REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Wheelerville School:
04-1348 Reconstruction 0-002-003 05/27/05 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
91-0810 New Construction 5-003-002 03/13/92 NO CHANGE ORDERS ON ELECTRONIC FILE
GLOVERSVILLE CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-05-00-01
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Boulevard School:
99-0710 Reconstruction 0-004-006 04/17/00 *CO No.* Amount Disallowed Received Approved Contractor
CN-2 2,774 05/30/02 06/04/02 Adirondack Cabling
GC-4 -2,760 05/30/02 06/04/02 LG White and Sons
M-1 -3,000 05/30/02 06/04/02 V&B Mech.
05-0174 Reconstruction 0-004-007 02/07/06 *CO No.* Amount Disallowed Received Approved Contractor
01-01 -1,171 11/10/06 12/27/06 CFi Construction
01-02 15,082 03/14/07 05/09/07 CFI Construction
01-07 2,377 03/28/07 05/09/07 CFi Construction
01-08 2,291 03/28/07 05/09/07 CFI Construction
02-01 -1,488 09/26/06 10/19/06 Bunkoff General Contractors
02-05 4,900 12/08/06 01/30/07 Bunkoff General Contractors
02-06 3,801 03/14/07 05/09/07 Bunkoff General
02-09 9,804 01/23/07 03/23/07 Bunkoff General Contractors
02-12 14,635 03/14/07 05/09/07 Bunkoff General Contractors
02-13 7,555 02/23/07 03/23/07 Bunkoff General Contractors
02-14 15,836 03/14/07 05/08/07 Bunkoff General Contractors
02-22 7,961 02/23/07 03/23/07 Bunkoff General
02-23 5,313 02/23/07 03/23/07 bunkoff General
02-26 2,251 02/23/07 03/23/07 Bunkoff General
02-27 2,395 03/28/07 05/09/07 Bunkoff General
02-28 2,713 03/28/07 05/09/07 Bunkoff General
02-29 2,543 03/28/07 05/09/07 Bunkoff General
02-34 741 07/20/07 08/23/07 Bunkoff General Contractors
02-36 2,138 07/20/07 08/23/07 Bunkoff General Contractors
02-37 3,871 01/03/08 08/06/08 Bunkoff General Contractors
02-38 10,244 01/03/08 01/23/08 BUNKOFF GENERAL CONTRACTORS, INCORPO
02-40 1,929 01/03/08 08/06/08 Bunkoff General Contractors
02-41 2,026 01/03/08 08/06/08 Bunkoff General Contractors
02-43 5,783 01/03/08 08/06/08 Bunkoff General Contractors
02-44 2,543 01/03/08 08/06/08 Bunkoff General Contractors
02-46 20,123 01/03/08 08/06/08 Bunkoff General Contractors
02-47 2,379 01/03/08 08/06/08 Bunkoff General Contractors
02-48 3,391 01/03/08 08/06/08 Bunkoff General Contractors
02-49 3,316 01/03/08 08/06/08 Bunkoff General Contractors
02-50 4,265 01/03/08 08/06/08 Bunkoff General Contractors
02-52 5,960 01/03/08 08/06/08 Bunkoff General Contractors
02-53 2,740 01/03/08 08/06/08 Bunkoff General Contractors
02-55 9,990 01/03/08 08/06/08 Bunkoff General Contractors
02-56 6,357 01/03/08 01/14/08 BUNKOFF GENERAL CONTRACTORS, INCORPO
02-57 7,150 01/03/08 08/06/08 Bunkoff General Contractors
02-58 8,640 01/03/08 08/06/08 Bunkoff General Contractors
02-59 9,006 01/03/08 08/06/08 Bunkoff General Contractors
02-63 3,296 02/28/08 03/08/08 BUNKOFF GENERAL CONTRACTORS
02-66 -774 02/28/08 03/08/08 BUNKOFF GENERAL CONTRACTORS
02-67 -675 04/17/08 04/21/08 BUNKOFF GENERAL CONTRACTORS, INC.
02-68 1,492 05/08/08 08/05/08 Bunkoff General Contractors, Inc.
03-01 61,848 04/09/07 / / Merit Plumbing heating
03-03 22,207 04/09/07 / / Merit Plumbing
03-04 25,147 11/10/06 12/27/06 Merit Plumbing Heating
03-06 -1,866 03/14/07 04/06/07 Merit Plumbing Heating
03-07 3,559 03/28/07 04/04/07 Merit Plumbing Heating
03-08 3,129 06/06/07 08/01/07 Merit Plumbing Heating
03-09 3,509 06/06/07 08/07/07 Merit Plumbing Heating
03-11 784 01/03/08 02/23/08 Merit Plumbing & Heating
03-12 1,717 01/03/08 08/06/08 Merit Plumbing & Heating
03-15 3,904 04/16/08 04/21/08 MERIT PLUMBING & HEATING
03-16 -1,627 04/16/08 04/21/08 MERIT PLUMBING & HEATING
04-03 -1,426 03/14/07 / / Schenectady Hardware
04-06 3,170 03/14/07 04/06/07 Schenectady Hardware
04-08 3,231 03/14/07 04/06/07 schenectady Hardware
04-11 4,526 03/14/07 04/06/07 Schenectady hardware
04-13 16,323 03/14/07 04/06/07 Schenectady Hardware
04-16 1,849 06/05/07 08/01/07 Schenectady hardware
04-17 2,732 06/06/07 06/18/07 Schenectady hardware
04-19 3,838 01/03/08 02/23/08 Schenectady Hardware & Electric
04-20 2,775 01/03/08 / / Schenectady Hardware & Electric
04-21 5,068 01/03/08 02/23/08 Schenectady Hardware & Electric
04-24 7,597 01/03/08 02/23/08 Schenectady Hardware & Electric
04-27 1,786 02/28/08 03/07/08 SCHENECTADY HARDWARE & ELECTRIC
04-30 6,973 04/16/08 / / SCHENECTADY HARDWARE & ELECTRIC
05-02 62 03/14/07 05/09/07 John Warren
05-03 27,943 03/14/07 05/09/07 John Warren
05-05 496 03/14/07 05/09/07 John Warren
05-07 2,524 05/17/07 05/25/07 John Warren
05-08 2,833 01/03/08 02/23/08 John V. Warren
05-09 4,724 01/03/08 02/23/08 John V. Warren
05-11 3,078 01/03/08 02/23/08 John V. Warren
06-01 1,627 02/28/08 / / JOSEPH FLIHAN CO
02-2091FP Reconstruction 0-004-FP1 10/02/03 NO CHANGE ORDERS ON ELECTRONIC FILE
McNab School:
97-1810 Reconstruction 0-007-004 08/06/98 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0711 Reconstruction 0-007-005 04/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0464 Reconstruction 0-007-006 01/29/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Park Terrace Elem.:
97-1801 Reconstruction 0-009-004 08/14/98 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0712 Reconstruction 0-009-005 04/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0175 Reconstruction 0-009-007 02/07/06 *CO No.* Amount Disallowed Received Approved Contractor
01 10 488 02/14/08 03/08/08 CFI CONSTRUCTION
01-03 -1,725 03/28/07 05/09/07 CFI Construction
01-04 9,478 03/28/07 05/09/07 CFI Construction
01-05 4,079 03/28/07 05/09/07 CFI Construction
01-06 2,391 03/28/07 05/09/07 CFI Construction
01-09 2,645 06/06/07 06/18/07 CFI Construction
01-11 1,042 03/31/08 04/21/08 CFI CONSTRUCTION
02 - 45 2,118 01/03/08 / / BUNKOFF GENERAL CONTRACTORS, INCORPO
02-02 -2,290 09/26/06 10/19/06 Bunkoff General Construction
02-03 1,791 12/08/06 01/19/07 Bunkoff General Contractors
02-04 4,900 12/08/06 01/19/07 Bunkoff General Contractors
02-07 3,801 03/14/07 05/09/07 Bunkoff General
02-08 12,616 03/14/07 05/08/07 Bunkoff General
02-10 762 01/23/07 03/23/07 Bunkoff General
02-11 13,209 03/14/07 05/09/07 Bunkoff General
02-15 9,502 03/14/07 05/08/07 Bunkoff General Contractors
02-16 8,756 02/23/07 03/23/07 Bunkoff General Contractors
02-17 8,969 02/23/07 03/23/07 Bunkoff General
02-18 3,910 02/23/07 03/23/07 Bunkoff General
02-19 9,296 02/23/07 03/23/07 Bunkoff General
02-20 3,921 02/23/07 03/23/07 Bunkoff General
02-21 6,318 02/23/07 03/23/07 Bunkoff General
02-24 4,188 02/23/07 03/23/07 bunkoff General
02-25 3,377 02/23/07 03/23/07 Bunkoff General
02-30 2,893 03/28/07 05/09/07 Bunkoff General Contractors
02-31 1,474 03/28/07 05/09/07 Bunkoff General Contractors
02-32 3,082 05/17/07 05/25/07 Bunkoff General Contractors
02-33 983 05/17/07 05/25/07 Bunkoff General Contractors
02-35 5,122 07/20/07 08/23/07 Bunkoff General Contractors
02-39 3,078 01/03/08 01/23/08 BUNKOFF GENERAL CONTRACTORS, INCORPO
02-42 2,328 01/03/08 01/23/08 BUNKOFF GENERAL CONTRACTORS, INCORPO
02-51 4,114 01/03/08 01/23/08 BUNKOFF GENERAL CONTRACTOR, INCOPROR
02-54 2,782 01/03/08 01/23/08 BUNKOFF GENERAL CONTRACTORS, INCORPO
02-60 9,650 01/25/08 08/05/08 BONKOFF GENERAL CONTRACTORS
02-61 4,482 01/25/08 08/06/08 BUNKOFF GENERAL CONTRACTORS
02-62 2,440 02/28/08 03/08/08 BUNKOFF GENERAL CONTRACTORS
02-64 3,962 02/28/08 03/08/08 BUNKOFF GENERAL CONTRACTORS
02-65 4,009 02/28/08 03/08/08 BUNKOFF GENERAL CONTRACTORS
02-69 1,434 05/08/08 08/05/08 Bunkoff General Contractors, Inc.
03-02 23,077 04/09/07 / / Merit Plumbing Heating
03-05 -1,145 12/08/06 / / Merit Plumbing
03-10 2,741 06/05/07 08/01/07 Merit Plumbing Heating
03-14 1,306 04/16/08 04/21/08 MERIT PLUMBING & HEATING
04 - 22 1,909 01/03/08 / / SCHENECTADY HARDWARE & ELECTRIC
04 - 23 7,231 01/03/08 / / SCHENECTADY HARDWARE & ELECTRIC
04-01 -895 11/10/06 08/23/07 Schenectady Hardware Electric
04-02 7,674 01/23/07 01/30/07 Schenectady Hardware Electric
04-04 5,257 03/14/07 04/06/07 Schenectady hardware
04-05 10,115 03/14/07 / / Schenectay hardware
04-07 5,397 03/14/07 04/06/07 Schenectady hardware Electric
04-09 3,231 03/14/07 04/06/07 schenectady hardware
04-10 1,548 03/14/07 04/06/07 Schenectady Hardware
04-12 4,450 03/14/07 04/06/07 Schenectady Hardware
04-14 846 05/17/07 / / Schenectady Hardware electric
04-15 905 06/06/07 08/01/07 Schenectady hardware Electric
04-25 271 02/14/08 03/07/08 SCHENECTADY HARDWARE & ELECTRIC
04-26 9,512 03/31/08 04/11/08 SCHENECTADY HARDWARE & ELECTRIC
04-28 1,500 02/28/08 03/08/08 SCHENECTADY HARDWARE & ELECTIRC
04-29 4,941 04/16/08 04/21/08 SCHENECTADY HARDWARE & ELECTRIC
05 - 10 4,975 01/03/08 / / JOHN V. WARREN
05 - 12 703 01/03/08 01/14/08 JOHN V. WARREN
05-01 -2,026 11/10/06 / / John Warren
05-04 3,538 03/14/07 05/09/07 John Warren
05-06 6,158 05/17/07 05/25/07 John Warren
05-13 1,399 05/08/08 08/05/08 JOHN V. WARREN
High School:
95-1046 Reconstruction 0-010-009 05/22/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0713 Reconstruction 0-010-011 04/17/00 *CO No.* Amount Disallowed Received Approved Contractor
CN-2 2,774 05/29/02 05/29/02 Adirondack Cabling
E-1 -5,510 05/30/02 05/30/02 Justin Elec.
GC-2 10,713 06/21/01 01/08/02 LG White & Sons
GC-4 -2,760 05/29/02 05/29/02 LG White & Sons
M-1 -3,000 05/29/02 05/29/02 V&B Mech.
04-1103 Additions and Alterations 0-010-013 05/24/05 *CO No.* Amount Disallowed Received Approved Contractor
01-01 -3,889 02/02/06 08/08/06 Ritter Paratore
01-02 -3,782 02/09/06 06/07/06 Ritter and Paratore
01-03 -245,000 08/21/06 10/13/06 Ritter Paratore
01-04 -523 09/08/06 10/19/06 Ritter and Paratore
01-05 24,877 07/20/07 08/23/07 Ritter Paratore
01-06 1,980 06/06/07 06/18/07 ritter & paratore
01-09 -4,500 12/28/07 01/28/08 Ritter & Paratore
02 25 -9,018 02/14/08 03/08/08 MLB CONSTRUCTION SERVICES, INC
02 27 8,605 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 28 2,218 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 30 3,738 02/14/08 03/08/08 MLB CONSTRUCTION SERVICES, INC
02 31 2,504 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 32 2,454 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 33 1,316 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 34 1,164 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02 35 4,166 02/14/08 03/08/08 MLB CONSTRUCTION SERVICES, INC
02 37 3,011 02/17/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02-01 -1,254 02/02/06 05/25/06 MLB Construction Services
02-02 25,000 02/15/06 06/19/06 MLB Construction Service
02-03 -8,200 03/07/06 06/07/06 mbl construction services
02-04 -530 08/21/06 10/13/06 MLB Construction
02-05 -22,600 11/10/06 / / MLB Construction
02-07 -420 09/26/06 10/19/06 MLB Construction
02-08 -5,000 11/10/06 01/09/07 MLB Construction
02-09 16,790 03/15/07 05/09/07 MLB Constructions
02-10 -7,145 12/28/07 01/07/08 MLB Construction
02-11 1,418 12/28/07 01/07/08 MLB Construction
02-12 3,682 12/28/07 01/07/08 MLB Construction
02-14 7,547 02/28/07 01/07/08 MLB Construction
02-15 3,911 12/28/07 01/07/08 MLB Construction
02-16 -1,000 12/28/07 04/03/08 MLB Construction
02-17 8,707 12/28/07 01/07/08 MLB Construction
02-18 9,370 12/28/07 01/07/08 MLB Construction
02-20 1,513 12/28/07 01/07/08 MLB Construction Services
02-21 4,087 12/28/07 01/07/08 MLB Construction Services
02-22 4,200 12/28/07 01/07/08 MLB Construction Services
02-23 4,988 12/28/07 01/07/08 MLB Construction
02-24 4,663 12/28/07 01/07/08 MLB Construction Services
02-26 4,681 02/14/08 03/08/08 MLB CONSTRUCTION SERVICES, INC
02-36 2,197 02/14/08 03/08/08 MLB CONSTRUCTION SERVICES, INC
02-38 1,561 03/31/08 04/07/08 MLB CONSTRUCTION SERVICES, INC.
02-40 1,941 03/31/08 04/07/08 MLB CONSTRUCTION SERVICES, INC.
02-41 3,651 03/31/08 04/07/08 MLB CONSTRUCTION SERVICES, INC.
02-42 3,190 03/31/08 04/07/08 MLB CONSTRUCTION CERVICES, INC.
02-43 1,289 03/31/08 04/07/08 MLB CONSTRUCTION SERVICES, INC.
02-45 1,000 04/17/08 04/21/08 MLB CONSTRUCTION SERVICES, INC.
02-46 -130 04/17/08 04/21/08 MLB CONSTRUCTION SERVICES, INC.
03-01 102,000 02/09/06 05/23/06 Campito Plumbing Heating
03-03 131,896 04/09/07 07/06/07 Campito Plumbing Heating
03-04 -6,751 01/23/07 01/30/07 campite plumbing & heating
03-05 1,478 05/17/07 08/07/07 Campito Plumbing Heating
03-06 2,238 12/28/07 04/03/08 Campito Plumbing & Heating
03-07 4,590 12/28/07 04/03/08 Campito Plumbing & Heating
03-08 1,296 12/28/07 01/28/08 Campito Plumbing
03-09 4,737 12/28/07 01/28/08 Campito Plumbing & Heating
03-10 2,803 12/28/07 01/28/08 Campito Plumbing & Heating
03-11 -16,284 3 04/17/08 / / CAMPITO PLUMBING & HEATING, INC.
03-12 -2,944 05/08/08 / / CAMPITO PLUMBING & HEATING, INC.
04 24 2,364 02/14/08 04/04/08 SCHENECTADY HARDWARE & ELECTRIC
04-01 -10,800 01/04/06 06/30/06 Schenectady hardware Electric
04-02 1,800 02/09/06 05/23/06 Schenectady hardware Electric
04-04 -2,089 08/21/06 01/12/07 Schenectady hardware
04-05 854 09/08/06 01/09/07 Schenectady Hardware
04-06 3,633 05/17/07 08/07/07 Schenectady hardware Electric
04-07 4,443 05/17/07 / / Schenectady Hardware Electric
04-08 4,578 05/17/07 08/07/07 Schenectady hardware Electric
04-09 1,975 05/17/07 08/07/07 Schenectady Hardware Electric
04-10 1,083 05/17/07 08/07/07 Schenectady Hardware Electric
04-11 26,434 07/20/07 08/23/07 Schenectady Hardware Electric
04-12 4,272 06/06/07 10/23/07 Schenectady Hardware Electric
04-13 7,958 06/06/07 10/23/07 Schenectady Hardware
04-14 2,424 12/28/07 04/03/08 Schenectady Hardware & Electric
04-15 3,937 12/28/07 04/03/08 Schenectady Hardware & Electric
04-16 5,265 12/28/07 04/03/08 Schenectady Hardware & Electric
04-17 2,020 12/28/07 04/03/08 Schenectady Hardware & Electric
04-18 7,316 12/28/07 04/03/08 Schenectady Hardware & Electric
04-19 6,008 12/28/07 04/03/08 Schenectady Hardware & Electric
04-22 3,915 12/28/07 04/03/08 Schenectady Hardware & Electric
04-23 3,385 12/28/07 04/03/08 Schenectady Hardware & Electric
04-26 3,160 03/31/08 08/05/08 SCHENECTADY HARDWARE & ELECTRIC
04-28 3,616 04/17/08 08/05/08 SCHENECTADY HARDWARE & ELECTRIC
04-29 4,980 05/08/08 06/12/08 SCHENECTADY HARDWARE & ELECTRIC
05-02 1,317 01/23/07 03/23/07 Lenz hardware
05-03 3,320 03/15/07 05/09/07 Lenz Hardware
05-04 986 03/28/07 05/09/07 Lenz Hardware
05-05 519 03/28/07 05/09/07 Lenz hardware
05-06 1,035 05/17/07 05/25/07 Lenz Hardware
05-07 5,029 05/17/07 05/25/07 Lenz Hadware
05-09 9,798 07/20/07 / / Lenz Hardware
05-10 4,346 07/20/07 08/23/07 Lenz Hardware
05-11 1,955 12/28/07 02/23/08 Lenz Hardware
05-12 2,606 12/28/07 01/28/08 Lenz Hardware
05-13 2,196 01/25/08 04/02/08 LENZ HARDWARE
05-14 1,242 01/25/08 04/02/08 LENZ HARDWARE
06-02 -235 03/15/07 05/09/07 Kittredge Equipment
06-03 286 03/15/07 05/09/07 Kittredge Equipment
06-04 294 03/15/07 05/09/07 Kittredge Equipment
06-05 -936 02/28/08 04/15/08 KITTREDGE EQUIPMENT
06-06 -480 02/28/08 04/15/08 KITTREDGE EQUIPMENT
04-0896 Reconstruction 0-010-014 03/24/05 *CO No.* Amount Disallowed Received Approved Contractor
01-01 -7,000 02/02/06 06/30/06 Midlantic Environmental
02-01 -3,613 02/09/06 05/25/06 Yukon Insulation
02-2090FP Reconstruction 0-010-FP1 10/02/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Meco Elementary School:
96-0248 Reconstruction 0-014-004 08/30/96 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0714 Reconstruction 0-014-005 04/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0465 Reconstruction 0-014-006 01/29/08 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0672 Reconstruction 0-014-007 02/08/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Kingsborough Elementary:
99-0715 Reconstruction 0-015-005 04/17/00 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0728 Reconstruction 0-015-007 04/19/01 *CO No.* Amount Disallowed Received Approved Contractor
E-2 1,687 01/10/02 03/22/02 Justin Elec.
GC-2 1,302 12/11/01 03/21/02 Wright & Morissey
GC-3 1,832 02/22/02 03/29/02 Wright & Morissey
M-2 1,902 12/11/01 03/21/02 Adirondack Mech.
07-0466 Reconstruction 0-015-008 01/29/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Middle School:
95-0700 New Construction 0-019-001 05/07/96 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0623 Reconstruction 0-019-002 01/10/01 *CO No.* Amount Disallowed Received Approved Contractor
E-1 997 04/25/01 01/15/02 T. McCarthy Elec. Const.
E-2 1,674 06/22/01 02/06/02 T. McCarthy Elec. Const.
H-1 300 06/22/01 02/06/02 Steven Miller
03-0925 Reconstruction 0-019-003 06/09/04 *CO No.* Amount Disallowed Received Approved Contractor
01-01 -781 08/26/05 09/02/05 BAST HATIFIELD INC.
01-02 -10,634 09/21/05 10/03/05 Bast hastfield
01-03 -400 08/26/05 09/02/05 BAST HATFIELD INC.
01-04 -10,022 02/02/06 06/26/06 Bast hatfield
02-01 -359 06/01/05 06/29/05 J and K Plumbing
02-02 -4,275 06/01/05 10/17/06 J and K Plumbing Heating Co
02-03 1,805 08/26/05 10/17/06 J & K PLUMBING & HEATING CO., INC
03-01 2,758 06/01/05 07/21/05 Brownell Electical Corp
03-02 1,803 06/01/05 10/17/06 Brownell Electrical
03-03 765 08/26/05 09/02/05 BROWNELL ELECTICAL CORP.
04-01 -3,101 08/26/05 09/02/05 LENZ HARDWARE, INC.
04-1104 Reconstruction 0-019-005 05/24/05 *CO No.* Amount Disallowed Received Approved Contractor
01-07 16,371 06/05/07 06/18/07 Ritter Paratore
01-08 183,563 06/06/07 06/18/07 Ritter Paratore
02 29 3,569 02/14/08 03/31/08 MLB CONSTRUCTION SERVICES, INC
02-06 -43,179 09/08/06 10/19/06 MLB Construction Services
02-19 -433 12/28/07 01/07/08 MLB Construction Services
02-39 5,673 03/31/08 04/02/08 MLB CONSTRUCTION SERVICES, INC.
02-44 6,744 03/31/08 04/18/08 MLB CONSTRUCTION SERVICES, INC.
03-02 -37,805 09/08/06 01/09/07 Campito Plumbing heating
04-03 -9,839 02/09/06 05/01/07 Schenectady Hardware Electric
04-25 4,959 02/14/08 03/07/08 SCHENECTADY HARDWARE & ELECTRIC
04-27 2,300 04/17/08 04/21/08 SCHENECTADY HARDWARE & ELECTRIC
05-08 5,373 07/20/07 08/23/07 Lenz Hardware
06-01 -104 11/10/06 12/27/06 Kittredge Equipment
07-01 3,600 11/10/06 08/23/07 John Warren
07-02 3,897 03/15/07 05/09/07 John Warren
07-03 1,390 12/28/07 01/07/08 John V. Warren
07-04 1,000 03/31/08 04/01/08 JOHN V. WARREN, INC.
02-2089FP Reconstruction 0-019-FP1 10/02/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Storage/Utility Building:
03-1116 New Construction 2-026-001 06/09/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage (lease):
01-0727 Reconstruction 5-024-L01 02/20/02 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0045 Reconstruction 5-024-L02 07/01/02 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0046 Reconstruction 5-024-L03 07/01/03 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0047 Reconstruction 5-024-L04 07/13/04 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Maintenance Facility:
04-0197 New Construction 5-025-001 10/21/04 *CO No.* Amount Disallowed Received Approved Contractor
01-01 1,721 09/21/05 10/03/05 CFI Construction
01-02 4,500 09/21/05 10/03/05 CFi Construction
01-03 6,887 09/21/05 10/03/05 CFI Construction
01-04 6,148 09/21/05 10/03/05 CFI Construction
01-05 1,164 09/21/05 10/03/05 CFI Construction
01-08 47,250 01/04/06 06/30/06 CFi Construction
01-09 4,667 02/09/06 03/26/07 CFI Construction
01-10 8,951 03/20/06 06/23/06 CFi Construction
01-11 36,000 03/28/06 06/07/06 CFI Construction
01-12 2,155 03/28/06 06/07/06 CFI Construction
01-13 1,203 11/10/06 01/09/07 CFI Construction
01-14 71,080 11/10/06 01/09/07 CFi Construction
01-15 11,005 11/10/06 01/09/07 CFI Construction
01-16 -2,325 09/08/06 10/30/06 CFI Construction
01-17 8,823 09/08/06 10/30/06 CFI Construction
01-18 2,092 09/08/06 10/30/06 CFI Construction
02-01 -24,000 01/04/06 06/26/06 BDC Construction
02-02 -114 01/04/06 06/30/06 BDC Construction
02-03 -3,178 02/09/06 03/26/07 BDC Construction
02-04 -811 02/15/06 07/21/06 BDC Construction
02-05 1,371 04/07/06 06/07/06 BDC Construction
02-06 1,784 03/28/06 06/07/06 BDC Construction
02-07 16,471 11/10/06 01/09/07 BDC Construction
02-08 2,378 09/08/06 10/30/06 BDC Construction
02-09 2,508 09/08/06 01/09/07 BDC Construction
02-10 -3,000 09/08/06 10/30/06 BDC Construction
02-11 1,906 09/08/06 10/30/06 BDC Construction
02-12 1,132 06/06/07 06/20/07 BDC Construction
03-01 1,675 09/08/06 01/09/07 J and K Plumbing Heating
03-02 9,689 04/17/07 08/07/07 J and K Plumbing Heating Co
03-04 1,725 11/10/06 / / brownell electirc
04-01 3,182 12/08/06 01/09/07 Brownell Electric
04-02 839 11/10/06 01/09/07 Brownell Electric
04-03 1,615 11/10/06 01/09/07 Brownell Electric
04-04 1,300 09/08/06 01/09/07 Brownell Electric
04-05 11,453 09/08/06 01/09/07 Brownell Electric
04-07 1,335 12/08/06 03/26/07 Brownell Electric
04-08 4,801 12/08/06 01/09/07 Brownell Electric
04-09 2,141 12/08/06 01/09/07 Brownell Electric
04-10 -1,132 06/06/07 10/23/07 Brownell Electric
04-11 1,272 06/06/07 10/23/07 Brownell Electric
05-01 3,092 11/10/06 01/09/07 John warren
05-02 1,363 08/31/06 12/19/06 John V. Warren
08-01 9,975 09/08/06 10/30/06 Total Tool
08-02 5,660 09/26/06 10/19/06 Total Tool
09-01 607 09/08/06 10/30/06 Total Tool
09-02 9,975 09/08/06 10/30/06 Total Tool
1-06 24,775 09/21/05 10/03/05 CRI Construction
1-07 15,091 09/21/05 10/03/05 CFI Construction
Transp. Storage & Toilet Fac.:
00-0409 Reconstruction 7-005-001 11/10/00 NO CHANGE ORDERS ON ELECTRONIC FILE
Pumphouse-Middle School:
95-1114 New Construction 7-020-001 05/07/96 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1124 Additions and Alterations 7-020-002 07/27/07 NO CHANGE ORDERS ON ELECTRONIC FILE
New Press Box @ High School:
04-1106 New Construction 7-027-001 05/24/05 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box @ Park Terrace:
05-0176 New Construction 7-028-001 02/07/06 NO CHANGE ORDERS ON ELECTRONIC FILE
JOHNSTOWN CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-06-00-01
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Warren Street School:
95-1437 Reconstruction 0-003-003 07/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1357 Additions and Alterations 0-003-004 06/25/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0837 Reconstruction 0-003-005 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
E-008 1,094 05/29/08 / / JUSTIN ELECTRICAL, INC.
02-1812FP Reconstruction 0-003-FP1 05/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Knox Junior High School:
91-0573 Reconstruction 0-006-001 01/24/92 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1438 Reconstruction 0-006-002 07/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1358 Additions and Alterations 0-006-003 06/25/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0838 Reconstruction 0-006-004 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
E-006 463 05/29/08 / / JUSTIN ELECTRICAL, INC.
E-011 1,101 07/02/08 / / JUSTIN ELECTRICAL, INC.
E-013 681 08/08/08 / / JUSTIN ELECTRICAL, INC.
GC-007 1,103 06/18/08 08/26/08 Bast Hatfield
H-002 42,968 07/16/08 / / DURR MECHANICAL CONSTRUCTION, INC.
02-1811FP Reconstruction 0-006-FP1 05/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Pleasant Ave. School:
93-1439 Reconstruction 0-007-006 06/21/94 NO CHANGE ORDERS ON ELECTRONIC FILE
94-1157 Additions and Alterations 0-007-007 05/15/95 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0839 Reconstruction 0-007-009 11/02/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Senior High School:
92-0228 Reconstruction 0-009-001 09/28/92 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1697 Reconstruction 0-009-003 08/05/94 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1439 Reconstruction 0-009-004 07/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1359 Additions and Alterations 0-009-005 06/25/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0840 Additions and Alterations 0-009-006 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
E-001 734,000 05/29/08 / / JUSTIN ELECTRICAL, INC.
E-002 0 05/29/08 / / JUSTIN ELECTRICAL, INC.
E-007 1,963 05/29/08 / / JUSTIN ELECTRICAL, INC.
E-009 3,044 06/25/08 / / Justin Electrical
E-010 5,671 07/02/08 / / JUSTIN ELECTRICAL, INC.
E-010 5,671 07/02/08 / / JUSTIN ELECTRICAL, INC.
E-012 2,168 08/08/08 / / JUSTIN ELECTRICAL, INC.
GC-001 -20,000 05/29/08 08/04/08 BAST HATFIELD, INC.
GC-002 21,651 05/29/08 08/04/08 BAST HATFIELD, INC.
GC-003 18,714 05/29/08 08/04/08 BAST HATFIELD, INC.
GC-005 4,561 05/29/08 08/04/08 BAST HATFIELD, INC.
GC-006 6,368 06/18/08 08/26/08 Bast Hatfield
GC-008 -4,917 07/21/08 / / BAST HATFIELD, INC.
GC-010 9,440 07/21/08 / / BAST HATFIELD, INC.
GC-011 66,958 07/21/08 / / BAST HATFIELD, INC.
GC-012 2,903 08/08/08 / / BAST HATFIELD, INC.
GC-013 2,875 08/08/08 / / BAST HATFIELD, INC.
GC-014 1,984 08/15/08 / / BAST HATFIELD, INC.
P-001 8,991 05/29/08 / / DURR MECH CONSTR., INC.
P-003 4,000 05/29/08 / / DURR MECH. CONSTR. INC.
P-004 -3,127 06/25/08 / / Durr Mech. Constr. INc.
P-005 9,360 08/11/08 / / DURR MECHANICAL CONSTRUCTION INC.
P-006 1,202 08/11/08 / / DURR MECHANICAL CONSTRUCTION INC.
02-1810FP Reconstruction 0-009-FP1 05/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Glebe Street Elem.:
95-1440 Reconstruction 0-010-003 07/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1360 Additions and Alterations 0-010-004 06/25/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0841 Reconstruction 0-010-005 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
E-004 403 05/29/08 / / JUSTIN ELECTRICAL, INC.
02-1809FP Reconstruction 0-010-FP1 05/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Jansen Avenue Elem. School:
95-1441 Reconstruction 0-011-001 07/19/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1361 Additions and Alterations 0-011-002 06/25/98 NO CHANGE ORDERS ON ELECTRONIC FILE
05-0842 Reconstruction 0-011-003 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
E-005 402 05/29/08 / / JUSTIN ELECTRICAL, INC.
H-004 3,311 08/15/08 / / DURR MECH. CONSTRUCTION INC.
02-1808FP Reconstruction 0-011-FP1 05/28/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Warehouse ABCD-Transportation Fac.:
00-0647 Reconstruction 5-033-L01 01/19/01 NO CHANGE ORDERS ON ELECTRONIC FILE
06-1076 Reconstruction 5-033-L02 03/12/07 NO CHANGE ORDERS ON ELECTRONIC FILE
GJSD Transportation/Maintenance:
05-1292 Reconstruction 5-038-L01 07/31/06 NO CHANGE ORDERS ON ELECTRONIC FILE
Press Box:
97-0337 New Construction 7-032-001 10/29/97 NO CHANGE ORDERS ON ELECTRONIC FILE
Field House Toilets:
05-0843 New Construction 7-039-001 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
P-002 2,474 05/29/08 08/26/08 DURR MECHANCIAL CONSTRUCTION, INC.
Field House-Concessions:
05-0844 New Construction 7-040-001 11/02/06 *CO No.* Amount Disallowed Received Approved Contractor
GC-004 1,225 05/29/08 08/04/08 BAST HATFIELD, INC.
GC-009 51 07/21/08 08/26/08 BAST HATFIELD, INC.
MAYFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-08-01-04
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Jr/Sr High School:
98-1528 Additions and Alterations 0-001-007 07/02/99 *CO No.* Amount Disallowed Received Approved Contractor
EC-6 11,509 05/15/03 05/20/03 Frank Brandl
EC-7 9,908 05/15/03 05/20/03 Frank Brandl
GC-16 8,408 03/05/02 04/29/02 MLB Industries
GC-20 11,915 08/02/02 10/28/02 MLB Industries
GC-21 14,497 05/15/03 05/20/03 MLB Industries
MC-2 3,696 05/15/03 05/20/03 Crisafulli Bros.
PC-5 2,805 06/03/02 06/17/02 DiGesare Mech.
PC=4 4,430 03/19/02 04/29/02 DiGesare Mech.
PS-1 -800 03/01/02 04/29/02 Alarm and Suppression
TS-1 -2,000 01/29/02 03/22/02 Brown Sound Equip.
Tel-2 5,330 04/17/03 05/06/03 Grace Com Telcommunications
00-0508 Reconstruction 0-001-009 01/13/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-3 9,855 08/02/02 08/07/02 FPI Elec.
GC-7 -533 03/04/03 03/05/03 Bast Hatfield
MC-1 -2,911 07/29/02 08/16/02 V&B Gen. Mech.
PC-1 2,690 06/03/02 06/11/02 DiGesare Mech.
SW-4 58,000 02/14/02 03/21/02 Delaney Const.
00-0511 Reconstruction 0-001-010 01/13/01 *CO No.* Amount Disallowed Received Approved Contractor
GC-5 55,633 03/21/02 05/06/02 Bast Hatfield
SW-1 53,136 08/24/01 01/08/02 Delaney Const.
SW-5 8,755 02/19/02 03/29/02 Delaney Const.
SW-6 6,724 03/05/02 05/22/02 Delaney Const.
SW-7 93,690 03/21/02 05/06/02 Delaney Const.
SW-8 638 03/21/02 05/06/02 Delaney Const.
00-0509 Reconstruction 0-001-012 01/13/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-2 6,803 07/29/02 08/16/02 FPI Elec.
GC-2 -11,355 02/11/02 03/22/02 Bast Hatfield
GC-3 8,403 02/11/02 03/22/02 Bast Hatfield
GC-4 29,302 02/26/02 05/22/02 Bast Hatfield
03-1565 Reconstruction 0-001-014 05/25/04 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1363FP Reconstruction 0-001-FP1 06/02/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1378SC Visual Structural Inspection 0-001-SC1 01/16/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Elementary School:
97-1252 Reconstruction 0-002-005 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1527 Additions and Alterations 0-002-006 07/02/99 *CO No.* Amount Disallowed Received Approved Contractor
EC-3 13,499 08/24/01 01/08/02 Frank Brandl
EC-4 14,416 09/04/01 01/08/02 Frank Brandl
EC-5 10,082 05/10/02 05/22/02 Frank Brandl
GC-12 7,472 12/27/01 02/28/02 MLB Industries
GC-13 10,330 01/17/02 03/22/02 MLB Industries
GC-14 9,788 02/11/02 03/18/02 MLB Industries
GC-15 6,520 02/26/02 04/29/02 MLB Industries
GC-17 14,332 07/18/02 07/23/02 MLB Industries
GC-18 11,458 07/29/02 10/25/02 MLB Industries
GC-19 10,125 07/29/02 10/25/02 MLB Industries
GC-22 -57,796 08/30/02 10/21/02 MLB Industries
MC-2 3,696 08/30/02 10/21/02 Crisafulli Bros.
RC-3 4,123 02/11/02 03/18/02 WeatherGuard Roofing
SC-2 10,143 02/19/02 04/29/02 Miscellaneous Iron Fabricators
TC-1 -2,000 02/26/02 04/29/02 Syracuse Scenery & Stage Lighting
00-0512 Reconstruction 0-002-007 01/13/01 *CO No.* Amount Disallowed Received Approved Contractor
EC-2 6,862 07/29/02 08/16/02 FPI Elec.
EC-4 11,273 09/03/02 10/29/02 FPI Elec.
EC-5 10,967 09/03/02 10/29/02 FPI Elec.
EC-6 5,793 04/17/03 05/05/03 FPI Elec.
EC-7 -1,648 09/22/03 12/17/03 FPI Elec.
GC-1 -3,944 12/10/01 05/28/02 Bast Hatfield
GC-6 -5,150 09/30/02 11/05/02 Bast Hatfield
MC-1 -575 07/29/02 08/16/02 V&B Gen. Mech.
SW-2 44,836 09/14/01 05/28/02 Delaney Const.
01-0028 Additions and Alterations 0-002-008 01/25/02 *CO No.* Amount Disallowed Received Approved Contractor
EC-1 25,774 07/02/03 07/11/03 FPI Elec.
EC-2 -2,666 10/08/03 10/14/03 FPI Elec.
GC-1 7,883 03/09/05 03/11/05 LG White and Sons Inc
MC-1 -4,310 10/08/03 10/14/03 Lenz Hardware
PC-1 -1,443 01/30/03 02/03/03 Lenz Hardware
02-0138 Reconstruction 0-002-009 08/22/02 NO CHANGE ORDERS ON ELECTRONIC FILE
03-1564 Reconstruction 0-002-010 05/25/04 *CO No.* Amount Disallowed Received Approved Contractor
RC-1 11,678 06/04/07 06/05/07 David Jablonski Construction
03-1364FP Reconstruction 0-002-FP1 06/02/04 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0018SC Visual Structural Inspection 0-002-SC1 07/09/07 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1379SC Visual Structural Inspection 0-002-SC2 01/16/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
97-1253 Reconstruction 5-003-003 05/05/98 NO CHANGE ORDERS ON ELECTRONIC FILE
00-0513 Reconstruction 5-003-004 01/13/01 *CO No.* Amount Disallowed Received Approved Contractor
SW-3 7,734 01/22/02 05/13/02 Delaney Const.
New Bus Garage:
99-1455 New Construction 5-007-001 06/29/00 *CO No.* Amount Disallowed Received Approved Contractor
EC-2 -2,007 07/29/02 08/16/02 FPI Elec.
GC-1 3,030 12/10/01 05/28/02 Bast Hatfield
GC-2 3,277 02/11/02 03/22/02 Bast Hatfield
MC-1 -1,745 07/29/02 08/16/02 V&B Gen. Mech.
NEW CONCESSION STAND:
97-1058 New Construction 7-006-001 04/10/98 NO CHANGE ORDERS ON ELECTRONIC FILE
House Purchase:
00-0510 New Construction 7-008-001 01/13/01 NO CHANGE ORDERS ON ELECTRONIC FILE
NORTHVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-09-01-04
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Northville Central School:
92-1281 Reconstruction 0-001-004 06/16/93 NO CHANGE ORDERS ON ELECTRONIC FILE
97-0115 Additions and Alterations 0-001-005 08/12/97 NO CHANGE ORDERS ON ELECTRONIC FILE
96-1319 Reconstruction 0-001-006 05/08/97 NO CHANGE ORDERS ON ELECTRONIC FILE
04-0042 Reconstruction 0-001-009 09/29/06 NO CHANGE ORDERS ON ELECTRONIC FILE
02-2398FP Reconstruction 0-001-FP1 08/25/03 NO CHANGE ORDERS ON ELECTRONIC FILE
07-1618SC Visual Structural Inspection 0-001-SC1 02/15/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
95-0286 Reconstruction 5-004-001 11/09/95 NO CHANGE ORDERS ON ELECTRONIC FILE
08-0003 Reconstruction 5-004-003 08/11/08 NO CHANGE ORDERS ON ELECTRONIC FILE
School District Public Library:
97-0080 Additions and Alterations 6-009-003 09/10/97 NO CHANGE ORDERS ON ELECTRONIC FILE
OPPENHEIM EPHRATAH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-10-01-04
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
Main Bldg:
95-0486 Additions and Alterations 0-001-001 02/02/96 NO CHANGE ORDERS ON ELECTRONIC FILE
93-1366 Reconstruction 0-001-003 06/10/94 NO CHANGE ORDERS ON ELECTRONIC FILE
99-0420 Reconstruction 0-001-004 11/16/99 NO CHANGE ORDERS ON ELECTRONIC FILE
01-0666 Reconstruction 0-001-005 02/19/02 *CO No.* Amount Disallowed Received Approved Contractor
0 / / / /
0 / / / /
0 / / / /
0 / / / /
E-001 0 10,009 09/30/03 10/03/03 Justin Electrical
E-10 10,009 07/16/04 07/21/04 Justin Electrical
E-11 5,569 11/15/04 11/23/04 Justin Electrical
E-12 1,426 11/15/04 11/23/04 Justin Electrical
E-4 0 12/10/03 12/24/03 Justin Electrical
E-6 3,730 03/17/04 04/27/04 Justin Electrical
E-7 0 03/26/04 04/28/04 Justin Electrical
E-8 6,718 06/25/04 07/15/04 Justin Electrical
E2 0 12/10/03 12/24/03 Justin Electrical
E3 0 12/10/03 12/24/03 Justin Electrical
G-1 0 03/26/04 04/12/04 Grates Building Ent.
G-3 0 03/26/04 04/12/04 Grates Building Ent.
G-4 0 03/26/04 04/12/04 Grates Building Ent.
G-5 0 03/26/04 04/12/04 Grates Building Ent.
G-6 7,620 10/15/04 10/25/04 Grates Building Ent.
G-7 0 10/15/04 10/25/04 Grates Building Ent.
H-1 0 01/23/04 02/02/04 HJ Brandeles
H-2 0 02/24/04 04/23/04 HJ Brandeles
H-3 0 03/17/04 04/27/04 HJ Brandeles
H-5 0 06/25/04 07/15/04 HJ Brandeles
H-6 0 07/16/04 07/21/04 HJ Brandeles
H-7 -6,475 09/28/04 10/25/04 HJ Brandeles
L-13 -24,800 02/04/05 06/29/05 Leitz Enterprises
L-3 0 01/23/04 02/18/04 Leitz Enterprises
L-4 11,587 01/23/04 03/17/04 Leitz Enterprises
L-6 21,525 21,525 02/24/04 03/17/04 Leitz Enterprises
L-7 9,609 08/18/04 09/17/04 Leitz Enterprises
L-8 5,543 08/18/04 09/17/04 Leitz Enterprises
L10 24,800 09/02/04 / / Leitz Enterprises
L11 3,575 02/04/05 06/29/05 Leitz Enterprises Inc
L12 -1,000 02/04/05 06/29/05 Leitz Enterprises
L9 4,696 09/02/04 / / Leitz Enterprises
P-1 0 01/23/04 02/02/04 Superior Plumbing
P-2 0 03/17/04 04/27/04 Superior Plumbing
P-3 -2,362 06/18/04 07/09/04 Superior Plumbing
P-4 -208 03/23/05 06/29/05 Superior Plumbing Heating
R-001 0 07/15/03 07/23/03 EV Roofing
R-002 0 08/11/03 09/05/03 EV Roofing
R-3 0 12/30/03 01/09/04 EV Roofing
R-4 -23,888 08/18/04 09/17/04 EV Roofing
07-0708 Additions and Alterations 0-001-006 04/22/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
01-0667 Additions and Alterations 5-005-002 10/29/02 *CO No.* Amount Disallowed Received Approved Contractor
E-5 0 01/23/04 02/02/04 Justin Electrical
E-9 254 06/25/04 07/15/04 Justin Electrical
G-2 0 03/26/04 04/12/04 Grates Building Ent.
H-4 0 03/17/04 04/27/04 HJ Brandeles
L-001 0 07/10/03 07/23/03 Leitz Enterprises
L-002 0 07/24/03 08/04/03 Leitz Enterprises
L-5 16,422 01/23/04 02/18/04 Leitz Enterprises
07-0709 Additions and Alterations 5-005-003 04/22/08 NO CHANGE ORDERS ON ELECTRONIC FILE
BROADALBIN-PERTH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 17-11-02-04
last updated on 08/27/08
REVIEW BUILDING NAME/ BLDG./ SED C. O. C.O. Disallowed C. O. C. O.
No. PROJECT SCOPE PROJ. NO. APPROVAL Number Amount Amount Received Approved Contractor
__________________________________________________________________________________________________________________________________________
ES/HS Broadalbin:
90-0664 Additions and Alterations 0-001-008 01/10/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0071 Reconstruction 0-001-009 07/25/91 NO CHANGE ORDERS ON ELECTRONIC FILE
91-0312 Reconstruction 0-001-010 10/04/91 *CO No.* Amount Disallowed Received Approved Contractor
EL-1 -837 02/28/02 05/22/02 Dunham Electric, Inc
GC-3 10,286 01/01/02 03/27/02 Beka Construction
MECH-2 -3 03/01/02 05/22/02 Crisafulli Brothers Plumbing
93-0909 Additions and Alterations 0-001-011 05/03/94 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1047 Reconstruction 0-001-012 05/17/93 NO CHANGE ORDERS ON ELECTRONIC FILE
95-1047 Reconstruction 0-001-013 04/05/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1151 Reconstruction 0-001-014 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1380 Reconstruction 0-001-015 07/26/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0406 Additions and Alterations 0-001-016 05/03/04 *CO No.* Amount Disallowed Received Approved Contractor
001 5,364 01/19/05 05/11/05 Excel Insilation
001 13,386 01/19/05 05/11/05 Murnane Building Co
001 13,704 11/17/05 / / Merit Plumbing Heating
001 4,366 02/08/06 05/24/06 Universal Custom Millwork
001 12,908 04/20/06 06/30/06 Kasselman Electric
001 6,151 04/20/06 07/05/06 Piccirilli slavik Vincent
001 820 05/11/07 05/14/07 Sports Builders
001-035 8,318 08/13/07 12/27/07 MURNANE BUILDING CO.
001-037 2,224 08/13/07 12/27/07 MURNANE BUILDING CO.
001-038 7,997 08/13/07 12/27/07 MURNANE BUILDING CO.
002 6,108 01/19/05 05/11/05 Murnane Building Co
002 3,618 04/20/06 06/23/06 universal Custom Millwork
002 20,686 06/29/06 08/24/06 Kasselman Electric
002 -2,875 09/08/06 11/03/06 Saratoga Rest Equipment
002 -18,740 12/01/06 01/09/07 EXcel Insulation
003 -1,163 03/05/07 01/23/08 Weather Guard Roofing
004 5,166 01/19/05 05/11/05 Murnane Building Co
005 3,620 04/25/05 06/14/05 Murnane Building
006 17,818 07/11/05 07/25/05 Murnane building
006 34,079 03/05/07 03/13/07 Kasselman Electric
007 14,324 07/11/05 07/25/05 Murnane building
008 2,405 07/11/05 07/25/05 Murnane building
008 9,962 03/09/07 04/25/07 Kasselman electric
009-009 9,409 03/09/07 04/25/07 Kasselman Electric
010 5,212 07/11/05 07/25/05 Murnane Building
010 4,792 05/11/07 07/27/07 Kasselman Electric
011 -7,395 07/11/05 07/25/05 Murnane Building
011 9,974 05/11/07 07/27/07 Kasselman Electric
012 5,974 07/11/05 07/25/05 Murnane Building
013 3,914 11/17/05 03/02/06 Murnane Building
014 3,491 11/17/05 02/15/06 Murnane Building
015 5,642 11/17/05 02/15/06 Murnane Building
016 9,147 02/08/06 08/08/06 Murnane Building
017 4,549 02/08/06 08/08/06 Murnane Building
018 7,837 02/08/06 08/08/06 Murnane Building
019 9,166 09/08/06 11/03/06 Murnane Building
020 7,499 09/08/06 11/03/06 Murnane Building
021 9,529 09/08/06 11/03/06 Murnane building
022 6,279 09/08/06 11/03/06 Murnane Building
023 11,596 12/01/06 01/09/07 Murnane Building
025 15,182 12/01/06 01/09/07 Murnane Building
026 9,765 12/01/06 01/09/07 Murnane Building
027 7,463 12/01/06 01/09/07 Murnane Building
028 6,303 12/01/06 01/09/07 Murnane Building
030 8,278 03/05/07 03/23/07 Murnane Building
031 9,038 03/05/07 03/23/07 Murnane Building
032 1,044 03/05/07 03/23/07 Murnane Building
033 472 05/11/07 05/14/07 Murnane Building
07-0769 Reconstruction 0-001-017 06/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
Grade School:
92-1069 Reconstruction 0-002-005 06/02/93 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0438 Reconstruction 0-002-006 12/08/94 NO CHANGE ORDERS ON ELECTRONIC FILE
95-0656 Reconstruction 0-002-007 04/30/96 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1152 Reconstruction 0-002-008 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0407 Additions and Alterations 0-002-009 05/03/04 *CO No.* Amount Disallowed Received Approved Contractor
001 -63,980 09/08/06 10/19/06 saratoga Rest
001-036 9,013 08/13/07 12/27/07 MURNANE BUILDING CO.
002 -32,495 09/08/06 10/19/06 Weather Guard Roofing
003 -60,986 09/08/06 10/19/06 Universal Custom Millwork
003 -127,135 12/01/06 12/27/06 Excel Insulation
003 -225,041 12/01/06 / / Kasselman Electric
003-002 -99,673 08/13/07 10/28/07 PICCIRILLI SLAVIN & VINCENT
024 -989,475 12/01/06 01/09/07 Murnane Building
Main Building Perth:
91-0311 Reconstruction 0-003-004 10/04/91 NO CHANGE ORDERS ON ELECTRONIC FILE
93-0910 Additions and Alterations 0-003-005 05/03/94 NO CHANGE ORDERS ON ELECTRONIC FILE
92-1048 Reconstruction 0-003-006 05/17/93 NO CHANGE ORDERS ON ELECTRONIC FILE
94-0836 Reconstruction 0-003-007 02/22/95 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1153 Reconstruction 0-003-008 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1381 Reconstruction 0-003-009 07/26/99 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0408 Additions and Alterations 0-003-010 05/03/04 *CO No.* Amount Disallowed Received Approved Contractor
00 2,642 01/19/05 05/11/05 Murnane Building Co
004 14,835 12/01/06 01/09/07 Excel Insulation
004 -635 03/05/07 01/23/08 Weather Guard Roofing
004 7,988 03/05/07 03/13/07 Kasselman Electric
005 9,522 03/05/07 03/13/07 Kasselman Electric
007 3,056 03/09/07 04/25/07 Kasselman Electric
029 9,025 12/01/06 01/09/07 Murnane Building
034 -1,701 05/11/07 05/14/07 Murnane Building
07-0770 Reconstruction 0-003-011 06/24/08 NO CHANGE ORDERS ON ELECTRONIC FILE
07-0768 Reconstruction 0-003-012 06/13/08 NO CHANGE ORDERS ON ELECTRONIC FILE
02-0813FP Reconstruction 0-003-FP1 01/07/03 NO CHANGE ORDERS ON ELECTRONIC FILE
Industrial Arts Bus Garage:
98-1382 Reconstruction 0-006-005 07/26/99 NO CHANGE ORDERS ON ELECTRONIC FILE
Bus Garage:
97-1154 Reconstruction 5-004-001 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0409 Reconstruction 5-004-002 05/03/04 *CO No.* Amount Disallowed Received Approved Contractor
001 13,200 02/08/06 08/08/06 Weather Guard Roofing
Bus Repair/Training Center:
93-1727 New Construction 5-014-001 08/08/94 NO CHANGE ORDERS ON ELECTRONIC FILE
97-1155 Reconstruction 5-014-002 05/28/98 NO CHANGE ORDERS ON ELECTRONIC FILE
03-0410 Additions and Alterations 5-014-003 05/03/04 *CO No.* Amount Disallowed Received Approved Contractor
005 -2,500 12/01/06 12/27/06 Excel Insulation
009 13,467 07/11/05 07/25/05 urnane Building
Concession Stand/Storage Building:
91-0310 New Construction 7-013-001 10/04/91 NO CHANGE ORDERS ON ELECTRONIC FILE
District Wide:
97-1139 Reconstruction 7-999-001 03/24/98 NO CHANGE ORDERS ON ELECTRONIC FILE
98-1383 Reconstruction 7-999-002 07/26/99 NO CHANGE ORDERS ON ELECTRONIC FILE
99-1229 Reconstruction 7-999-003 04/29/00 NO CHANGE ORDERS ON ELECTRONIC FILE