-002  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/23/05   09/20/05   2,9,155,15,16             80,000        80,000  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             
  -       Reconstruction               5-019-003                                              /  /       /  /     11/16/07     /  /     2,7,9,13,155,15,16             0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Press Box:
05-0943   Reconstruction               7-021-002  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/23/05   09/20/05   2,16                      20,000             0  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          :
05-0944   New Construction             7-022-001  06/27/06     DONE    DONE       DONE      03/13/06   03/03/06   08/22/05   09/20/05   02 - 16                  223,200             0  RDR             0           0            0
                                                                                                                                                                                                                                 Bearsch Compeau Knudson             

          Concession/Restroom Building:
  -       New Construction             7-024-001                                              /  /       /  /     11/16/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED