Final Building Project Report Hints
The plans and specs have been delivered to the State Education Departments
Office of Facilities Planning. The paperwork is all in order. The Commissioners
Approval is issued and the school districts on their way to a successful
construction project. Just when you think youre finished with the project and the
Office of Facilities Planning, you realize its time to complete the Final Building Project
Report.
Here are some tips on how to ensure the timely processing of this final (and important)
stage of a capital construction project.
- Before mailing the Final Building Project Report to Facilities Planning, be sure that
the Report has been properly completed.
- Is the cover page signed and dated?
- Are the contract dates on the top of each page for which there is a contract?
- Are all change orders listed, including the SED approval date and the amount of addition
and/or deduction to the original contract?
- Have you indicated whether the contract has been completed and all expenditures have
been paid?
- Are all of the expenditures claimed in the Final Project Report relevant to the scope of
the project?
- Is the source of funds properly referenced on page 21?
- Are all expenditures noted on page 22?
- Attach a copy of the completed Certificate of Substantial Completion to the Final
Project Report.
- Has the Certificate of Substantial Completion been completed on the official State
Education Department form?
- Are all of the signatures in place (front and back)?
- Is the date of substantial completion noted on the form?
- If the actual project expenditures have exceeded the estimated costs on the SA-4, a
Request for Revision of Financial Information (FP-FI) form is required.
- Column A reflects the costs as they appeared on the SA-4.
- Column B shows any deletions or additions to the project totals, as well as any change
in the source of financing.
- Column C equals the new total cost of the project. (HINT: If the project cost has
exceeded the original SA-4 amount, the new total in Column C on the FP-FI should be
greater than or equal to the total on the Final Building Project Report.)
- Are all of the signatures in place on the bottom of the FP-FI?
- Have you attached the appropriate authorization documentation to increase and/or change
the source of funds? (This documentation shall be a copy of the board resolution if a city
school district; or if a noncity school district, a copy of the actual language of the
resolution which was placed before the voters at a special referendum; or a copy of the
Popular Budget, and a copy of the SBM-1, if the approval occurred at the annual meeting.)