AUBURN 050100
CATO MERIDIAN 050401
CAYUGA BOCES 059000
MORAVIA 051301
PORT BYRON 051101
SOUTHERN CAYUG 050701
UNION SPRINGS 051901
WEEDSPORT 050301
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Genesee Street School:
05-1188 Reconstruction 0-001-007 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 96,630 0 JOD 0 0 0
SWBR Architects P.C.
07-0501 Reconstruction 0-001-008 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,4,8,9,155,16 911,679 0 JOD 0 0 113,048
SWBR Architects P.C.
- Reconstruction 0-001-009 / / / / 06/25/07 / / 4,8,9,13,155 0 0 JOD 0 0 0
07-1642 Reconstruction 0-001-010 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
Herman Avenue School:
05-1189 Reconstruction 0-002-010 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 98,000 0 JOD 0 0 0
SWBR Architects P.C.
07-0502 Reconstruction 0-002-011 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,8,10,155,15,16 586,919 0 JOD 0 0 72,778
SWBR Architects P.C.
- Reconstruction 0-002-012 / / / / 06/25/07 / / 8,10,13,155,15 0 0 JOD 0 0 0
07-1643 Reconstruction 0-002-013 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
03-1403FP Reconstruction 0-002-FP1 04/14/05 DONE DONE DONE 04/14/04 / / / / / / 16 4,000 4,000 JOD 0 0 0
East Middle School:
04-0742 Reconstruction 0-004-014 07/25/05 DONE DONE DONE 02/01/05 02/01/05 11/13/03 11/13/03 10 851,691 851,691 JOD 0 0 0
Energy Concepts Engineering,P.C.
- XX Reconstruction 0-004-015 CANCELLED / / / / 03/12/04 / / 7 0 11,798,972 JOD 0 0 0
- XX Reconstruction 0-004-016 CANCELLED / / / / 03/29/04 / / 7 0 11,798,972 JOD 0 0 0
- XX Alterations 0-004-017 CANCELLED / / / / 12/10/04 / / 02 - 16 0 0 JOD 0 0 0
04-0958 Reconstruction 0-004-017 03/29/05 DONE DONE DONE 03/11/05 03/10/05 / / 03/31/99 290,500 290,500 0 0 0
Clark Patterson Associates
05-1190 Reconstruction 0-004-018 05/01/07 DONE DONE DONE 04/21/06 04/12/06 04/21/06 11/13/03 7,15,16 81,220 0 JOD 0 0 0
SWBR Architects P.C.
06-0370 Reconstruction 0-004-019 01/04/07 DONE DONE DONE 10/27/06 10/24/06 08/04/06 10/17/06 2,4,7,8,9,155,15,16 922,105 922,105 JOD 0 0 114,341
SWBR Architects P.C.
07-0503 Reconstruction 0-004-020 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,7,16 1,581,201 0 JOD 0 0 196,069
SWBR Architects P.C.
- Reconstruction 0-004-021 / / / / 06/25/07 / / 8,13,14,155,16 0 0 JOD 0 0 0
07-1644 Reconstruction 0-004-022 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
02-1733FP Reconstruction 0-004-FP1 10/20/03 DONE DONE DONE 03/27/03 / / / / / / 16 0 4,332,000 MGL 0 0 0
West Middle School:
05-1191 Reconstruction 0-006-006 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 131,476 0 JOD 0 0 0
SWBR Architects P.C.
07-0504 Reconstruction 0-006-007 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,4,8,9,155,15,16 1,410,481 0 JOD 0 0 174,900
SWBR Architects P.C.
- Reconstruction 0-006-008 / / / / 06/25/07 / / 8,13,155,15,16 0 0 JOD 0 0 0
07-1645 Reconstruction 0-006-009 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,16 0 0 JOD 0 0 0
SWBR Architects P.C.
02-1732FP Reconstruction 0-006-FP1 10/20/03 DONE DONE DONE 03/26/03 / / / / / / 16 0 4,170,000 MGL 0 0 0
Owasco Elementary:
03-1369 Reconstruction 0-010-009 04/28/04 DONE DONE DONE 04/07/04 04/06/04 03/12/04 03/31/99 7 590,000 590,000 JOD 0 0 0
Clark Patterson Associates
- XX Reconstruction 0-010-010 CANCELLED / / / / 03/29/04 / / 7 0 7,127,968 JOD 0 0 0
05-1192 Reconstruction 0-010-011 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 594,836 0 JOD 0 0 0
SWBR Architects P.C.
07-0505 Reconstruction 0-010-012 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,8,9,155,15,16 528,519 0 JOD 0 0 65,536
SWBR Architects P.C.
- Reconstruction 0-010-013 / / / / 06/25/07 / / 8,9,10,13,15,16 0 0 JOD 0 0 0
07-1646 Reconstruction 0-010-014 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
03-1402FP Reconstruction 0-010-FP1 04/14/05 DONE DONE DONE 04/15/04 / / / / / / 16 4,000 4,000 JOD 0 0 0
Casey Park Elementary:
05-1193 Reconstruction 0-012-009 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 116,611 0 JOD 0 0 0
SWBR Architects P.C.
07-0506 Reconstruction 0-012-010 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,8,10,155,16 1,082,339 0 JOD 0 0 134,210
SWBR Architects P.C.
- Reconstruction 0-012-011 / / / / 06/25/07 / / 8,13,155 0 0 JOD 0 0 0
07-1647 Reconstruction 0-012-012 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
03-1401FP Reconstruction 0-012-FP1 04/14/05 DONE DONE DONE 04/15/04 / / / / / / 16 4,000 4,000 JOD 0 0 0
Auburn High School:
- XX Reconstruction 0-015-010 CANCELLED / / / / 03/12/04 / / 7 0 49,070,653 JOD 0 0 0
- XX Reconstruction 0-015-011 CANCELLED / / / / 03/29/04 / / 7 0 49,070,653 JOD 0 0 0
05-1194 Reconstruction 0-015-012 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 2,338,537 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 0-015-013 / / / / 08/04/06 / / 2,4,8,9,10,155,15,16 0 49,070,653 JOD 0 0 0
06-0371 Reconstruction 0-015-014 01/04/07 DONE DONE DONE 10/27/06 10/24/06 08/04/06 10/17/06 2,7,16 3,068,385 2,302,000 JOD 0 0 380,480
SWBR Architects P.C.
07-0507 Reconstruction 0-015-015 03/31/08 DONE DONE DONE 10/09/07 10/05/07 06/25/07 10/17/06 2,4,7,8,13,155,15 1,431,411 0 JOD 0 0 177,495
SWBR Architects P.C.
07-1648 Reconstruction 0-015-016 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
02-1731FP Reconstruction 0-015-FP1 03/26/04 DONE DONE DONE 03/26/03 / / / / / / 16 0 16,842,000 MGL 0 0 0
Seward Elementary:
05-1195 Reconstruction 0-017-011 05/01/07 DONE DONE DONE 04/21/06 04/12/06 02/18/05 11/13/03 155,16 1,280,053 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 0-017-012 / / / / 08/04/06 / / 2,4,9,10,155,15,16 0 8,287,996 JOD 0 0 0
07-0508 Reconstruction 0-017-013 03/31/08 DONE DONE DONE 10/09/07 10/05/07 06/25/07 10/17/06 8,9,10,13,15,16 479,164 0 JOD 0 0 59,416
SWBR Architects P.C.
07-1649 Reconstruction 0-017-014 UNREVIEWED 02/19/08 02/15/08 11/21/07 01/22/08 8,155,16 0 0 JOD 0 0 0
SWBR Architects P.C.
03-1404FP Reconstruction 0-017-FP1 04/14/05 DONE DONE DONE 04/15/04 / / / / / / 16 4,989 4,989 JOD 0 0 0
Administartion Building:
07-0509 Reconstruction 1-005-005 03/31/08 DONE DONE DONE 10/09/07 10/05/07 08/04/06 10/17/06 2,7,8,9,155,15 621,543 0 JOD 0 0 0
SWBR Architects P.C.
- Reconstruction 1-005-006 / / / / 06/25/07 / / 7,8,13,155,15,16 0 0 JOD 0 0 0
07-1650 Reconstruction 1-005-007 UNREVIEWED 02/19/08 02/15/08 12/20/07 01/22/08 155,15 0 0 JOD 0 0 0
SWBR Architects P.C.
Equipment House@ Middle Sch:
05-0792DB Discovered Building 7-035-001 04/26/06 DONE DONE DONE 02/21/06 02/21/06 09/02/05 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
06-1588 Reconstruction 0-001-012 06/08/07 DONE DONE DONE 06/08/07 06/08/07 05/24/05 03/14/00 2,7,155,15,16 1,000,000 905,000 JOD 0 0 0
samuel J Cichello
Junior Senior High School:
06-0197 Reconstruction 0-002-017 08/30/06 DONE DONE DONE 08/30/06 08/30/06 05/24/05 03/14/00 155,15,16 367,000 367,000 JOD 0 0 0
samuel J Cichello
06-1589 Reconstruction 0-002-018 06/08/07 DONE DONE DONE 06/08/07 06/08/07 09/22/06 03/14/00 2,7,155,15,16 1,210,686 1,225,000 JOD 0 0 0
samuel J. Cichello
Field Storage E @ JR/SR HS:
06-1590 New Construction 2-011-001 06/08/07 DONE DONE DONE 06/08/07 06/08/07 11/30/06 03/14/00 02 - 16 47,000 0 JOD 0 0 0
samuel J. Cichello
Field Storage W @ Jr./Sr. HS:
06-1591 New Construction 2-012-001 06/08/07 DONE DONE DONE 06/08/07 06/08/07 11/30/06 03/14/00 02 - 16 47,000 0 JOD 0 0 0
samuel J. Cichello
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary/Middle School:
03-1006 Reconstruction 0-001-015 05/20/04 DONE DONE DONE 01/21/04 12/29/03 05/21/99 06/10/03 2 3,849,151 3,849,151 HCM 0 0 0
Teitsch-Kent
- XX Reconstruction 0-001-016 CANCELLED / / / / 07/31/03 / / 2,8,9,10,155,15,16 0 17,142,158 HCM 0 0 0
07-0006 Reconstruction 0-001-017 12/12/07 DONE DONE DONE 07/03/07 07/03/07 11/03/06 03/13/07 2,4,7,8,9,10,14,155, 2,234,200 2,234,200 HCM 0 0 205,546
Teitsch Kent fay architects
High School:
03-1007 Reconstruction 0-004-012 05/20/04 DONE DONE DONE 01/21/04 12/29/03 05/21/99 06/10/03 2 10,760,848 10,760,848 HCM 0 0 0
Teitsch-Kent
07-0007 Reconstruction 0-004-013 12/12/07 DONE DONE DONE 07/03/07 07/03/07 11/03/06 03/13/07 2,7 218,600 0 HCM 0 0 20,112
Teitsch Kent fay architects
Bus Maint Center:
05-0059 Reconstruction 5-002-004 11/10/05 DONE DONE DONE 07/20/05 07/19/05 08/10/04 06/10/03 2,15 297,730 297,730 HCM 0 0 0
Teitsch-Kent
Press Box:
05-0060 Reconstruction 7-005-001 11/10/05 DONE DONE DONE 07/20/05 07/19/05 03/11/05 06/10/03 7,8,9,10,155,16 35,000 0 HCM 0 0 0
Teitsch-Kent
Concession Stand:
- PR New Construction 7-007-001 / / / / 11/06/06 / / 02 - 16 0 0 HCM 0 0 0
06-0693 New Construction 7-007-001 06/04/07 DONE DONE DONE 12/28/06 12/18/06 11/06/06 06/10/03 02 - 16 0 0 HCM 0 0 0
Teitsch-Kent-Fay Architects,P.C.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Emily Howland ES K-4:
04-0756 Reconstruction 0-006-011 03/23/05 DONE DONE DONE 02/02/05 02/01/05 10/14/04 05/18/04 4,10 80,000 80,000 RDR 0 0 0
King & King, Architects
- XX Reconstruction 0-006-012 CANCELLED / / / / 10/22/04 / / 4,10,13 0 6,262,003 MGL 0 0 0
07-0351 Reconstruction 0-006-013 01/31/08 DONE DONE DONE 09/11/07 09/11/07 01/11/07 03/15/07 16 238,400 240,500 MGL 0 0 44,819
King & King, Architects
Jr/Sr High School:
- XX Reconstruction 0-007-011 CANCELLED / / / / 04/01/04 / / 7 0 27,019,020 MGL 0 0 0
04-0757 Reconstruction 0-007-012 03/23/05 DONE DONE DONE 02/02/05 02/01/05 04/23/04 05/18/04 4,7,10,13 1,733,356 1,733,356 RDR 0 0 0
King & King, Architects
07-0352 Reconstruction 0-007-013 01/31/08 DONE DONE DONE 09/11/07 09/11/07 01/11/07 03/15/07 2,9,15,16 1,341,600 1,339,000 MGL 0 0 248,081
King & King, Architects
Greenhouse:
04-0149 New Construction 0-010-001 09/02/04 DONE DONE DONE 08/23/04 08/19/04 05/11/04 08/09/04 02 - 16 40,000 0 RDR 0 0 0
King & King, Architects
Observatory:
03-1120 New Construction 7-009-001 06/07/04 DONE DONE DONE 02/17/04 02/13/04 04/25/03 10/10/02 02 - 16 50,000 0 RDR 0 0 0
King & King Architects
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main School Building K-12:
07-0187 Reconstruction 0-004-010 04/28/08 DONE DONE DONE 08/16/07 08/16/07 02/27/07 12/20/06 2,4,7,8,9,155,15,16 4,960,000 0 DDJ 0 0 361,799
William Taylor Architects, PLLC.
Bus Garage:
07-0188 Reconstruction 5-011-002 04/28/08 DONE DONE DONE 08/16/07 08/16/07 02/27/07 12/20/06 2,16 10,000 0 DDJ 0 0 0
William Taylor Architects, PLLC.
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
03-0323XX Reconstruction 0-002-005 CANCELLED 09/18/03 09/04/03 05/30/03 06/03/03 2,9 14,200 14,200 MGL 0 0 0
Teitsch-Kent
- Reconstruction 0-002-006 / / / / 06/14/06 / / 2,16 0 11,210,376 MGL 0 0 0
07-1132 Additions and Alterations 0-002-007 DONE ADD. REQ'D DONE 12/14/07 12/14/07 09/12/06 02/13/07 02 - 16 0 16,949,392 MGL 0 0 0
Hunt Engineers, Arch. & Land Surveyo
03-0023FP Reconstruction 0-002-FP1 09/18/03 DONE DONE DONE 07/09/03 / / / / / / 16 5,428 5,428 MGL 0 0 0
Greenhouse:
07-1133 Reconstruction 0-007-002 DONE ADD. REQ'D DONE 12/14/07 12/14/07 09/12/06 02/13/07 2,4,7,9,155,15,16 0 0 MGL 0 0 0
Hunt Engineers, Arch. & Land Surveyo
Fillmore ES:
03-0324XX Reconstruction 0-012-004 CANCELLED 09/18/03 09/04/03 05/30/03 06/03/03 2,9 11,900 11,900 MGL 0 0 0
Teitsch-Kent
07-1134 Additions and Alterations 0-012-005 DONE ADD. REQ'D DONE 12/14/07 12/14/07 09/12/06 02/13/07 02 - 16 0 0 MGL 0 0 0
Hunt Engineers, Arch. & Land Surveyo
07-1917 Alterations 0-012-006 04/18/08 DONE DONE DONE 04/03/08 03/27/08 03/19/08 02/13/07 02 - 16 860,400 0 JOD 0 0 0
Hunt Engineers, Arch. & Land Surveyo
03-0024FP Reconstruction 0-012-FP1 09/18/03 DONE DONE DONE 07/09/03 / / / / / / 16 5,530 5,530 MGL 0 0 0
Ag Building Brick:
03-0325XX Reconstruction 2-004-002 CANCELLED 09/18/03 09/04/03 05/30/03 06/03/03 2,155 6,100 0 MGL 0 0 0
Teitsch-Kent
07-1135 Reconstruction 2-004-003 DONE ADD. REQ'D DONE 12/14/07 12/14/07 09/12/06 02/13/07 2,4,7,9,155,15,16 0 0 MGL 0 0 0
Hunt Engineers, Arch. & Land Surveyo
Athletic Storage Container:
- XX New Construction 2-014-001 CANCELLED / / / / 01/05/05 / / 02 - 16 0 0 MGL 0 0 0
Bus Garage:
- Reconstruction 5-001-002 / / / / 09/12/06 / / 2,4,7,9,10,15,16 0 0 MGL 0 0 0
New Bus Garage:
07-1136 New Construction 5-013-001 DONE ADD. REQ'D DONE 12/14/07 12/14/07 07/09/01 02/13/07 02 - 16 0 0 MGL 0 0 0
Hunt Engineers, Arch. & Land Surveyo
Concession Stand - Main Campus:
- DB Discovered Building 7-015-001 / / / / 12/28/07 / / 0 0 MGL 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Stone School House:
07-1810 Reconstruction 0-002-001 UNREVIEWED 03/17/08 03/07/08 / / 12/11/07 2,4,7,8,9,10,155,15, 0 240,646 DDJ 0 0 0
C&S Engineers, Inc.
Cook Environ. Learning Ctr.:
03-0395 New Construction 0-007-001 07/02/04 DONE DONE DONE 09/29/03 09/08/03 10/01/99 03/22/01 02 - 16 728,000 633,648 DDJ 0 0 0
Brennan Architectural Associates
Stone School House:
- Reconstruction 2-002-001 / / / / 02/01/07 / / 2,4,7,8,9,10,155,15, 0 0 DDJ 0 0 0
Districtwide:
07-0526 Reconstruction 7-999-001 03/10/08 DONE DONE DONE 10/11/07 10/09/07 02/01/07 02/26/07 10,16 1,570,000 0 DDJ 0 0 260,000
C&S Companies
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Occ. Educ. Center:
05-0563 Reconstruction 0-001-004 02/16/06 DONE DONE DONE 01/17/06 01/17/06 05/03/05 12/14/04 2,13 900,000 900,000 JOD 0 0 0
samuel J. Cichello
- Reconstruction 0-001-005 / / / / 07/26/05 / / 2,9 0 0 JOD 0 0 0
- Reconstruction 0-001-006 / / / / 08/12/05 / / 2,9 0 0 JOD 0 0 0
Education Complex:
05-0564 New Construction 0-023-001 02/16/06 DONE DONE DONE 01/17/06 01/17/06 11/29/99 12/14/04 02 - 16 41,295,000 39,302,277 MAC 0 0 0
samuel J Cichello
Greenhouse I:
- DB Discovered Building 0-027-001 / / / / 06/08/04 / / 02 - 16 0 0 MAC 0 0 0
Greenhouse II:
- DB Discovered Building 0-028-001 / / / / 06/08/04 / / 02 - 16 0 0 MAC 0 0 0
Storage Container 1:
- New Construction 2-029-001 / / / / 02/18/05 / / 02 - 16 0 0 JOD 0 0 0
Greenhouse:
- New Construction 7-033-001 / / / / 10/01/07 / / 02 - 16 0 0 JOD 0 0 0
Lattimore Hall @ Cayuga County CC:
- TQ Temporary Quarters 8-024-002 / / / / 12/21/04 / / 0 0 MAC 0 0 0
Natural Resource Center:
04-0047TQ Temporary Quarters 8-025-001 12/15/04 DONE DONE DONE 07/07/04 06/29/04 03/25/02 / / 0 0 MAC 0 0 0
Central Business Office:
05-0308 Reconstruction 8-030-001 01/18/08 DONE DONE DONE 10/28/05 10/26/05 08/22/05 / / 0 0 JOD 0 0 0
Special Ed @ Cayuga CC-Sparten Hotel:
06-1349TQ Temporary Quarters 8-031-001 02/19/08 DONE DONE DONE 04/23/07 04/06/07 04/18/07 / / 0 0 JOD 0 0 0
Special Ed. @ Cayuga CC-Reg Eco. Ctr:
06-1350TQ Temporary Quarters 8-032-001 02/19/08 DONE DONE DONE 04/23/07 04/06/07 04/18/07 / / 0 0 JOD 0 0 0
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED