AFTON 080101
BAINBRIDGE GUI 080201
GRGETWN-SO OTS 081401
GREENE 080601
NEW BERLIN 081001
NORWICH 081200
OXFORD 081501
SHERBURNE EARL 082001
SO NEW BERLIN 081002
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
03-0071FP Reconstruction 0-001-FP1 09/30/03 DONE DONE DONE 07/23/03 / / / / / / 16 11,548 11,548 JOD 0 0 0
Bus Garage & Ag. Shop:
03-0256 Reconstruction 0-003-004 01/14/04 DONE DONE DONE 09/08/03 08/29/03 05/19/03 09/29/03 7 172,546 172,546 JOD 0 0 0
William F. Taylor, P.C.
Storage Bldg. @ Athletic Fields:
- DB Discovered Building 2-007-001 / / / / 05/27/08 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
- PR Additions and Alterations 0-001-017 / / / / 02/13/07 / / 02 - 16 0 0 HCM 0 0 0
Greenlawn Elementary:
03-0855 Reconstruction 0-002-011 08/21/03 DONE DONE DONE 12/22/03 12/12/03 08/21/03 08/19/03 2 54,800 54,800 HCM 0 0 0
Bearsch Compeau Knudson
- Reconstruction 0-002-012 / / / / 02/13/07 / / 2,4,7,8,9,155,15,16 0 8,120,196 HCM 0 0 0
Elementary School:
- Reconstruction 0-003-010 / / / / 02/13/07 / / 2,4,7,8,9,155,15,16 0 2,781,919 HCM 0 0 0
Technology/Storage Building:
- Reconstruction 0-004-003 / / / / 02/13/07 / / 7 0 3,356,412 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
MS/HS 6-12:
04-0787 Reconstruction 0-002-014 03/17/05 DONE DONE DONE 02/08/05 02/07/05 03/23/04 11/16/04 2,7,9,10,16 1,213,001 1,213,001 MAC 0 0 0
Thomas Associates
05-0947 Reconstruction 0-002-015 09/18/06 DONE DONE DONE 03/14/06 03/13/06 01/18/06 11/16/04 2,7,16 673,343 673,343 HCM 0 0 0
Thomas Associates
- PR Additions and Alterations 0-002-016 / / / / 10/25/07 / / 02 - 16 0 0 HCM 0 0 0
Intermediate School:
04-0788 Reconstruction 0-003-012 03/17/05 DONE DONE DONE 02/08/05 02/07/05 03/23/04 11/16/04 2,16 697,962 697,962 MAC 0 0 0
Thomas Associates
05-0948 Reconstruction 0-003-013 09/18/06 DONE DONE DONE 03/14/06 03/13/06 02/22/06 11/16/04 8,16 246,000 246,000 HCM 0 0 0
Thomas Associates
- PR Additions and Alterations 0-003-014 / / / / 10/25/07 / / 02 - 16 0 0 HCM 0 0 0
Primary School:
04-0789 Reconstruction 0-004-011 03/17/05 DONE DONE DONE 02/08/05 02/07/05 03/23/04 11/16/04 2,16 978,653 978,653 MAC 0 0 0
Thomas Associates
05-0949 Reconstruction 0-004-012 09/18/06 DONE DONE DONE 03/14/06 03/13/06 02/22/06 11/16/04 8 479,970 479,970 HCM 0 0 0
Thomas Associates
- PR Additions and Alterations 0-004-013 / / / / 10/23/07 / / 02 - 16 0 0 HCM 0 0 0
- PR Additions and Alterations 0-004-014 / / / / 10/24/07 / / 02 - 16 0 0 HCM 0 0 0
Canal St. Pole Barn:
04-0790 Additions and Alterations 2-006-002 03/17/05 DONE DONE DONE 02/08/05 02/07/05 08/19/04 11/16/04 02 - 16 37,489 0 MAC 0 0 0
Thomas Associates
Ball Flats - Storage Facility:
07-0163 New Construction 2-015-001 09/12/07 DONE DONE DONE 08/16/07 08/15/07 07/23/07 08/08/07 02 - 16 58,000 0 HCM 0 0 0
Thomas Associates
Bus Garage:
04-0791 Additions and Alterations 5-005-008 03/17/05 DONE DONE DONE 02/08/05 02/07/05 03/23/04 11/16/04 02 - 16 617,233 617,233 MAC 0 0 0
Thomas Associates
05-0950 Reconstruction 5-005-009 09/18/06 DONE DONE DONE 03/14/06 03/13/06 01/18/06 11/16/04 15 33,825 33,825 HCM 0 0 0
Thomas Associates
- PR Additions and Alterations 5-005-010 / / / / 10/25/07 / / 02 - 16 0 0 HCM 0 0 0
- Additions and Alterations 5-005-011 / / / / 10/29/07 / / 02 - 16 0 0 HCM 0 0 0
Districtwide:
- Reconstruction 7-999-003 / / / / 10/23/07 / / 155 0 0 HCM 0 0 0
- Reconstruction 7-999-004 / / / / 10/25/07 / / 10,13,14,155,16 0 0 HCM 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New Pre K-12 Building:
04-0085 Additions and Alterations 0-014-002 09/03/04 DONE DONE DONE 07/26/04 07/23/04 03/23/04 05/18/04 02 - 16 86,276 86,276 RDR 0 0 0
Ashley McGraw Architects
- Reconstruction 0-014-003 / / / / 07/25/05 / / 4,7 0 40,773,053 MGL 0 0 0
- PR Additions and Alterations 0-014-004 / / / / 02/27/08 / / 02 - 16 0 0 MGL 0 0 0
Bus Transportation Facility:
- PR Additions and Alterations 5-015-002 / / / / 02/27/08 / / 02 - 16 0 0 MGL 0 0 0
CONCESSION STAND:
- PR New Construction 7-016-001 / / / / 02/15/06 / / 02 - 16 0 0 MGL 0 0 0
- Reconstruction 7-016-002 / / / / 02/27/08 / / 2,4,7,8,9,155,15,16 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Stanford J. Gibson School:
06-0668 Reconstruction 0-002-007 03/22/07 DONE DONE DONE 12/27/06 12/22/06 01/09/06 03/14/06 155,15,16 2,087,625 1,741,673 JOD 0 0 85,593
Thomas Associates
02-2233FP Reconstruction 0-002-FP1 08/19/03 DONE DONE DONE 05/21/03 / / / / / / 16 5,100 5,100 MGL 0 0 0
Browne School:
06-0669 Reconstruction 0-004-008 03/22/07 DONE DONE DONE 12/27/06 12/22/06 01/09/06 03/14/06 155,15,16 2,137,960 2,366,030 JOD 0 0 87,656
Thomas Associates
02-2232FP Reconstruction 0-004-FP1 08/19/03 DONE DONE DONE 05/27/04 05/27/04 / / / / 16 5,100 5,100 MGL 0 0 0
Norwich Senior High School:
- XX Additions and Alterations 0-008-007 CANCELLED / / / / 06/03/04 / / 02 - 16 0 0 JOD 0 0 0
- Reconstruction 0-008-008 / / / / 09/08/05 / / 155,16 0 13,576,638 JOD 0 0 0
- Reconstruction 0-008-009 / / / / 09/20/05 / / 155 0 13,576,638 JOD 0 0 0
06-0670 Reconstruction 0-008-010 03/22/07 DONE DONE DONE 12/27/06 12/22/06 01/09/06 03/14/06 155,15,16 30,725,259 30,927,912 JOD 0 0 1,259,736
Thomas Associates
06-0002 Reconstruction 0-008-011 07/12/06 DONE DONE DONE 07/06/06 07/03/06 06/22/06 03/14/06 15 97,400 35,000 JOD 0 0 97,400
Thomas Associates
02-2230FP Reconstruction 0-008-FP1 08/19/03 DONE DONE DONE 05/21/03 / / / / / / 16 10,400 10,400 MGL 0 0 0
Norwich Middle School:
- Reconstruction 0-009-004 / / / / / / / / 2,4,8,9,10,13,155,15 0 12,303,798 JOD 0 0 0
- PR Additions and Alterations 0-009-005 / / / / 01/09/06 / / 02 - 16 0 0 JOD 0 0 0
06-0671XX Additions and Alterations 0-009-005 03/22/07 CANCELLED 12/27/06 12/22/06 01/09/06 03/14/06 02 - 16 0 0 JOD 0 0 0
Thomas Associates
02-2231FP Reconstruction 0-009-FP1 08/19/03 DONE DONE DONE 05/21/03 / / / / / / 16 4,900 4,900 MGL 0 0 0
Storage Building @ High School:
- PR New Construction 2-034-001 / / / / 04/24/08 / / 02 - 16 0 0 JOD 0 0 0
Bus Storage Bldg. #2:
06-0672 Reconstruction 4-012-002 03/22/07 DONE DONE DONE 12/27/06 12/22/06 01/13/06 03/14/06 16 211,256 223,887 JOD 0 0 0
Thomas Associates
Guernsey Mem. Library:
03-0685 Reconstruction 6-022-002 04/08/04 DONE DONE DONE 11/13/03 11/07/03 04/10/00 10/07/03 155 390,027 0 MGL 0 0 0
St. John Associates
05-1287 Reconstruction 6-022-003 09/21/06 DONE DONE DONE 05/24/06 05/22/06 10/27/05 02/16/06 2,8,155,16 760,000 0 JOD 0 0 0
Thomas Associates
High School Press Box:
06-1259 New Construction 7-033-001 04/03/07 DONE DONE DONE 04/03/07 03/21/07 03/22/07 03/14/06 02 - 16 40,500 0 JOD 0 0 0
Thomas Associates
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior Senior High School:
- PR Additions and Alterations 0-001-006 / / / / 06/10/08 / / 02 - 16 0 0 DDJ 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Oxford Middle School:
03-1058 Reconstruction 0-002-012 04/20/04 DONE DONE DONE 01/30/04 01/28/04 08/10/00 02/15/00 2,9 69,320 69,320 RDR 0 0 0
Bearsch Compeau Knudson
04-1353 Reconstruction 0-002-013 08/09/05 DONE DONE DONE 06/02/05 05/31/05 11/29/04 05/09/05 2,16 38,060 38,060 RDR 0 0 0
Bearsch Compeau Knudson
06-1400 Reconstruction 0-002-014 05/10/07 DONE DONE DONE 05/03/07 04/24/07 07/05/06 07/20/06 8,9,155,15,16 1,018,303 1,018,303 MGL 0 0 0
Thomas Associates
03-0355FP Reconstruction 0-002-FP1 10/20/03 DONE DONE DONE 10/02/03 / / / / / / 16 9,640 9,640 MGL 0 0 0
Primary School:
03-1059 Reconstruction 0-010-011 04/20/04 DONE DONE DONE 01/30/04 01/28/04 09/04/02 02/15/00 2,7,9,155,16 536,189 536,189 RDR 0 0 0
Bearsch Compeau Knudson
04-1354 Reconstruction 0-010-012 08/09/05 DONE DONE DONE 06/02/05 05/31/05 08/25/04 05/09/05 2,4,8,9,10,155,15,16 186,940 186,940 RDR 0 0 0
Bearsch Compeau Knudson
03-0356FP Reconstruction 0-010-FP1 10/20/03 DONE DONE DONE 10/02/03 / / / / / / 16 4,820 4,820 MGL 0 0 0
District Office Adm. Building:
- XX Reconstruction 1-012-005 CANCELLED / / / / 11/22/04 / / 2,13,15,16 0 0 MGL 0 0 0
Storage 2-Wood:
- DB Discovered Building 2-017-001 / / / / 10/26/06 / / 0 0 MGL 0 0 0
Barn:
- DB Discovered Building 2-018-001 / / / / 10/26/06 / / 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
03-0412 Reconstruction 0-012-006 03/04/04 DONE DONE DONE 10/03/03 09/24/03 11/25/98 06/28/00 2,155,16 1,111,200 1,111,200 RDR 0 0 0
Bearsch Compeau Knudson
04-0682XX Reconstruction 0-012-008 03/09/05 CANCELLED 01/13/05 01/12/05 09/23/04 06/28/00 2,9,155,16 132,350 132,350 RDR 0 0 0
Bearsch Compeau Knudson
05-0939 Reconstruction 0-012-009 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/23/05 09/20/05 2,4,7,8,9,10,13,14,1 3,480,400 3,480,400 RDR 0 0 0
Bearsch Compeau Knudson
- Reconstruction 0-012-010 / / / / 11/16/07 / / 2,4,7,8,9,10,155,15, 0 0 MGL 0 0 0
New Elementary School:
04-0683XX Reconstruction 0-018-003 03/09/05 CANCELLED 01/13/05 01/12/05 09/23/04 06/28/00 9,155,16 56,150 56,150 RDR 0 0 0
Bearsch Compeau Knudson
- PR Additions and Alterations 0-018-004 / / / / 08/23/05 / / 02 - 16 0 0 MGL 0 0 0
05-0940 Additions and Alterations 0-018-004 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/23/05 09/20/05 02 - 16 1,319,400 1,319,400 RDR 0 0 0
Bearsch Compeau Knudson
- PR Additions and Alterations 0-018-005 / / / / 11/16/07 / / 02 - 16 0 0 MGL 0 0 0
- Reconstruction 0-018-006 / / / / 04/25/08 / / 2,9,155,15,16 0 0 DDJ 0 0 0
:
- New Construction 2-023-001 / / / / 08/22/05 / / 02 - 16 0 0 MGL 0 0 0
New Bus Storage:
05-0941 Additions and Alterations 4-020-002 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/23/05 09/20/05 02 - 16 377,000 377,000 RDR 0 0 0
Bearsch Compeau Knudson
- Reconstruction 4-020-003 / / / / 11/16/07 / / 2,155,15,16 0 0 MGL 0 0 0
New Bus Maintenance:
05-0942 Reconstruction 5-019-002 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/23/05 09/20/05 2,9,155,15,16 80,000 80,000 RDR 0 0 0
Bearsch Compeau Knudson
- Reconstruction 5-019-003 / / / / 11/16/07 / / 2,7,9,13,155,15,16 0 0 MGL 0 0 0
Press Box:
05-0943 Reconstruction 7-021-002 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/23/05 09/20/05 2,16 20,000 0 RDR 0 0 0
Bearsch Compeau Knudson
:
05-0944 New Construction 7-022-001 06/27/06 DONE DONE DONE 03/13/06 03/03/06 08/22/05 09/20/05 02 - 16 223,200 0 RDR 0 0 0
Bearsch Compeau Knudson
Concession/Restroom Building:
- New Construction 7-024-001 / / / / 11/16/07 / / 02 - 16 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED