Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 10/10/08 at 08:41:42




ALFRED ALMOND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-01-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
04-1265   Reconstruction               0-001-005  12/12/05     DONE    DONE       DONE      05/16/05   05/13/05   12/02/02   02/07/04   2,4,7,8,9,10,13,155,   2,897,800     2,897,800  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     
08-0062   Reconstruction               0-001-006                         UNREVIEWED         07/21/08   07/10/08   03/05/07   11/13/07   2,4,8,9,10,13,155,15           0    17,123,277  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     
08-0063   Reconstruction               0-001-007                         UNREVIEWED         07/21/08   07/10/08   03/14/08   11/13/07   2,9,10,15,16                   0    18,403,676  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Athletic Field Storage Building:
08-0090   New Construction             2-007-001                         UNREVIEWED         07/24/08   07/10/08   07/17/08   11/13/07   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          Bus Garage:
04-1266   Reconstruction               5-002-003  12/12/05     DONE    DONE       DONE      05/16/05   05/13/05   12/03/02   12/07/04   2,4,8,9,155,15,16         97,955        97,955  JOD             0           0            0
                                                                                                                                                                                                                                                                     
08-0064   Reconstruction               5-002-004                         UNREVIEWED         07/21/08   07/10/08   03/05/07   11/13/07   2,9,10,13,15,16                0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     

          New Concession Stand:
08-0065   New Construction             7-006-001                         UNREVIEWED         07/21/08   07/10/08   04/24/07   11/13/07   02 - 16                        0             0  JOD             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ANDOVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-06-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-1326   Reconstruction               0-001-006  08/05/08     DONE    DONE       DONE      01/04/08   01/02/08   08/15/06   03/27/07   2,4,7,8,9,10,155,15,   3,307,200             0  HCM             0           0      125,674
                                                                                                                                                                                                                                 Habiterra Associates                

          Maintenance Storage:
  -    DB Discovered Building          2-005-001                                              /  /       /  /     10/16/07     /  /                                    0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Bus Garage Maintenance:
07-1327   Reconstruction               5-002-002  08/05/08     DONE    DONE       DONE      01/04/08   01/02/08   08/15/06   03/27/07   4,7,8,155,15,16          137,800             0  HCM             0           0            0
                                                                                                                                                                                                                                 Habiterra Associates                


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GENESEE VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-07-02-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          New Pre-K-12:
05-0027   Reconstruction               0-012-002  07/12/05     DONE    DONE       DONE      07/08/05   07/07/05   06/09/05   06/27/05   9                        170,000       170,000  DDJ             0           0            0
                                                                                                                                                                                                                                 Habiterra Associates                
  -    PR Additions and Alterations    0-012-003                                              /  /       /  /     02/21/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Bison Steel Building @ Main Building:
  -    PR New Construction             2-015-001                                              /  /       /  /     02/28/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          TRANSPORATION STORAGE:
  -       New Construction             4-019-001                                              /  /       /  /     08/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
  -       Additions and Alterations    5-011-002                                              /  /       /  /     02/21/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Upper Field Restrooms & Storage:
  -    PR New Construction             7-016-001                                              /  /       /  /     05/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Announcer's Booth:
  -    PR New Construction             7-017-001                                              /  /       /  /     05/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Consessions & Restroom:
  -    PR New Construction             7-018-001                                              /  /       /  /     05/27/08     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BELFAST CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-08-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-1962   Additions and Alterations    0-001-009                       ADDENDUM REQ'D       04/15/08   04/04/08   02/12/07   06/21/07   02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
04-0427SC Visual Structural Inspection 0-001-SC1  11/23/04     DONE    DONE       DONE      11/23/04   11/17/04     /  /       /  /     16                        66,100        58,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          Shop Bus Garage:
  -       Reconstruction               0-002-004                                              /  /       /  /     11/28/06     /  /                                    0     5,370,500  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Steel Storage Bldg.:
07-1963   Reconstruction               2-003-001                       ADDENDUM REQ'D       04/15/08   04/04/08   02/12/07   06/21/07   7,16                           0             0  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          New Bus Garage:
  -    PR Additions and Alterations    5-007-002                                              /  /       /  /     02/12/07     /  /     02 - 16                        0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     
07-1964   Reconstruction               5-007-002               DONE    UNREVIEWED STARTED   04/15/08   04/04/08     /  /     06/21/07                                  0             0                  0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Grandstand/Bleachers:
  -       Reconstruction               7-004-003                                              /  /       /  /     02/12/07     /  /     2,4,7,10,16                    0             0  MGL             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CANASERAGA CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-11-02-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
  -       Reconstruction               0-001-004                                              /  /       /  /     11/27/07     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          Industrial Arts Bus Garage:
  -       Reconstruction               0-002-003                                              /  /       /  /     11/27/07     /  /     2,4,7,8,9,155,15,16            0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
  -       New Construction             5-004-001                                              /  /       /  /     10/10/01     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FRIENDSHIP CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-16-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
03-0509   Additions and Alterations    0-001-012  07/28/05     DONE    DONE       DONE      10/28/03   12/10/02   03/17/99   06/16/00   02 - 16                3,940,305     3,940,305  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0228   Reconstruction               0-001-013  10/21/05     DONE    DONE       DONE      09/30/05   09/30/05   09/28/05     /  /     2                         96,440        96,440  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0814   Reconstruction               0-001-014  03/20/06     DONE    DONE       DONE      02/24/06   02/23/06   12/23/05   02/14/06   16                       100,000       100,000  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
06-0314   Reconstruction               0-001-015  12/23/05     DONE    DONE       DONE      10/13/06   10/10/06   01/18/06   01/15/06   13                       167,091       167,091  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -    PR Additions and Alterations    0-001-016                       ADD. REQ'D DONE        /  /       /  /     01/18/06     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-1275   Additions and Alterations    0-001-016  05/18/06     DONE    DONE       DONE      05/19/06   05/19/06   01/18/06   04/06/06   02 - 16                  505,000       505,000  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -    PR Additions and Alterations    0-001-017               DONE                           /  /       /  /     06/01/06     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
06-0435   Additions and Alterations    0-001-017  02/09/07     DONE    DONE       DONE      11/06/06   11/03/06   06/01/06   04/05/06   02 - 16                  829,500       740,000  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
08-0066   Reconstruction               0-001-018                         UNREVIEWED         ***SHPO RESPONSE***                                                              6,326,048  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
07-1383   Reconstruction               0-001-019  03/10/08     DONE    DONE       DONE      01/16/08   01/16/08   09/13/07     /  /     7                         88,050             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
02-0930FP Reconstruction               0-001-FP1  06/08/04     DONE    DONE       DONE      01/06/03     /  /       /  /       /  /     16                         5,150         5,150  MGL             0           0            0
                                                                                                                                                                                                                                                                     

          Wellman Barn:
03-0510XX Reconstruction               2-007-002                         CANCELLED          ***MULTIPLE PROBLEMS***                                                                  0  HCM             0           0            0
                                                                                                                                                                                                                                 Brennan Architectural Associates    

          Bus Garage:
04-1190XX Reconstruction               4-002-003  07/28/05               CANCELLED          04/25/05   04/21/05   10/28/04   06/16/00   4,7,9,155,15,16          204,500       204,500  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
06-0436   Reconstruction               4-002-004  02/09/07     DONE    DONE       DONE      11/06/06   11/03/06   01/18/06   04/05/06   4,7,8,9,155,15,16        314,500       314,500  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -       Additions and Alterations    4-002-005                                            ***MULTIPLE PROBLEMS***                                                                  0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
08-0067   Additions and Alterations    5-005-002                         UNREVIEWED         08/04/08   07/30/08   07/09/08   08/29/07   02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




FILLMORE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-20-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Fillmore Main Building:
02-2391   Reconstruction               0-001-005  03/09/04     DONE    DONE       DONE      06/13/03   06/05/03   10/03/02   03/18/03   2,8,9,10,155,15,16       950,000       950,000  MAC             0           0            0
                                                                                                                                                                                                                                 Thomas Associates                   
06-0617   Additions and Alterations    0-001-006  03/20/07     DONE    DONE       DONE      12/12/06   12/12/06   12/29/04   10/13/05   02 - 16               15,712,000    15,631,767  HCM             0           0      556,427
                                                                                                                                                                                                                                 Habiterra Associates                

          Maintenance Building:
06-0618   New Construction             3-004-001  03/20/07     DONE    DONE       DONE      12/12/06   12/12/06   06/28/06   10/13/05   02 - 16                  104,351             0  HCM             0           0            0
                                                                                                                                                                                                                                 Habiterra Associates                


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WHITESVILLE CENTRAL SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-21-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
07-0008   Additions and Alterations    0-001-007  02/04/08     DONE    DONE       DONE      07/06/07   07/02/07   09/18/06   12/20/06   02 - 16                4,909,361     4,909,361  HCM             0           0      199,222
                                                                                                                                                                                                                                 Hunt Engineers,                     

          New Bus Garage:
07-0009   New Construction             5-009-001  02/04/08     DONE    DONE       DONE      07/06/07   07/02/07   02/03/00   12/20/06   02 - 16                2,905,776     2,905,776  HCM             0           0            0
                                                                                                                                                                                                                                 Hunt Engineers,                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




CUBA-RUSHFORD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-23-02-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cuba Campus K-5 Bldg:
  -       Reconstruction               0-001-008                                              /  /       /  /     01/23/07     /  /     2,8,9,10,15,16                 0     3,125,631  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-2063   Reconstruction               0-001-009  06/10/08     DONE    DONE       DONE      05/02/08   04/25/08   03/31/08   04/08/08   7                         60,026        60,026  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Cuba Elementary:
03-0664   Reconstruction               0-002-002  04/09/04     DONE    DONE       DONE      11/12/03   11/03/03   03/05/01   10/21/03   2,4,7,8,9,10,155,15,   4,337,827     4,337,827  BJB             0           0            0
                                                                                                                                                                                                                                 Habiterra Associates                
  -       Reconstruction               0-002-003                                              /  /       /  /     09/19/06     /  /     16                             0    14,654,328  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-002-004                                              /  /       /  /     09/29/06     /  /     155                            0    14,654,328  HCM             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-002-005                                              /  /       /  /     05/21/07     /  /     13,15                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Cuba Annex E C'hood fmr AG-IA Shop:
07-2064   Reconstruction               0-003-002  06/10/08     DONE    DONE       DONE      05/02/08   04/25/08     /  /     04/08/08   7                         39,962        39,962  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Rushford K-5 Building:
03-1553   Reconstruction               0-015-007  05/21/04     DONE    DONE       DONE      05/17/04   05/17/04   03/30/04   06/03/03   7                        100,000       100,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     
04-0609   Reconstruction               0-015-008  12/31/04     DONE    DONE       DONE      12/30/04   12/29/04   12/08/04   12/07/04   15                       118,902       118,902  JOD             0           0            0
                                                                                                                                                                                                                                 M/E Engineering, P.C.               
  -       Reconstruction               0-015-009                                              /  /       /  /     01/23/07     /  /     2,7,8,9,15,16                  0     4,788,700  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0186   Reconstruction               0-015-010                       ADDENDUM REQ'D       08/16/07   08/16/07   07/24/07   05/22/07   15,16                          0             0  HCM             0           0            0
                                                                                                                                                                                                                                 M/E Engineering, P.C.               
03-0227SC Visual Structural Inspection 0-015-SC1  09/28/04     DONE    DONE       DONE      08/21/03   08/21/03     /  /       /  /     16                        17,103        17,103  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New MS/HS 6-12:
06-0457   Reconstruction               0-020-004  11/21/06     DONE    DONE       DONE      11/09/06   11/08/06   09/29/06   09/12/06   155                       90,000        90,000  HCM             0           0            0
                                                                                                                                                                                                                                 M/E Engineering, P.C.               
  -    PR Additions and Alterations    0-020-005                                              /  /       /  /     01/23/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     
03-0226SC Visual Structural Inspection 0-020-SC1  09/28/04     DONE    DONE       DONE      08/21/03   08/21/03     /  /       /  /     16                        37,682        36,000  JOD             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage '96:
  -    PR Additions and Alterations    5-021-002                                              /  /       /  /     01/23/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          Concession Building:
  -    PR New Construction             7-023-001                                              /  /       /  /     01/23/07     /  /     02 - 16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SCIO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-24-01-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
05-0194   Reconstruction               0-001-011  09/30/05     DONE    DONE       DONE      09/14/05   09/10/05   07/27/05   08/03/05   16                        23,369        23,369  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
05-0967   Reconstruction               0-001-012  08/10/06     DONE    DONE       DONE      03/15/06   03/14/06   08/29/05   11/09/05   2,7,8,9,155,15,16      3,110,669     3,260,831  HCM             0           0       65,217
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
06-1613   Reconstruction               0-001-013  08/02/07     DONE    DONE       DONE      06/14/07   06/14/07   03/29/07   11/09/05   2,7,13                   150,162       152,000  HCM             0           0      150,162
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Bus Garage:
  -       Reconstruction               5-002-006                                              /  /       /  /     08/29/05     /  /     15                             0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WELLSVILLE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-26-01-06
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Wellsville Middle School:
  -    XX Reconstruction               0-001-009                         CANCELLED            /  /       /  /     06/02/04     /  /     2                              0     9,899,648  MAC             0           0            0
                                                                                                                                                                                                                                                                     

          Washington Primary/Inter.:
  -       Reconstruction               0-003-008                                              /  /       /  /     11/14/07     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-003-009                                              /  /       /  /     06/04/08     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          High School/Middle School:
04-0253   Reconstruction               0-004-011  09/30/04     DONE    DONE       DONE      09/29/04   09/23/04     /  /     02/17/04   2                        183,219       183,219  MAC             0           0            0
                                                                                                                                                                                                                                 Habiterra Associates                
  -       Reconstruction               0-004-012                                              /  /       /  /     11/14/07     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     
  -       Reconstruction               0-004-013                                              /  /       /  /     06/04/08     /  /     2,4,7,8,9,10,155,15,           0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage:
  -       New Construction             5-011-001                                              /  /       /  /     11/14/07     /  /     02 - 16                        0             0  DDJ             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOLIVAR-RICHBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 02-29-02-04
last updated on 10/10/08
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bolivar 6-12 Building:
02-1854   Reconstruction               0-001-015  12/01/03     DONE    DONE       DONE      03/31/03   03/17/03   04/23/02   02/29/00   8,9,155,15,16          1,684,500     1,684,500  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
04-0794   Additions and Alterations    0-001-016  04/19/05     DONE    DONE       DONE      02/09/05   02/08/05   01/30/03   04/09/03   02 - 16                4,646,500     4,646,500  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
03-1033   Reconstruction               0-001-017  03/02/04     DONE    DONE       DONE      01/26/04   01/23/04   11/13/03   10/28/03   10                       282,650       282,650  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -       Reconstruction               0-001-018                                              /  /       /  /     04/06/05     /  /     7,8,9,155,15,16                0    17,525,895  HCM             0           0            0
                                                                                                                                                                                                                                                                     
05-0727   Reconstruction               0-001-019  03/01/06     DONE    DONE       DONE      02/13/06   02/01/06   08/23/05   10/16/05   10                       125,000        99,000  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
07-0460   Reconstruction               0-001-020  02/22/08     DONE    DONE       DONE      10/01/07   09/28/07   02/13/07   05/15/07   2,8,9,10,13,155,15,1   3,621,797     4,132,564  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Pre-Kindergarten Bldg.(Demolished):
07-0461   Reconstruction               0-005-006  02/22/08     DONE    DONE       DONE      10/01/07   09/28/07   02/13/07   05/15/07   2,155,16                 457,733       678,948  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Richburg K-5 Building:
02-1855   Reconstruction               0-011-009  12/01/03     DONE    DONE       DONE      03/31/03   03/17/03   04/24/02   02/29/00   4,8,9,155,15,16        1,387,900     1,387,900  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
04-0795   Additions and Alterations    0-011-010  04/19/05     DONE    DONE       DONE      02/09/05   02/08/05   01/30/03   04/09/03   02 - 16                  823,500       823,500  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -       Reconstruction               0-011-011                                              /  /       /  /     04/06/05     /  /     2,8,9,155,15,16                0     7,067,578  HCM             0           0            0
                                                                                                                                                                                                                                                                     
07-0462   Reconstruction               0-011-012  02/22/08     DONE    DONE       DONE      10/01/07   09/28/07   02/13/07   05/15/07   2,9,10,155,15,16       1,829,978     2,411,838  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Bolivar Bus Garage:
02-1856   Reconstruction               5-002-004  12/01/03     DONE    DONE       DONE      03/31/03   03/17/03   04/24/02   02/29/00   7,8,9,155,15,16          476,600       476,600  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Richburg Bus Garage:
02-1857   Reconstruction               5-012-007  12/01/03     DONE    DONE       DONE      03/31/03   03/17/03   04/24/02   02/29/00   8,9,155,15,16            345,165       345,165  MGL             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              
  -       Reconstruction               5-012-008                                              /  /       /  /     10/30/07     /  /     4,15,16                        0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     

          New Bus Garage in Bolivar:
07-0463   Reconstruction               5-016-003  02/22/08     DONE    DONE       DONE      10/01/07   09/28/07   02/13/07   05/15/07   2,15,16                  390,492       186,272  HCM             0           0            0
                                                                                                                                                                                                                                 Clark Patterson Assoc.              

          Wastewater Treatment Plant:
  -       Reconstruction               7-015-003                                              /  /       /  /     02/13/07     /  /     2,16                           0             0  HCM             0           0            0
                                                                                                                                                                                                                                                                     


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED