REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Congers Elementary:
91-0774 Reconstruction 0-001-002 02/26/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1196 Reconstruction 0-001-003 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0416 Reconstruction 0-001-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1214 Reconstruction 0-001-007 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
3 43,525 01/16/07 / / Institutional Systems
04-0386 Reconstruction 0-001-009 12/17/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0036 Additions and Alterations 0-001-010 02/04/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0627 Reconstruction 0-001-011 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1363 Reconstruction 0-001-012 07/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Birchwood School:
92-1227 Reconstruction 0-002-002 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0417 Reconstruction 0-002-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0469 Reconstruction 0-002-008 01/19/01 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0628 Reconstruction 0-002-009 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
New City Elementary:
92-0768 Reconstruction 0-003-003 04/01/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0863 Reconstruction 0-003-005 11/27/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0418 Reconstruction 0-003-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0806 Reconstruction 0-003-007 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1215 Reconstruction 0-003-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
06-0625 Additions and Alterations 0-003-010 03/09/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0678 Reconstruction 0-003-011 05/23/06 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0629 Reconstruction 0-003-012 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1213FP Reconstruction 0-003-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Little Tor Elementary School:
91-0106 Reconstruction 0-004-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1317 Reconstruction 0-004-004 06/01/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1630 Reconstruction 0-004-006 07/14/95 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0370 Reconstruction 0-004-007 10/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0419 Reconstruction 0-004-009 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1216 Reconstruction 0-004-010 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
05-0679 Reconstruction 0-004-011 05/23/06 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0630 Reconstruction 0-004-013 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Chestnut Grove(Data Center):
91-1073 Reconstruction 0-005-003 04/20/92 NO CHANGE ORDERS ON ELECTRONIC FILE
91-1550 Reconstruction 0-005-004 07/08/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1561 Reconstruction 0-005-006 07/27/95 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0420 Reconstruction 0-005-009 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2340FP Reconstruction 0-005-FP1 08/26/03 NO CHANGE ORDERS ON ELECTRONIC FILE
West Nyack Elementary School:
92-0769 Reconstruction 0-006-003 04/01/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0864 Reconstruction 0-006-007 11/27/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0421 Reconstruction 0-006-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1217 Reconstruction 0-006-010 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institional systems
02-0196 Reconstruction 0-006-012 03/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0680 Reconstruction 0-006-014 05/23/06 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0631 Reconstruction 0-006-015 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Bardonia Elementary School:
92-0284 Reconstruction 0-007-003 10/21/92 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0732 Reconstruction 0-007-005 01/27/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0422 Reconstruction 0-007-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1218 Reconstruction 0-007-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
2 2,959 2,959 01/16/07 12/28/07 Institutional Systems
3 43,525 01/16/07 12/28/07 Institional Systems
06-0564 Reconstruction 0-007-011 05/17/07 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0681 Reconstruction 0-007-012 05/23/06 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0632 Reconstruction 0-007-014 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1364 Reconstruction 0-007-015 07/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1212FP Reconstruction 0-007-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
High School North Annex:
00-1317 Reconstruction 0-009-003 05/29/01 *CO No.* Amount Disallowed Received Approved Contractor
01 3,542 04/12/02 04/26/02 Pearl River PH&E
04-0158 Reconstruction 0-009-004 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School North:
91-1074 Reconstruction 0-010-002 04/20/92 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0775 Reconstruction 0-010-003 02/26/92 NO CHANGE ORDERS ON ELECTRONIC FILE
92-0975 Reconstruction 0-010-005 05/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1255 Reconstruction 0-010-007 05/25/94 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1130 Reconstruction 0-010-011 04/29/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0756 Additions and Alterations 0-010-012 06/30/02 *CO No.* Amount Disallowed Received Approved Contractor
0001A 896,291 10/24/05 04/03/07 darlind Construction
1 52,000 12/23/05 04/12/06 Vardon Inc
1 71,395 12/23/05 / / thomas Kempton
1 15,041 12/23/05 01/19/06 JD parrella electric
2 20,995 10/24/05 03/23/07 Darlind Construction
2 36,421 12/23/05 / / Vardon Inc
2A 46,776 10/24/05 04/03/07 darlind Construction
3 16,901 10/24/05 04/03/07 darlind Construction
4 2,216 10/24/05 12/07/05 darlind Construction
5 41,529 12/23/05 06/26/06 Darlind Construction
03-0423 Reconstruction 0-010-013 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0626 Additions and Alterations 0-010-015 03/09/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0633 Reconstruction 0-010-017 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0641 Reconstruction 0-010-018 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1216FP Reconstruction 0-010-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Laurel Plains Elementary:
91-0107 Reconstruction 0-011-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1197 Reconstruction 0-011-003 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0896 Additions and Alterations 0-011-005 05/05/03 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0424 Reconstruction 0-011-006 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0682 Reconstruction 0-011-007 05/23/06 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0634 Reconstruction 0-011-008 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0934FP Reconstruction 0-011-FP1 02/02/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Felix Festa Junior High:
92-1228 Reconstruction 0-012-005 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1471 Reconstruction 0-012-006 06/21/95 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0211 Reconstruction 0-012-008 10/03/94 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0425 Reconstruction 0-012-014 10/08/04 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
002 59,016 07/25/06 12/27/06 Joe Lombardo Plumbing
005 65,000 07/25/06 / / Joe Lombardo Plumbing
007 69,429 07/25/06 / / JD Parella Electric
12 45,890 07/25/06 08/10/06 Morris Park Contracting
4 8,048 07/25/06 12/27/06 Joe Lombardo Plumging
6 32,535 07/25/06 / / JD Parella Electric
8 20,312 07/25/06 / / Jd Parella Electric
03-1440 Reconstruction 0-012-016 04/13/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0287 Reconstruction 0-012-019 12/28/06 NO CHANGE ORDERS ON ELECTRONIC FILE
05-1419 Reconstruction 0-012-020 01/24/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0635 Reconstruction 0-012-021 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0642 Reconstruction 0-012-022 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1263FP Reconstruction 0-012-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Dina Link Elementary:
92-1198 Reconstruction 0-013-002 05/03/93 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1205 Reconstruction 0-013-005 07/28/00 *CO No.* Amount Disallowed Received Approved Contractor
1 3,700 06/30/04 06/30/04 Parker Elec.
1 2,428 06/30/04 06/30/04 Pearl River Plumbing
1 12,600 06/30/04 06/30/04 Robert Runge Const.
2 830 06/30/04 06/30/04 Parker Elec.
2 5,083 06/30/04 06/30/04 Pearl River Plumbing
2 -18,268 06/30/04 06/30/04 Robert Runge Const.
3 4,000 06/30/04 06/30/04 Parker Elec.
3 575 06/30/04 06/30/04 Pearl River Plumbing
4 1,725 06/30/04 06/30/04 Pearl River Plumbing
03-0426 Reconstruction 0-013-006 10/08/04 *CO No.* Amount Disallowed Received Approved Contractor
3 43,525 01/16/07 / / Institutional Systems
01-1219 Reconstruction 0-013-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
1 11,116 01/16/07 / / Instituional Systems
02-1695 Additions and Alterations 0-013-009 03/16/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0636 Reconstruction 0-013-012 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Wood Glen Elementary:
98-0900 Reconstruction 0-016-004 04/28/99 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0283 Alterations 0-016-005 11/29/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0427 Reconstruction 0-016-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0637 Reconstruction 0-016-010 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1214FP Reconstruction 0-016-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Lakewood Elementary School:
91-0109 Reconstruction 0-017-002 08/12/91 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1443 Additions and Alterations 0-017-004 06/21/95 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0514 Additions and Alterations 0-017-005 02/12/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0428 Reconstruction 0-017-007 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1220 Reconstruction 0-017-008 06/17/02 *CO No.* Amount Disallowed Received Approved Contractor
1 11,116 11,116 01/16/07 12/28/07 Instituional Systems
3 43,525 43,525 01/16/07 Disapproved Ins6itutional Systems
07-0638 Reconstruction 0-017-009 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1211FP Reconstruction 0-017-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School South:
92-0976 Reconstruction 0-018-003 05/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1039 Reconstruction 0-018-004 05/20/93 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1229 Reconstruction 0-018-005 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0017 Reconstruction 0-018-007 07/28/00 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0085 Reconstruction 0-018-008 08/28/95 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0845 Reconstruction 0-018-010 03/06/98 NO CHANGE ORDERS ON ELECTRONIC FILE
01-1242 Additions and Alterations 0-018-011 06/30/02 *CO No.* Amount Disallowed Received Approved Contractor
1 68,875 08/08/05 08/15/05 Pearl River Plumbing
1 5,905 08/08/05 / / GTL Construction
1 3,531 08/08/05 08/15/05 Pearl River Plumbing Heating
2 9,403 08/08/05 / / GTL Construction
2 9,403 12/08/05 07/26/06 GTL CONSTRUCTION, LLC.
3 10,961 08/08/05 / / GTL Construction
00-0119 Reconstruction 0-018-012 10/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0429 Reconstruction 0-018-013 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1441 Reconstruction 0-018-014 04/13/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0389 Reconstruction 0-018-015 02/21/06 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0936 Reconstruction 0-018-016 05/04/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0639 Reconstruction 0-018-017 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0643 Reconstruction 0-018-018 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-1215FP Reconstruction 0-018-FP1 09/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Strawtown Road Elementary:
92-1230 Reconstruction 0-019-002 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0809 Reconstruction 0-019-004 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0016 Reconstruction 0-019-007 08/24/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0430 Reconstruction 0-019-008 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0810 Reconstruction 0-019-009 06/07/02 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0470 Reconstruction 0-019-010 01/19/01 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0640 Reconstruction 0-019-011 04/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Storage Shed:
03-1080 New Construction 2-027-001 03/16/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
94-1546 Reconstruction 5-022-002 06/05/95 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0431 Reconstruction 5-022-004 10/08/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box @ South High School:
06-0369 New Construction 7-030-001 10/19/07 NO CHANGE ORDERS ON ELECTRONIC FILE
Districtwide-Elementary:
94-1506 Reconstruction 7-999-001 06/27/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-0849 Reconstruction 7-999-002 02/28/97 NO CHANGE ORDERS ON ELECTRONIC FILE
NANUET UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-01-08-03
last updated on 09/05/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Miller Elementary:
96-1247 Additions and Alterations 0-001-004 04/30/97 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1362 Additions and Alterations 0-001-005 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0558 Reconstruction 0-001-006 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1388 Reconstruction 0-001-007 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1437 Reconstruction 0-001-008 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1077 Additions and Alterations 0-001-009 05/11/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0334 Reconstruction 0-001-010 10/15/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0447 Reconstruction 0-001-011 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1060 Reconstruction 0-001-012 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0065 Reconstruction 0-001-013 07/24/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0989 Reconstruction 0-001-014 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0681FP Reconstruction 0-001-FP1 03/03/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Highview Elementary:
94-1337 Reconstruction 0-002-004 05/11/95 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1330 Reconstruction 0-002-005 07/06/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0559 Reconstruction 0-002-006 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1361 Reconstruction 0-002-007 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0064 Additions and Alterations 0-002-008 05/07/04 *CO No.* Amount Disallowed Received Approved Contractor
EL-3 -25,000 08/05/05 08/17/05 Habiterra Architecture and Landscape
03-0448 Reconstruction 0-002-009 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1061 Reconstruction 0-002-010 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0990 Reconstruction 0-002-011 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Nanuet Senior High:
98-1364 Reconstruction 0-003-006 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0560 Reconstruction 0-003-007 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1390 Reconstruction 0-003-008 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1436 Reconstruction 0-003-009 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1075 Reconstruction 0-003-010 03/21/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0335 Additions and Alterations 0-003-012 07/13/04 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0080 Reconstruction 0-003-013 03/26/03 *CO No.* Amount Disallowed Received Approved Contractor
01-001 6,128 03/04/04 03/15/04 Cali Brothers
03-001 -5,000 04/05/04 04/08/04 Pearl River Plumbing
04-001 395 03/04/04 03/25/04 Fanshawe Inc
03-0449 Reconstruction 0-003-014 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1062 Reconstruction 0-003-015 02/12/04 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1427 Reconstruction 0-003-016 07/19/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0991 Reconstruction 0-003-017 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0682FP Reconstruction 0-003-FP1 03/03/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nanuet Middle:
98-1363 Reconstruction 0-004-003 07/15/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0561 Reconstruction 0-004-004 03/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1389 Reconstruction 0-004-005 07/01/99 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1438 Reconstruction 0-004-006 07/23/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1078 Additions and Alterations 0-004-007 06/06/00 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0065 Reconstruction 0-004-008 05/07/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0450 Reconstruction 0-004-009 01/21/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0992 Reconstruction 0-004-011 05/09/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0680FP Reconstruction 0-004-FP1 12/19/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Maintenance Building:
98-1703 New Construction 7-007-001 10/22/99 NO CHANGE ORDERS ON ELECTRONIC FILE
Land Purchse w/23 Structures(See L):
06-0690 New Construction 7-011-001 03/21/07 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
98-1165 Reconstruction 7-999-001 05/06/99 NO CHANGE ORDERS ON ELECTRONIC FILE
NORTH ROCKLAND/HAVERSTRAW-STONY PT STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-02-01-06
last updated on 09/05/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Farley Middle School:
03-1549 Reconstruction 0-003-007 06/01/04 *CO No.* Amount Disallowed Received Approved Contractor
0 3 / / / /
0 / / / /
0 3 / / / /
01 -44,900 02/16/05 02/18/05 Milcon Construction
02 14,000 02/16/05 02/18/05 Milcon Construction
03 6,100 06/10/05 06/30/05 Milcon Construction Corp
RC-04 1,178,300 05/20/05 06/03/05 Milcon Construction Corp
RC-05 11,900 07/22/05 07/26/05 Milcon Construction
RC-06 15,000 02/06/06 12/18/06 Milcon Construction
RC-07 6,400 03/28/06 07/13/06 milcon Construction
RC-08 5,800 03/28/06 07/24/06 Milcon Construction
02-0322FP Reconstruction 0-003-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
No. Garnerville Elem/Admin.:
93-1221 Additions and Alterations 0-007-005 06/16/94 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1368 Reconstruction 0-007-006 06/10/94 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1544 Reconstruction 0-007-008 01/23/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 2,936 01/28/03 02/05/03 NEI/Naber Elec.
GC-1 -15,000 12/23/02 01/10/03 Piazza Brothers
GC-2 -13,800 12/23/02 01/10/03 Piazza Brothers
PC-1 3,990 01/28/03 02/05/03 Thomas Kempton
PC-2 3,200 05/02/03 05/05/03 Thomas Kempton
01-0285 Reconstruction 0-007-010 02/08/02 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0323FP Reconstruction 0-007-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Haverstraw Middle School:
97-0560 Reconstruction 0-009-008 12/29/97 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0713 Reconstruction 0-009-009 12/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 5,000 06/23/04 06/28/04 Pearl River Plumbing
2 4,850 06/23/04 06/28/04 Pearl River Plumbing
3 14,800 06/23/04 06/28/04 Pearl River Plumbing
4 5,929 06/23/04 06/28/04 Pearl River Plumbing
99-1139 Reconstruction 0-009-010 06/22/00 *CO No.* Amount Disallowed Received Approved Contractor
EC-11 1,309 12/12/02 01/07/03 Ray S. Pantel
EC-13 870 03/20/03 03/28/03 Ray S. Pantel
EC-14 -5,000 10/10/03 11/05/03 Ray S. Pantel
EC-3 1,007 11/29/02 01/02/03 Ray S. Pantel
EC-4 2,416 12/23/02 01/10/03 Ray S. Pantel
G-15 -7,000 12/17/03 12/29/03 Helmer Cronin
G-7 1,524 12/23/02 01/10/03 Helmer Cronin
HC-5 -1,250 07/28/03 08/04/03 Hauser Brothers
Gerald F. Neary Elementary:
02-1498 Reconstruction 0-011-004 04/08/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Railroad Avenue School (Alt. Ed. Bld:
03-0770 Reconstruction 0-013-001 02/20/04 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1389 Reconstruction 0-013-002 10/21/05 *CO No.* Amount Disallowed Received Approved Contractor
1 2,021 02/15/07 03/14/07 KG Construction Associates
Stony Point Elementary:
92-0463 Additions and Alterations 0-014-005 01/27/93 NO CHANGE ORDERS ON ELECTRONIC FILE
North Rockland High School:
90-1498 Reconstruction 0-016-007 06/14/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0073 Reconstruction 0-016-008 09/07/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0235 Reconstruction 0-016-009 10/28/93 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1683 Additions and Alterations 0-016-010 06/16/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1090 Reconstruction 0-016-011 08/30/95 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1362 Reconstruction 0-016-013 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0175 Reconstruction 0-016-015 02/05/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 4,150 11/29/02 12/09/02 Ray Pantel Elec.
EC-10 2,236 12/23/02 01/02/03 Ray Pantel
EC-12 1,750 03/20/03 03/24/03 Ray Pantel
EC-2 4,174 11/29/02 12/09/02 Ray Pantel
EC-5 2,236 11/22/02 01/08/03 Ray Pantel
EC-6 280 11/22/02 01/08/03 Ray Pantel
EC-7 1,415 11/22/02 01/08/03 Ray Pantel
EC-8 2,830 11/22/02 01/08/03 Ray Pantel
EC-9 1,677 12/02/02 01/02/03 Ray Pantel
G-1 51,480 12/23/02 01/10/03 Helmer Cronin Const.
G-10 6,036 11/22/02 01/08/03 Helmer Cronin Const.
G-11 1,493 11/22/02 01/08/03 Helmer Cronin Const.
G-12 1,819 11/22/02 01/08/03 Helmer Cronin Const.
G-13 -1,000 12/17/03 12/26/03 Helmer Cronin Const.
G-14 -26,452 12/17/03 12/26/03 Helmer Cronin Const.
G-2 2,117 12/23/02 01/10/03 Helmer Cronin Const.
G-3 1,732 12/23/02 02/21/03 Helmer Cronin Const.
G-4 3,850 12/23/02 02/21/03 Helmer Cronin Const.
G-5 1,900 12/23/02 01/10/03 Helmer Cronin Const.
G-6 853 12/23/02 02/21/03 Helmer Cronin Const.
G-8 21,500 12/23/02 01/10/03 Helmer Cronin Const.
G-9 938 12/23/02 01/10/03 Helmer Cronin Const.
HB-3 4,995 02/03/04 02/03/04 Hauser Brothers
HC-1 1,250 12/23/02 01/07/03 Hauser Brothers
HC-2 4,700 12/23/02 01/07/03 Hauser Brothers
HC-4 7,171 07/28/03 07/29/03 Hauser Brothers
PC-1 5,064 01/28/03 02/05/03 Thomas Kempton
PC-2 -5,000 10/10/03 12/22/03 Thomas Kempton
PW-1 15,500 12/23/02 01/07/03 Urban-Suburban Recreation
PW-2 9,638 12/23/02 01/07/03 Urban-Suburban Recreation
PW-3 25,544 03/12/02 05/06/02 Urban-Suburban Recreation
SC-1 104,250 01/28/03 02/05/03 Mountain View Const.
SC-2 80,812 02/11/02 03/22/02 Mountain View Const.
SC-3 19,136 03/12/02 05/06/02 Mountain View Const.
SC-4 -1,654 12/22/03 12/26/03 Mountain View Const.
00-1868 Additions and Alterations 0-016-016 06/12/01 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1071 Reconstruction 0-016-017 05/24/04 *CO No.* Amount Disallowed Received Approved Contractor
04 1,600 06/10/05 07/20/05 Carjen Fence Co
05 -1,746 10/21/05 11/08/05 Carjen Fence Co
GC-01 5,000 06/10/05 07/20/05 carjen Fence Co
GC-02 6,600 06/10/05 07/20/05 Carjen Fence Co
GC-03 2,400 06/10/05 07/20/05 Carjen Fence Co
GW-06 -5,000 03/28/06 07/21/06 Carjen Fence Co
04-0319 Reconstruction 0-016-018 11/05/04 *CO No.* Amount Disallowed Received Approved Contractor
GW-04 200 02/06/06 / / Conserv Construction
GW-2 4,500 02/06/06 / / Conserv Corp
GW-3 14,212 10/21/05 11/07/05 Consery Corp
03-1550 Reconstruction 0-016-019 07/16/04 *CO No.* Amount Disallowed Received Approved Contractor
01 -6,611 06/10/05 01/11/06 Eagle Electric
02 5,400 06/10/05 08/18/05 Eagle electric
03 1,472 03/28/06 04/21/06 Eagle Electric
02-0319FP Reconstruction 0-016-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
06-0139 Visual Structural Inspection 0-016-SC1 08/07/06 NO CHANGE ORDERS ON ELECTRONIC FILE
West Haverstraw Elementary:
92-0629 Reconstruction 0-024-005 03/10/93 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1361 Reconstruction 0-024-006 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0284 Reconstruction 0-024-007 02/08/02 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1388 Reconstruction 0-024-008 10/21/05 *CO No.* Amount Disallowed Received Approved Contractor
1 14,400 11/15/06 01/09/07 Monpat Construction
2 6,400 02/13/07 03/14/07 Monpat Construction
02-0321FP Reconstruction 0-024-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
Thiells Elementary School:
92-1134 Additions and Alterations 0-025-006 05/05/93 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0403 Reconstruction 0-025-008 11/07/97 *CO No.* Amount Disallowed Received Approved Contractor
1 88,920 01/28/03 02/11/03 Ed Coupart & Son
2 14,375 01/28/03 02/11/03 Ed Coupart & Son
99-0303 Reconstruction 0-025-009 10/07/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1192 Reconstruction 0-025-011 04/09/04 *CO No.* Amount Disallowed Received Approved Contractor
01 -109,600 02/16/05 02/18/05 Milcon Construction Corp
02 29,080 06/10/05 06/30/05 Milcon Construction
03 18,890 08/23/06 08/25/06 Milcon Construction
02-0320FP Reconstruction 0-025-FP1 11/13/02 NO CHANGE ORDERS ON ELECTRONIC FILE
8/9th Grade Ctr. @ Letchworth:
01-1106SR New Construction 0-031-001 05/23/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
EC-01 19,631 05/19/08 / / All Bright Electric
GC-67 16,804 05/19/08 / / Morris Park Contracting
GC-68 55,625 05/19/08 / / Morris Park Contracting
HC-01 975,000 05/19/08 / / David L. Kempton Inc.
PC-01 16,448 05/19/08 / / Davidson and Howard
SC-01 0 12/09/02 01/07/03 Pinnacle Environ.
02-0309 New Construction 0-031-001 12/11/02 *CO No.* Amount Disallowed Received Approved Contractor
CW-01 4,180 06/16/05 07/12/05 Longo Associates
EC-01 19,630 03/15/04 08/11/08 All Bright Electric
EC-02 56,780 10/12/04 10/18/04 All Bright Electric
EC-03 22,147 06/07/04 06/22/04 All Bright Electric
EC-04 3,512 06/07/04 06/22/04 All Bright Electric
EC-05 6,696 06/07/04 06/22/04 All Bright Electric
EC-06 122,910 122,910 06/17/04 09/27/04 All Bright Electric
EC-07 19,248 06/16/04 09/27/04 All Bright Electric
EC-08 11,454 09/29/04 12/24/04 All Bright Electric
EC-09 19,954 12/06/04 12/23/04 All Bright Electric
EC-10 7,323 09/29/04 12/24/04 All Bright Electric
EC-11 43,343 09/29/04 12/24/04 All Bright Electric
EC-12 10,005 09/29/04 12/24/04 All Bright Electric
EC-13 -5,391 09/29/04 12/24/04 All Bright Electric
EC-14 19,555 11/01/04 12/06/04 All Bright Electric
EC-15 14,297 11/01/04 12/21/04 All Bright Electric
EC-16 8,212 11/18/04 12/06/04 All Bright Electric
EC-17 18,772 01/18/05 03/17/05 All Bright Electric
EC-18 18,184 01/18/05 03/17/05 All Bright Electric
EC-19 16,830 01/18/05 03/17/05 All Bright Electric
EC-20 17,597 01/18/05 03/17/05 All Bright Electric
EC-21 14,735 01/18/05 03/17/05 All Bright Electric
EC-25 67,810 06/13/05 07/12/05 All Bright Electric
EC-26 17,159 06/13/05 07/12/05 All Bright Electric
EC-29 5,890 09/18/06 10/19/06 All Bright Electric
EC-30 4,000 09/18/06 10/19/06 All Bright Electric
EQ-01 4,428 01/18/05 03/18/05 Nickerson Corp
EQ-02 3,575 10/24/05 11/08/05 Nickerson Corp
FS-01 3,100 10/24/05 11/08/05 E Friedman Associates
GC-01 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-02 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-03 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-04 16,566 07/28/03 07/29/03 Morris Park Contracting
GC-05 17,603 07/28/03 07/29/03 Morris Park Contracting
GC-06 12,020 10/23/03 11/18/03 Morris Park Contracting
GC-07 16,283 10/23/03 11/18/03 Morris Park Contracting
GC-08 14,460 10/23/03 11/18/03 Morris Park Contracting
GC-09 4,062 10/23/03 11/18/03 Morris Park Contracting
GC-10 10,323 10/10/03 11/26/03 Morris Park Contracting
GC-11 12,032 10/10/03 11/26/03 Morris Park Contracting
GC-12 10,201 10/10/03 11/26/03 Morris Park Contracting
GC-13 6,771 10/10/03 11/26/03 Morris Park Contracting
GC-14 17,550 10/20/03 11/17/03 Morris Park Contracting
GC-15 19,643 11/13/03 12/26/03 Morris Park Contracting
GC-16 40,000 11/13/03 12/26/03 Morris Park Contracting
GC-17 10,809 11/13/03 11/24/03 Morris Park Contracting
GC-19 11,701 12/17/03 12/26/03 Morris Park Contracting
GC-20 19,620 01/23/04 03/08/04 Morris Park Contracting
GC-21 9,876 03/15/04 04/07/04 Morris Park Contracting
GC-22 13,333 03/15/04 04/07/04 Morris Park Contracting
GC-23 15,722 06/07/04 06/22/04 Morris Park Contracting
GC-24 14,247 06/07/04 06/22/04 Morris Park Contracting
GC-25 8,463 06/07/04 06/14/04 Morris Park Contracting
GC-26 23,926 06/07/04 06/22/04 Morris Park Contracting
GC-27 13,825 06/07/04 06/22/04 Morris Park Contracting
GC-28 11,591 06/07/04 06/22/04 Morris Park Contracting
GC-29 30,100 06/07/04 06/22/04 Morris Park Contracting
GC-30 12,730 06/07/04 06/22/04 Morris Park Contracting
GC-31 8,080 06/07/04 06/22/04 Morris Park Contracting
GC-32 14,830 06/07/04 06/22/04 Morris Park Contracting
GC-33 14,484 06/17/04 06/22/04 Morris Park Contracting
GC-34 2,633 09/29/04 12/24/04 Morris Park Contracting
GC-35 12,429 09/29/04 12/24/04 Morris Park Contracting
GC-36 18,259 09/29/04 12/24/04 Morris Park Contracting
GC-37 15,366 09/29/04 12/24/04 Morris Park Contracting
GC-38 19,795 09/29/04 12/24/04 Morris Park Contracting
GC-39 19,590 09/29/04 12/24/04 Morris Park Contracting
GC-40 18,449 09/29/04 12/24/04 Morris Park Contracting
GC-41 11,740 09/29/04 12/24/04 Morris Park Contracting
GC-42 19,132 09/29/04 12/24/04 Morris Park Contracting
GC-43 10,285 09/29/04 12/24/04 Morris Park Contracting
GC-44 -1,492 09/29/04 12/24/04 Morris Park Contracting
GC-45 16,109 11/01/04 12/21/04 Morris Park Contracting
GC-46 14,158 11/01/04 12/21/04 Morris Park Contracting
GC-47 13,462 11/01/04 12/21/04 Morris Park Contracting
GC-48 13,674 11/01/04 12/06/04 Morris Park Contracting
GC-49 9,471 11/01/04 12/06/04 Morris Park Contracting
GC-50 19,635 11/10/04 12/06/04 Morris Park Contracting
GC-51 -955 11/10/04 12/06/04 Morris Park Contracting
GC-52 16,025 11/10/04 12/06/04 Morris Park Contracting
GC-53 2,436 11/10/04 12/06/04 Morris Park Contracting
GC-54 11,567 11/10/04 12/06/04 Morris Park Contracting
GC-56 9,616 01/24/05 03/18/05 Morris Park Contracting Corp
GC-57 16,991 01/24/05 03/18/05 Morris park Contracting
GC-58 15,280 01/24/05 03/18/05 Morris Park Contracting
GC-59 19,604 01/18/05 / / Morris Park Contracting Corp
GC-59 19,604 01/18/05 03/17/05 Morris Park Contracting
GC-60 10,257 01/24/05 03/18/05 Morris Park Contracting Corp
GC-61 9,888 01/24/05 03/18/05 Morris Park Contracting
GC-62 33,558 01/24/05 03/18/05 Morris Park Contracting Corp
GC-63 13,597 01/24/05 03/18/05 Morris Park Contracting
GC-64 11,217 01/24/05 03/18/05 Morris Park Contracting Corp
GC-65 21,820 01/24/05 03/18/05 Morris Park Contracting
GC-66 7,136 04/08/05 04/24/06 Morris Park Contracting
GC-67 16,804 04/08/05 / / Morris Park Contracting
GC-68 55,625 04/08/05 08/11/08 Morris Park Contracting
GC-69 21,244 04/08/05 04/24/06 Morris Park Contracting
GC-70 17,179 04/08/05 06/15/05 Morris Park Contracting
GC-71 15,659 04/08/05 06/15/05 Morris Park Contracting
GC-72 10,221 04/08/05 06/15/05 Morris Park Contracting
GC-73 3,738 04/08/05 06/15/05 Morris Park Contracting
HC-01 975,000 10/10/03 08/11/08 David Kempton
HC-02 17,735 10/24/05 10/26/05 David kempton Inc
HC-03 15,463 10/24/05 11/01/05 david kempton
HC-04 2,218 08/19/05 09/02/05 David kampton
HC-05 3,159 03/31/06 07/24/06 David kempton
HC-06 2,307 09/18/06 10/19/06 David Kempton
PC-01 16,448 03/15/04 08/11/08 Davidson and Howard
PC-02 6,804 04/07/04 06/22/04 Davidson and Howard
PC-03 4,575 09/29/04 12/24/04 Davidson and Howard
PC-04 14,284 11/10/04 12/06/04 Davidson and Howard
PC-05 19,858 01/18/05 03/22/05 Davidson and Howard Inc
PC-06 6,791 04/08/05 06/21/05 Davidson and Howard Inc
PC-07 -1,052 10/24/05 10/26/05 Davidson and Howard
SC-02 13,500 03/20/03 03/24/03 Pinnacle Environ.
SC-03 8,740 03/20/03 03/24/03 Pinnacle Environ.
SC-04 12,760 03/20/03 03/24/03 Pinnacle Environ.
SC-05 8,426 08/12/03 08/14/03 Pinnacle Environ.
SC-06 -94,886 06/07/04 06/22/04 Pinnacle Environ.
05-0346SC Visual Structural Inspection 0-031-SC1 11/15/05 NO CHANGE ORDERS ON ELECTRONIC FILE
8/9 Grade Ctr-Mechanical Bldg.(#28):
02-0310 Reconstruction 0-042-001 12/11/02 *CO No.* Amount Disallowed Received Approved Contractor
GC-18 11,324 12/17/03 12/26/03 Morris Park Contracting
03-1651 Reconstruction 0-042-002 01/26/05 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1525 Reconstruction 0-042-003 06/05/07 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 29:
99-1202 Reconstruction 0-043-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
````````````` Bldg 31:
99-0665 Reconstruction 0-045-001 04/10/00 *CO No.* Amount Disallowed Received Approved Contractor
AC-1 -10,000 01/17/02 03/26/02 Netrix
CAT Letchworth Bldg 32:
99-0666 Reconstruction 0-046-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 33:
99-0667 Reconstruction 0-047-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 35:
99-0668 Reconstruction 0-049-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 36:
99-0669 Reconstruction 0-050-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 37:
99-0670 Reconstruction 0-051-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
CAT Letchworth Bldg 38:
99-0671 Reconstruction 0-052-001 04/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
Railroad Ave Admin. Bldg.:
96-0255 Reconstruction 1-013-004 09/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1140 Reconstruction 1-013-005 06/22/00 NO CHANGE ORDERS ON ELECTRONIC FILE
Maintenance Garage:
96-1363 Reconstruction 3-002-003 05/22/97 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
99-1647 Reconstruction 7-999-003 06/20/00 *CO No.* Amount Disallowed Received Approved Contractor
G-1 12,306 01/28/03 02/03/03 Tenavision
G-2 5,918 01/28/03 02/03/03 Tenavision
G-3 7,526 01/28/03 02/03/03 Tenavision
G-4 61,205 02/06/02 05/05/03 Tenavision
G-5 19,409 02/06/02 03/21/02 Tenavision
G-6 19,562 12/23/02 01/14/03 Tenavision
G-7 11,135 12/23/02 01/14/03 Tenavision
Willow Grove Middle School:
96-1023 Reconstruction 8-030-002 04/16/97 *CO No.* Amount Disallowed Received Approved Contractor
PC-01 -15,320 10/24/05 11/25/05 David kempton
97-0502 Additions and Alterations 8-030-003 12/18/97 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0124 Reconstruction 8-030-005 09/17/02 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0496 Reconstruction 8-030-006 03/12/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1541 Reconstruction 8-030-008 07/16/04 *CO No.* Amount Disallowed Received Approved Contractor
01 9,504 02/16/05 02/18/05 Nikko Construction Corp
02 11,695 02/16/05 02/18/05 Nikko Construction
03 4,604 02/16/05 02/18/05 Nikko Construction
04 13,981 02/16/05 02/18/05 Nikko Construction
03-1563 Reconstruction 8-030-009 07/23/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1769 Reconstruction 8-030-010 07/29/08 NO CHANGE ORDERS ON ELECTRONIC FILE
SOUTH ORANGETOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-01-06
last updated on 09/05/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Tappan Zee High School:
90-1294 Reconstruction 0-006-009 05/02/91 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0521 Additions and Alterations 0-006-010 03/11/99 *CO No.* Amount Disallowed Received Approved Contractor
7 4,802 03/15/00 12/01/03 Rockland Elec.
97-0228 Reconstruction 0-006-011 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0775 Reconstruction 0-006-012 01/27/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1431 Reconstruction 0-006-014 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1478 Additions and Alterations 0-006-015 06/28/05 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
1C-SC133 -9,000 10/05/07 11/08/07 LANDTEK
1C-SC134 5,000 10/05/07 11/08/07 LANDTEK
1C-SC135 -6,000 10/05/07 11/08/07 LANDTEK
1C-SC136 1,000 10/05/07 / / LANDTEK
EC-201 0 08/04/06 08/31/06 Perreca Electric
EC-207 1,645 11/07/06 01/30/07 Perreca electric
EC-208 886 11/07/06 01/30/07 Perreca Electric
EC-210 -1,719 11/07/06 01/30/07 Perreca Electric
EC202 2,201 08/04/06 08/31/06 Perreca Elecgtric
EC203 3,550 08/25/06 10/12/06 Perreca Electric
EC205 0 08/25/06 10/12/06 Perreca Electric
EC206 15,214 08/25/06 10/12/06 Perreca Electric
SC-110 0 08/25/06 10/13/06 Landtek
SC-115 0 08/25/06 10/13/06 Landtek
SC-122 0 07/05/07 07/17/07 Landtek
SC-123 13,175 07/05/07 07/17/07 Landtek
SC-125 7,000 07/05/06 07/17/07 Landtek
SC-126 -4,400 07/05/07 07/17/07 Landtek
SC-128 0 07/05/07 07/17/07 Landtek
SC-129 4,000 07/05/07 07/17/07 Landtek
SC-130 700 07/05/07 / / Landtek
SC-131 5,900 07/05/07 07/17/07 Landtek
SC132 1,720 07/05/07 07/17/07 Landtek
Sc127 7,265 07/05/07 07/17/07 Landtek
05-0523 Reconstruction 0-006-016 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2 EC220 0 03/06/07 04/03/07 Fanshawe Inc
2 PC402 0 03/06/07 03/13/07 Pearl River Plumbing
2-EC 235 5,234 02/28/08 04/15/08 FANSHAWE
2-EC 236 651 02/28/08 04/15/08 FANSHAWE
2-EC 237 835 02/28/08 04/15/08 FANSHAWE
2-EC 241 1,900 02/28/08 04/15/08 FANSHAWE
2-EC 242 7,900 02/28/08 04/15/08 FANSHAWE
2-EC 243 6,292 02/28/08 04/15/08 FANSHAWE
2-EC-244 3,414 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-247 1,867 03/17/08 / / FANSHAWE, INC.
2-EC-248 -2,500 03/17/08 / / FANSHAWE, INC.
2-GC-157 85,298 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-158 55,030 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-159 2,006 10/05/07 11/08/07 FOURMAN CONSTRUCTION INC.
2-GC-162 6,208 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-163 3,689 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-164 23,024 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-168 15,000 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-169 -2,023 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-GC-170 -1,600 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-GC-171 -4,793 03/17/08 03/31/08 FOURMEN CONSTRUCTION INC.
2-MC-315 -2,980 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-316 1,532 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-317 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-318 2,198 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-320 -436 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-322 3,085 02/28/08 04/15/08 PEARL RIVER PLUMBING & HEATING
2-MC-324 2,401 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-PC-406 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-408 41,224 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-409 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-410 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-411 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-414 1,926 06/02/08 / / Pearl River Plumbing
2-pc-405 571 10/05/07 11/09/07 Peal river plubing, heating & ele.
20MC-316 1,532 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2EC 204 0 03/06/07 04/03/07 Fanshawe Inc
2EC 205 0 03/06/07 04/03/07 Fanshawe Inc
2EC 206 0 03/06/07 04/03/07 Fanshawe Inc
2EC 207 0 03/06/07 04/03/07 Fanshawe Inc
2EC 208 0 03/06/07 04/03/07 Fanshawe Inc
2EC 209 0 03/06/07 04/03/07 Fanshawe Inc
2EC 210 0 03/06/07 04/03/07 Fanshawe Inc
2EC 211 -12,481 03/06/07 04/03/07 Fanshwe Inc
2EC 212 0 03/06/07 04/03/07 Fanshwe Inc
2EC 213 0 03/06/07 04/03/07 Fanshwe Inc
2EC 214 0 04/06/07 04/03/07 Fanshawe Inc
2EC 215 0 03/06/07 04/03/07 Fanshawe Inc
2EC 216 0 03/06/07 04/03/07 Fanshawe Inc
2EC 217 0 03/06/07 04/03/07 Fanshawe Inc
2EC 218 0 04/06/07 04/04/07 Fanshawe Inc
2EC 219 0 03/06/07 04/04/07 Fanshawe Inc
2EC 221 0 03/06/07 04/03/07 Fanshawe Inc
2EC 227 -4,565 06/15/07 / / Fanshawe Inc
2EC-222 0 05/01/07 05/15/07 Fanshawe Inc
2EC-223 0 05/01/07 05/15/07 Fanshawe Inc
2EC-224 0 05/01/07 05/15/07 Fanshawe Inc
2EC-225 -360 05/01/07 05/15/07 Fanshaw Inc
2EC-226 3,600 06/15/07 06/20/07 Fanshawe Inc
2EC-227 -4,565 06/15/07 06/20/07 Fanshawe Inc
2EC-228 7,471 06/15/07 06/20/07 Fanshawe Inc
2EC-229 85,825 06/15/07 06/20/07 Fanshawe Inc
2EC-230 -17,603 06/15/07 06/20/07 Fanshawe Inc
2EC-231 0 06/15/07 06/20/07 Fanshawe Inc
2EC-232 2,823 06/15/07 06/20/07 Fanshawe Inc
2EC-233 -5,673 06/15/07 06/20/07 Fanshawe Inc
2EC-234 2,151 06/15/07 06/20/07 Fanshawe Inc
2GC-101 -438 11/07/06 01/09/07 Fourmen Construction
2GC-105 15,453 11/07/06 12/28/06 Fourmen Construction
2GC-106 6,171 11/07/06 12/28/06 Fourmen Construction
2GC-107 -111 05/29/07 06/20/07 Fourmen Construction
2GC-108 0 05/29/07 06/20/07 Fourmen Construction
2GC-109 0 05/29/07 06/20/07 Fourmen Construction
2GC-110 0 05/29/07 06/20/07 Fourmen Construction
2GC-111 -13,149 05/29/07 06/20/07 Fourmen Construction
2GC-112 0 05/29/07 06/20/07 Fourmen Construction
2GC-113 0 05/29/07 06/20/07 Fourmen Construction
2GC-114 0 05/29/07 06/20/07 Fourmen Construction
2GC-115 0 05/29/07 06/20/07 Fourmen Construction
2GC-116 0 05/29/07 06/20/07 Fourmen Construction
2GC-117 -47,593 05/29/07 06/20/07 Fourmen Construction
2GC-118 0 05/29/07 06/20/07 fourmen Construction
2GC-119 -2,473 05/29/07 06/20/07 Fourmen Construction
2GC-120 -12,034 05/29/07 06/20/07 Fourmen Construction
2GC-121 12,034 05/29/07 06/20/07 Fourmen Construction
2GC-122 -3,319 05/29/07 06/20/07 Fourmen Construction
2GC-123 0 05/29/07 06/20/07 Fourmen Construction
2GC-125 0 05/29/07 06/20/07 Fourmen Construction
2GC-126 0 05/29/07 06/20/07 Fourmen Construction
2GC-127 0 05/29/07 06/20/07 Fourmen Construction
2GC-128 0 05/29/07 06/20/07 Fourmen Construction
2GC-129 -16,656 05/29/07 06/20/07 Fourmen Construction
2GC-130 -3,300 05/29/07 06/20/07 Fourmen Construction
2GC-131 4,152 05/29/07 06/20/07 Fourmen Construction
2GC-132 0 05/29/07 06/20/07 Fourmen Construction
2GC-133 0 05/29/07 06/20/07 Fourmen Construction
2GC-134 0 05/29/07 06/20/07 Fourmen Construction
2GC-135 52,500 05/29/07 06/20/07 Fourmen Construction
2GC-136 12,619 05/29/07 06/20/07 Fourmen Construction
2GC-137 19,274 05/29/07 / / Fourmen Construction
2GC-138 12,680 05/29/07 06/20/07 Fourmen Construction
2GC-139 23,419 05/29/07 06/20/07 Fourmen Construction
2GC-140 1,864 05/29/07 06/20/07 Fourmen Construction
2GC-141 1,425 05/29/07 06/20/07 Fourmen Construction
2GC-142 2,349 05/29/07 06/20/07 Fourmen Construction
2GC-143 6,991 05/29/07 06/20/07 Fourmen Construction
2GC-145 2,631 05/29/07 06/20/07 Fourmen Construction
2GC-146 3,837 05/29/07 06/20/07 Fourmen Construction
2GC-147 10,149 05/29/07 06/20/07 Fourmen Construction
2GC-148 34,536 05/29/07 06/20/07 Fourmen Construction
2GC-149 21,379 05/29/07 06/20/07 Fourmen Construction
2GC-150 1,357 05/29/07 06/20/07 Fourmen Construction
2GC-151 5,482 05/29/07 06/20/07 Fourmen Construction
2GC-152 3,500 05/29/07 06/20/07 Fourmen Construction
2GC-153 2,429 05/29/07 06/20/07 Fourmen Construction
2GC-154 -5,000 06/15/07 06/20/07 Fourmen Construction
2GC-155 -9,900 06/15/07 06/20/07 Fourmen Construction
2GC-156 14,363 03/15/07 06/20/07 Fourmen Construction
2GC124 0 05/29/07 06/20/07 Fourmen Construction
2Gc-144 6,139 05/29/07 06/20/07 Fourmen Construction
2MC 305 0 03/06/07 03/13/07 Pearl River Plumbing
2MC 309 -16,391 05/01/07 07/27/07 Pearl River Plumbing
2MC 311 0 05/01/07 07/27/07 Pearl River Plumbing
2MC 312 0 05/01/07 07/27/07 Pearl River Plumbing
2MC306 0 03/06/07 03/13/07 Pearl River Plumbing
2MC307 0 03/06/07 03/13/07 Pearl River Plumbing
2MC308 0 04/06/07 03/13/07 Pearl River Plumbing
2MC313 0 05/01/07 07/27/07 Pearl River Plumbing
2Mc 310 14,804 05/01/07 07/27/07 Pearl River Plumbing
2PC 401 0 03/06/07 03/13/07 Pearl River Plumbing
2PC 403 0 03/06/07 03/13/07 Pearl River Plumbing
2PC 404 0 03/06/07 03/13/07 Pearl River Plumbing
4 3,017 06/02/08 / / Peart River Plumbing & Heating
07-0580 Reconstruction 0-006-017 10/18/07 *CO No.* Amount Disallowed Received Approved Contractor
GC X-001 8,139 03/17/08 03/31/08 TRITION CONSTRUCTION COMPANY
GC X-002 2,515 03/17/08 03/31/08 TRITION CONSTRUCTION COMPANY
08-0140 Reconstruction 0-006-018 08/19/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2170FP Reconstruction 0-006-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Tappan Zee Elementary:
93-0802 Reconstruction 0-007-008 03/25/94 NO CHANGE ORDERS ON ELECTRONIC FILE
98-0115 Additions and Alterations 0-007-009 10/30/98 *CO No.* Amount Disallowed Received Approved Contractor
2 16,100 11/19/99 01/16/03 Environcon LLC
97-0229 Reconstruction 0-007-010 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1432 Reconstruction 0-007-011 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0524 Additions and Alterations 0-007-012 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-GC-166 24,745 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-MC-314 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
02-2166FP Reconstruction 0-007-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Cottage Lane Elementary:
98-0116 Additions and Alterations 0-010-008 10/30/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0230 Reconstruction 0-010-009 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1433 Reconstruction 0-010-010 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0525 Additions and Alterations 0-010-011 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-EC 240 7,875 02/28/08 / / FANSHAWE
2-EC-245 707 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-246 1,000 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-247 1,867 03/17/08 08/06/08 FANSHAWE, INC.
2-EC-248 -2,500 03/17/08 08/06/08 FANSHAWE, INC.
2-GC-161 16,943 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-165 -4,824 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-GC-167 27,984 02/28/08 04/14/08 FOURMEN CONSTRUCTION
2-MC 321 34,877 02/28/08 / / PEARL RIVER PLUMBING & HEATING
2-MC 323 45,888 02/28/08 / / PEARL RIVER PLUMBING & HEATING
2-MC-319 3,735 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-MC-325 -2,988 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-MC-326 1,392 03/17/08 08/06/08 PEARL RIVER PLUMBING, HEATING & E
2-PC-407 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-412 0 10/05/07 01/23/08 PEARL RIVER PLUMBING, HEATING & ELEC
2-PC-413 2,312 06/02/08 / / Pearl River Plumbing
04-1075 Reconstruction 0-010-013 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
101A-080 -579 08/04/06 08/31/06 S and M Management
102A -1,082 08/04/06 08/31/06 S and M Management
103a 1,253 08/04/06 08/31/06 S and M Management
104 0 08/04/06 08/31/06 S and M Managment
106A 0 08/04/06 08/31/06 S and M managment
02-2168FP Reconstruction 0-010-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
William Schaefer Elementary:
98-0118 Additions and Alterations 0-012-005 10/30/98 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0231 Reconstruction 0-012-006 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1430 Reconstruction 0-012-007 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0526 Additions and Alterations 0-012-008 02/23/06 *CO No.* Amount Disallowed Received Approved Contractor
2-EC 238 2,176 02/28/08 04/15/08 FANSHAWE
2-EC 239 2,840 02/28/08 04/15/08 FANSHAWE
2-GC-160 -29,519 02/28/08 04/14/08 FOURMEN CONSTRUCTION
04-1076 Reconstruction 0-012-010 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
102B -1,083 08/04/06 08/31/06 S and M Management
103B 1,253 08/04/06 08/31/06 S and M Management
106B 0 08/04/06 08/31/06 S and M Management
108 6,475 08/04/06 08/31/06 S and M Managment
1afo109 0 08/04/06 09/06/06 S&M Management Inc.
q01B -579 08/04/06 08/31/06 S and M Management
02-2169FP Reconstruction 0-012-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Middle School:
98-0520 Additions and Alterations 0-013-010 03/11/99 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0232 Reconstruction 0-013-011 02/03/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1434 Reconstruction 0-013-012 08/03/99 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0860 Reconstruction 0-013-013 03/05/01 NO CHANGE ORDERS ON ELECTRONIC FILE
04-1160 Reconstruction 0-013-014 05/10/05 *CO No.* Amount Disallowed Received Approved Contractor
1BPC-401 0 10/05/07 / / PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-402 0 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-403 0 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
1BPC-404 -649 10/05/07 10/23/07 PEARL RIVER PLUMBING, HEATING & ELEC
EC 221 2,649 03/06/07 03/23/07 Fanshawe Inc
EC 222 479 03/06/07 03/23/07 Fanshawe Inc
EC 223 463 03/06/07 03/23/07 Fanshawe Inc
EC 224 691 03/06/07 03/23/07 Fanshawe Inc
EC 225 432 03/06/07 03/23/07 Fanshawe Inc
EC 226 3,817 03/06/07 03/23/07 Fanshawe Inc
EC-208 0 08/04/06 08/25/06 Fansshawe
EC-217 1,237 08/25/06 10/13/06 Fanshawe, inc.
EC202 5,137 08/04/06 08/25/06 Fanshawe
EC203 -19,948 08/04/06 08/25/06 Fanshawe
EC206 0 08/04/06 08/25/06 Fanshawe
EC207 0 08/04/06 08/25/06 Fanshawe
EC209 0 3 08/25/06 10/13/06 Fanshawe
EC210 7,792 08/25/06 10/13/06 Fanshawe
EC213 0 08/25/06 / / Fanshawe
EC216 0 08/25/06 10/13/06 Fanshawe
EC218 1,639 08/25/06 10/13/06 Fanshawe
EC219 9,821 03/06/07 03/23/07 Fanshawe Inc
EC220 3,069 03/06/07 03/23/07 Fanshawe Inc
GC-113 18,687 08/04/06 08/25/06 Fourmen Construction
GC-115 3,994 08/04/06 08/25/06 Fourmen Construction
GC-116 4,165 08/04/06 08/25/06 Fourmen Construction
GC-117 0 08/04/06 08/25/06 Fourmen Construction
GC-122 0 08/04/06 08/25/06 Fourmen Construction
GC114 0 08/04/06 08/25/06 Fourmen Construction
GC118 0 08/25/06 10/13/06 Fourmen Construction
GC121 9,044 08/25/06 10/13/06 Fourmen Construction
GC123 0 08/25/06 10/13/06 Fourmen Construction
GC124 0 08/25/06 10/13/06 Fourmen Construction
GC125 9,911 08/25/06 10/13/06 Fourmen Construction
GC128 1,877 12/27/06 01/23/07 fourmen Construction
GC129 1,568 12/27/06 01/23/07 Fourmen Construction
MC-307 -2,000 05/11/07 05/14/07 David Kempton
MC301 -10,749 05/11/07 05/14/07 David Kempton Inc
MC302 -10,000 05/11/07 05/14/07 David Kempton
MC303 3,000 05/11/07 05/14/07 David Kempton
MC306 -5,000 05/11/07 05/14/07 David Kempton
PC-403 0 08/04/06 08/25/06 Pearl River Plumbing
Pc402 0 08/04/06 08/25/06 Pearl River Plumbing
04-1096 Reconstruction 0-013-017 04/12/05 *CO No.* Amount Disallowed Received Approved Contractor
101C-080 -579 08/04/06 12/18/06 S and M Management
102C -1,082 08/04/06 12/18/06 S and M Management
103C 1,253 08/04/06 12/18/06 S and M Managment
105 0 08/04/06 12/18/06 S and M Management
106C 0 08/04/06 12/18/06 S and M management
07-1076 Additions and Alterations 0-013-018 07/21/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2167FP Reconstruction 0-013-FP1 09/04/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Field House:
04-1479 New Construction 7-019-001 06/28/05 NO CHANGE ORDERS ON ELECTRONIC FILE
NYACK UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-04-03
last updated on 09/05/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Valley Cottage Elementary:
01-0811 Reconstruction 0-001-004 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
01 1,950 09/04/02 10/21/02 Universal Construction
03-1502 Reconstruction 0-001-005 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0800 Reconstruction 0-001-007 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0347FP Reconstruction 0-001-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nyack High School:
92-0199 Reconstruction 0-003-004 09/02/92 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0578 Reconstruction 0-003-005 01/04/95 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0158 Reconstruction 0-003-006 09/26/00 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0676 Reconstruction 0-003-007 12/05/02 *CO No.* Amount Disallowed Received Approved Contractor
H-1 524 05/23/03 06/05/03 David L. Kempton
H-2 1,200 05/23/03 06/05/03 David L. Kempton
H-3 262 05/23/03 06/05/03 David L. Kempton
H-4 3,487 05/23/03 06/05/03 David L. Kempton
H-5 106 05/23/03 06/05/03 David L. Kempton
H-6 942 05/23/03 06/05/03 David L. Kempton
H-7 4,741 05/23/03 06/05/03 David L. Kempton
H-8 5,306 05/23/03 06/05/03 David L. Kempton
02-2255 Reconstruction 0-003-008 05/27/03 *CO No.* Amount Disallowed Received Approved Contractor
R-1 -11,029 12/23/05 02/23/06 DME Construction Assoc
03-1194 Reconstruction 0-003-009 06/30/04 *CO No.* Amount Disallowed Received Approved Contractor
EC-01 6,885 05/24/05 05/24/05 Fanshawe Inc
EC-02 14,933 12/23/05 02/23/06 Fanshawe
EC-03 6,960 12/23/05 01/19/06 Fanshawe
EC-04 13,290 12/23/05 01/19/06 Fanshawe Inc
EC-05 5,212 06/23/06 11/30/06 Fanshawe
EC-06 2,496 06/23/06 11/30/06 Fanshawe
EC-07 2,335 01/10/07 03/23/07 Fasnshaws Inc
GW-06 18,260 03/28/06 06/13/06 Holt Construction
GW-1 12,691 12/23/05 05/24/06 Holt Construction
GW-2 10,096 12/23/05 02/23/06 Holt Construction
GW-3 5,900 12/23/05 02/23/06 Holt Construction
GW-4 6,445 12/23/05 02/23/06 Holt Construction
GW-5 4,955 12/23/05 02/23/06 Holt Construction
HC-01 15,900 05/24/05 05/24/05 David Kempton
HW-02 -6,850 06/23/06 03/09/07 David Kempton
HW-03 9,440 06/23/06 / / David kempton
HW-04 4,322 02/14/08 / / DAVID L KEMPTON
MC-01 25,800 03/28/06 06/13/06 Milcon Construction
MC-02 30,133 03/28/06 06/13/06 Milcon Construction
SW-01 12,777 12/23/05 05/24/06 Ascape Landscape Construction
SW-02 3,932 12/23/05 02/23/06 ASCApe Landscape Construction
03-1503 Reconstruction 0-003-010 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0344 Reconstruction 0-003-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Nyack Jr. High School:
94-0476 Reconstruction 0-004-003 12/13/94 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1504 Reconstruction 0-004-004 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0103 Reconstruction 0-004-005 03/03/06 *CO No.* Amount Disallowed Received Approved Contractor
1 10,260 09/29/06 10/19/06 JMK enterprises
2 3,652 03/13/06 06/18/07 JMK Enterprises
3 28,542 01/16/08 01/23/08 JMK Enterprises
4 18,260 01/16/08 01/23/08 JMK Enterprises
07-0801 Reconstruction 0-004-008 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0345FP Reconstruction 0-004-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Hilltop Intermediate:
90-1667 Reconstruction 0-005-002 06/05/91 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1505 Reconstruction 0-005-004 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0802 Reconstruction 0-005-005 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
Liberty Elementary School:
01-0813 Reconstruction 0-006-006 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 13,500 09/04/02 10/21/02 Universal Construction
03-1506 Reconstruction 0-006-007 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0803 Reconstruction 0-006-008 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0348FP Reconstruction 0-006-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Upper Nyack Elementary:
90-1668 Reconstruction 0-007-007 06/05/91 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0812 Reconstruction 0-007-009 03/27/02 *CO No.* Amount Disallowed Received Approved Contractor
1 2,100 09/04/02 10/21/02 Universal Construction
03-1507 Reconstruction 0-007-010 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0024 Reconstruction 0-007-011 07/12/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0804 Reconstruction 0-007-012 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0346FP Reconstruction 0-007-FP1 06/24/03 NO CHANGE ORDERS ON ELECTRONIC FILE
New High School:
03-1508 Reconstruction 0-021-003 04/21/05 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0805 Reconstruction 0-021-005 12/10/07 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
91-1552 Reconstruction 7-999-002 07/14/92 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1740 Reconstruction 7-999-003 08/08/94 NO CHANGE ORDERS ON ELECTRONIC FILE
PEARL RIVER UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 50-03-08-03
last updated on 09/05/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Evans Park School:
91-0352 Reconstruction 0-002-003 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1191 Reconstruction 0-002-004 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1505 Reconstruction 0-002-005 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0841 Reconstruction 0-002-006 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0624 Additions and Alterations 0-002-008 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-04 3,240 01/23/08 04/02/08 FANSHAWE INC
Lincoln Ave.Elementary School:
91-0353 Reconstruction 0-003-003 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1192 Reconstruction 0-003-005 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1504 Reconstruction 0-003-006 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0842 Reconstruction 0-003-007 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0625 Additions and Alterations 0-003-009 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-05 2,439 01/23/08 04/02/08 FANSHAWE INC
CO-EC-06 2,630 07/14/08 08/26/08 FANSHAWE, INC. DBA ROCKLAND ELECTRIC
EC-01 3,466 07/15/08 07/29/08 Richard Parker Electrical
03-1448 Reconstruction 0-003-010 06/01/04 *CO No.* Amount Disallowed Received Approved Contractor
Roof 01 61,565 05/24/06 06/23/06 Best roofing of new Jersey
Root 02 7,028 05/24/06 06/23/06 Best Roofing
Senior High School:
91-0354 Reconstruction 0-009-007 11/08/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1193 Reconstruction 0-009-009 05/11/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1502 Reconstruction 0-009-010 05/18/95 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0843 Reconstruction 0-009-011 05/16/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0478 Additions and Alterations 0-009-012 03/22/00 *CO No.* Amount Disallowed Received Approved Contractor
1 3,500 08/07/01 01/08/02 DeRosa Tennis Contractors
1 25,280 08/07/01 01/08/02 Key Interiors
1 31,000 10/16/01 03/15/02 Pearl River Plumbing
2 55,164 08/07/01 02/11/02 Key Interiors
3 18,500 08/07/01 02/21/02 Key Interiors
4 26,700 10/16/01 03/15/02 Key Interiors
E-1 21,500 07/31/01 03/28/02 Fanshawe
E-2 13,500 10/16/01 02/21/02 Fanshawe
02-2083 Reconstruction 0-009-013 05/01/03 *CO No.* Amount Disallowed Received Approved Contractor
1 85,972 85,972 09/17/03 09/22/03 W. Harris & Sons
04-0626 Additions and Alterations 0-009-014 04/07/05 *CO No.* Amount Disallowed Received Approved Contractor
CO-EC-01 977 01/23/08 04/02/08 FANSHAWE INC
MC-01 19,674 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-02 12,841 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-03 10,132 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-06 19,380 10/29/07 01/25/08 Pearl River Plumbing,Heating & Elect
MC-09 14,667 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-10 19,674 10/29/07 01/25/08 Pearl River Plumbing, Heating & Elec
MC-17 13,536 10/29/07 01/28/08 PEARL RIVER PLUMBING HEATING
MC-18 14,037 10/29/07 01/24/08 Pearl River Plumbing, Heating & Elec
MC-19 17,436 10/29/07 01/24/08 Pearl River Plumbing, Heating & Ele